ML19123A349
ML19123A349 | |
Person / Time | |
---|---|
Site: | Vogtle |
Issue date: | 05/01/2019 |
From: | George Khouri NRC/RGN-II |
To: | Nicole Coovert NRC/RGN-II |
George Khouri, RII/DCO | |
References | |
Download: ML19123A349 (10) | |
Similar Documents at Vogtle | |
---|---|
Category:Meeting Summary
MONTHYEARML24213A2462024-08-0505 August 2024
[Table view]Summary of Closed Meeting SNC Fleet - Physical Barriers Exemption ML24187A0012024-07-17017 July 2024 Summary of Observation Pre-Application Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Revise TS 3.3.8, Engineered Safety Feature Actuation System for Vogtle Electric ML24179A1592024-07-0202 July 2024 June 27, 2024, Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML24156A1772024-06-11011 June 2024 Summary of June 6, 2024, Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding the Physical Barrier Exemptions for Joseph M. Farley Nuclear Plant, Units 1 and 2, Edwin I. Hatch Nuclear Plant, Units 1 and 2, and Vogtle ML24149A0742024-06-0101 June 2024 Summary of May 29, 2024, Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding the Steam Generator Tube Inspection Report for Vogtle Electric Generating Plant, Unit 1 ML24122C6202024-05-0101 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 Docket Nos.. 50-424, 50-424, 52-025, and 52-026 Meeting Number 20240471 ML24108A0832024-04-19019 April 2024 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML24093A0612024-04-18018 April 2024 April 1, 2024, Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Proposed Alternative Requests to the Extend Examination Intervals for Joseph M. Farley Nuclear Plant and Vogtle ML24068A0962024-03-18018 March 2024 Summary of 3-7-24, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Co., Inc., Regarding a Proposed License Amendment Request for TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspection ML24025A1372024-01-31031 January 2024 Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23313A0952023-11-16016 November 2023 Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML23275A0882023-10-12012 October 2023 Summary of Meeting with Southern Nuclear Operating Company ML23272A1822023-10-11011 October 2023 Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML23121A1692023-05-12012 May 2023 Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves ML23115A3282023-05-10010 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML23090A1422023-04-0303 April 2023 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML23065A0732023-03-17017 March 2023 March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 ML23055A0902023-03-14014 March 2023 February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company ML23048A0682023-03-0101 March 2023 Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23037A0032023-02-0606 February 2023 Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company ML23012A0512023-01-17017 January 2023 January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company ML22336A0812022-12-0505 December 2022 Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22335A4922022-12-0202 December 2022 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22319A0132022-11-30030 November 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on November 10, 2022 ML22322A1672022-11-28028 November 2022 Summary of 11/15/2022 Public Meeting on Lessons Learned ML22271A0182022-10-0404 October 2022 Summary of Public Meeting with SNC on Lessons Learned Final ML22257A2362022-09-19019 September 2022 Summary of September 13, 2022, Partially Open and Partially Closed Pre-Submittal Meeting Held with SNC, Regarding a Proposed OLM License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22243A0302022-09-0909 September 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022 ML22145A6052022-06-0202 June 2022 Summary of May 24, 2022, Public Meeting with SNC, Regarding a Proposed Alternative Request for Performance-Based Leakage Test Frequencies for the Refueling Water Tank Suction Check Valves for Vogtle, Units 1 & 2 ML22145A4492022-05-27027 May 2022 Summary of May 23, 2022, Public Meeting with SNC, Regarding a Proposed License Amendment Request to Change Technical Specification 3.8.1 and Implement TSTF-163 for Vogtle Electric Generating Plant, Units 1 and 2 ML22131A3422022-05-18018 May 2022 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Requests to Implement Alternate Source Term, TSTF-51, TSTF-471, and TSTF-490 for Vogtle, Units 1 & 2 (EPID No. L-2022-LRM-0033 ML22132A0102022-05-17017 May 2022 Meeting of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding Proposed Accident Tolerant Fuel License Amendment Request and Exceptions for Vogtle Electric Generating Plant, Units 1 and 2 ML22123A0652022-05-0202 May 2022 Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 ML22098A1292022-04-26026 April 2022 Summary of March 31, 2022 Public Meeting with Southern Nuclear Operating Company ML22095A2292022-04-11011 April 2022 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML22077A5432022-04-0404 April 2022 Summary of Meeting with Southern Nuclear Operating Co ML22028A0462022-02-0101 February 2022 MTS - Meeting Summary - Pre-Submittal Meeting on January 27, 2022 - Vogtle ATF LAR and Exemption ML21337A0032021-12-0707 December 2021 Summary of Vogtle Readiness Group Public Meeting on December 2, 2021 ML21322A1502021-12-0202 December 2021 Summary of November 10, 2021 Public Meeting with Southern Nuclear Operating Company 2024-08-05 Category:Memoranda MONTHYEARML24122C6202024-05-0101 May 2024
[Table view]Public Meeting Summary - 2023 Annual Assessment Meeting Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 Docket Nos.. 50-424, 50-424, 52-025, and 52-026 Meeting Number 20240471 ML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report ML24004A2192024-01-0808 January 2024 Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML22348A0862023-07-25025 July 2023 Finding in Accordance with 10 CFR 52.103(G) That All Acceptance Criteria Are Met for Vogtle Electric Generating Plant, Unit 4 ML23115A0382023-05-0909 May 2023 Summary of Readiness Group Public Meeting on April 20, 2023 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML22214B4882023-02-0808 February 2023 Initial Commission Memo Regarding Status of ITAAC Closure, Inspection, and Licensing Activities for Vogtle Electric Generating Plant, Unit 4 ML22355A0322023-01-0303 January 2023 Revised Charter for the Vogtle Readiness Group to Oversee the Transition to Operations for Vogtle Units 3 and 4 ML22334A0812022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 ML22322A1672022-11-28028 November 2022 Summary of 11/15/2022 Public Meeting on Lessons Learned ML22237A0782022-08-0505 August 2022 American Nuclear Insurers, Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program ML20290A2812022-08-0101 August 2022 103g - Final Memorandum ML22123A0652022-05-0202 May 2022 Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 ML21337A0032021-12-0707 December 2021 Summary of Vogtle Readiness Group Public Meeting on December 2, 2021 ML21322A1502021-12-0202 December 2021 Summary of November 10, 2021 Public Meeting with Southern Nuclear Operating Company ML21316A0692021-11-22022 November 2021 November 4, 2021 Summary of Public Meeting with Southern Nuclear Operating Company ML21280A2962021-10-22022 October 2021 Replacement of Page 2 to Letter Dated June 30, 2020, Titled License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions (EPID L-2020-LLA0150) ML21230A0102021-08-24024 August 2021 Summary of Public Meeting with Southern Nuclear Operating Company on August 12, 2021 ML21194A0402021-07-20020 July 2021 Summary of June 24, 2021 Public Meeting with SNC ML21154A2772021-07-20020 July 2021 Summary of a Public Meeting with Southern Nuclear Operating Company on May 27, 2021 ML21190A0622021-07-16016 July 2021 Summary of July 8 2021 Public Meeting to Discuss Late-Filed Allegation Process for Vogtle Electric Generating Plant Units 3 and 4 ML21194A0392021-07-16016 July 2021 July 8, 2021 Summary of Public Meeting with Southern Nuclear Operating Company ML21124A2032021-05-0606 May 2021 ASME Alternative ALT-16 Pre-submittal Meeting Summary 4-29-21 ML21123A1432021-05-0505 May 2021 April 22, 2021, Summary of a Public Meeting with Southern Nuclear Operating Company ML20318A2422020-12-18018 December 2020 .72 50.73 Applicability Memo ML20351A2822020-12-10010 December 2020 Summary of Public Meeting with Southern Nuclear Operating Co ML20318A2412020-11-18018 November 2020 Summary of Public Meeting with Southern Nuclear Operating Company, to Discuss Topic Regarding Vogtle Electric Generating Plant, Unit 4: ITAAC Post Closure Notification for ITAAC Index Number 344 ML20303A0422020-11-0505 November 2020 Summary of October 22, 2020 Public Meeting with Southern Nuclear Operating Company NL-20-1262, Submission of Proposed Alternative to Submitting Vogtle Unit 2 Inservice Inspection Summary Report within 90 Days of Outage Completion2020-10-30030 October 2020 Submission of Proposed Alternative to Submitting Vogtle Unit 2 Inservice Inspection Summary Report within 90 Days of Outage Completion ML20296A2432020-10-15015 October 2020 Summary of 10-15-20 Public Meeting with Southern Nuclear Operating Company ML20283A4652020-10-15015 October 2020 Summary of Public Meeting on October 8, 2020 with Southern Nuclear Operating Company ML20279A5202020-10-0707 October 2020 October 1, 2020, Summary of Public Meeting with Southern Nuclear Operating Company ML20183A0902020-09-24024 September 2020 Initial Commission Memo Regarding Status of ITAAC Closure, Inspection, and Licensing Activities for Vogtle Electric Generating Plant, Unit 3 ML20262G9882020-09-22022 September 2020 September 17, 2020 Summary of Public Meeting with Southern Nuclear Operating Company ML20248H3292020-09-10010 September 2020 Meeting Summary for September 3, 2020 Public Meeting with Southern Nuclear Operating Company ML20247J4812020-09-10010 September 2020 Summary for August 27, 2020 Public Meeting with Southern Nuclear Operating Company ML20191A3832020-08-14014 August 2020 Transition to Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3 and 4 ML20216A6362020-08-10010 August 2020 Summary of a Public Meeting with Southern Nuclear Operating Company on July 23, 2020 ML20216A6252020-08-10010 August 2020 Summary of a Public Meeting with Southern Nuclear Operating Company on July 30, 2020 ML20205L4312020-07-29029 July 2020 Summary of a Public Meeting with Southern Nuclear Operating Company to Discuss Inspections, Tests, Analyses and Acceptance Criteria Nos. 375 and 216 ML20178A1302020-07-15015 July 2020 Memorandum Transmitting Safety Evaluation Regarding Welded Reinforcement Bar Splices at Vogtle Electric Generating Plant Units 3 and 4 ML20190A0182020-07-0808 July 2020 Summary of Meeting Regarding the Vogtle Readiness Group ML20168A3352020-06-26026 June 2020 Summary of June 11, 2020 Public Meeting with Southern Nuclear Operating Company ML20150A0092020-06-0202 June 2020 Summary of May 28, 2020 Public Meeting with Southern Nuclear Operating Company ML20154K7272020-06-0202 June 2020 EOC Meeting Summary ML20141L6182020-06-0101 June 2020 Summary of May 14, 2020 Public Meeting with Southern Nuclear Operating Company ML20141L6982020-05-26026 May 2020 Audit Report for Vogtle Electric Generating Plant Unit 3 LAR 20-001: Auxiliary Building Wall 11 Seismic Gap Requirements ML20133K1062020-05-15015 May 2020 Audit Plan for Vogtle Electric Generating Plant Units 3 and 4, Request for License Amendment: Core Makeup Tank Boron Concentration Requirements (LAR 20-004) 2024-05-01 Category:Slides and Viewgraphs MONTHYEARML24164A2942024-06-17017 June 2024
[Table view]Licensee Slides for Pre-submittal Meeting for VEGP Units 3 and 4 for a Proposed License Amendment Request Regarding TS 3.3.8 ML24158A3832024-06-0606 June 2024 SNC Slides - Vogtle 3 and 4 - TS 3-8-2 - Pre-Submittal Meeting - 06-27-2024 ML24120A2202024-04-30030 April 2024 Annual Assessment Meeting Presentation Slides - April 30, 2024 ML24089A1492024-04-0404 April 2024 Slides - SNC Presentation - Pre-Submittal Meeting on April 4, 2024 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML24060A2732024-03-0707 March 2024 SNC Slides - Pre-Submittal Meeting on March 7, 2024 - Vogtle 3 & 4 TSTF-577 LAR ML24022A1192024-01-24024 January 2024 Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML24004A1852024-01-0404 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised ML23304A2682023-11-0707 November 2023 License Amendment Request to Revise the Ultimate Heat Sink Mission Time Pre Submittal Meeting on November 7, 2023 ML23311A2452023-11-0707 November 2023 Pre-Submittal Meeting on November 7, 2023 - License Amendment Request to Revise the Ultimate Heat Sink Mission Time (Slides) ML23293A0052023-10-20020 October 2023 Lessons Learned from the ITAAC Hearing Process for Vogtle 3 and 4 ML23257A2322023-09-28028 September 2023 SNC Presentation - Pre-Submittal Meeting on September 28, 2023 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML23137A1162023-06-0202 June 2023 Draft Slides for Advisory Committee on Reactor Safeguards Subcommittee Meeting Regarding Use of Accident Tolerant Fuel Lead Test Assemblies ML23094A1402023-04-0404 April 2023 4 -- 2022 Aam Slides ML23072A1802023-03-13013 March 2023 2023 RIC Powerpoint Slide Presentation, Vogtle 3: Journey from Construction to Operations ML23055A0402023-02-24024 February 2023 VEGP, Unit 4, Potential License Amendment Request for Prior to Initial Criticality Overview Presentation ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22329A0192022-12-0101 December 2022 Southern Nuclear Company Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1 ML22335A5542022-12-0101 December 2022 Slides - SNC Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request - ML22332A0012022-11-28028 November 2022 SNC Slides - Pre-Submittal Meeting on November 30, 2022 - Vogtle TS 5.5.11 License Amendment Request ML22319A1232022-11-15015 November 2022 Kozak Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22319A0052022-11-15015 November 2022 NEI Slides for November 15 2022 Public Meeting on Part 52 Lessons Learned ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22251A0002022-09-30030 September 2022 Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR ML22265A0972022-09-22022 September 2022 Southern Nuclear Company Slides on Lessons Learned from Part 52 Implementation for Public Meeting on 9/27/2022 ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22206A1712022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1682022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22201A0442022-07-20020 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 20, 2022 ML22144A0492022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22144A0502022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22138A3952022-05-24024 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 24, 2022 - Vogtle RR RWST Suction Check Valves ML22137A2812022-05-23023 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 23, 2022 - Vogtle TS 3.8.1 and TSTF-163 LAR ML22126A0102022-05-11011 May 2022 Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemption Requests - Licensing Questions ML22123A3332022-05-10010 May 2022 Pre-Submittal Meeting 2: TSTF-51, TSTF-471, TSTF-490, and Alternative Source Term License Amendment Request - May 10, 2022 (EPID L-2022-LRM-0033)(slides) ML22126A0012022-05-0606 May 2022 SNC Slides - Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemptions ML22110A1702022-04-20020 April 2022 4 2022 Annual Assessment Meeting.Final ML22060A0062022-02-28028 February 2022 4Q 2021 Performance Summary U3 ML22021B6472022-01-27027 January 2022 Pre-Submittal for Westinghouse Increased Enrichment Accident Tolerant Fuel Lead Test Assemblies (EPID L-2022-LRM-0003) (Slides) ML22026A0582022-01-26026 January 2022 Dashboard Report 1-26-2022 ML21306A0242021-11-30030 November 2021 SNC Pre-Submittal Meeting for LAR to Relocate Augmented Piping Inspection Program Details from TSs to a Licensee Controlled Document for Farley Nuclear Plant, Units 1 & 2; and Vogtle Electric Generating Plant, Units 1 & 2 (EPID L-2021-LRM-0 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21230A2842021-08-18018 August 2021 SNC Slides - Vogtle MSIV Elimination LAR - Pre-submittal Meeting Part 2 - 08-25-2021 ML21197A0032021-08-0606 August 2021 Slides - SNC Slides - Pre-Submittal Meeting on August 13, 2021 - Vogtle TS 3.3.1 and 3.3.2 LAR ML21187A0972021-07-0808 July 2021 Late Filed Allegations (Lfa) Process ML21193A0762021-07-0808 July 2021 ITAAC Related to Incore Instrument Thimble Assembly (Iita) ML21188A3592021-07-0606 July 2021 1Q 2021 Performance Summary U3 ML21188A3612021-07-0606 July 2021 1Q 2021 Performance Summary U4 2024-06-06 |
Contents
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 1, 2019 MEMORANDUM TO: Nicole Coovert, Chief Division of Construction Oversight Inspection Branch 1 FROM: George Khouri, Senior Construction Engineer /RA/
Division of ConstructionOversight Inspection Branch 1
SUBJECT:
PUBLIC MEETING
SUMMARY
- VOGTLE ELECTRIC GENERATING PLANT, DOCKET NOS. 05200025 AND 05200026 On April 25, 2019, the Nuclear Regulatory Commission (NRC) staff met with members of the public concerning the annual assessment of Vogtle Electric Generating Plant, Units 3 and 4, in Waynesboro, Georgia. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Vogtle Electric Generating Plant, Units 3 and 4, for the period of January 1, 2018 - December 31, 2018. Enclosed are a list of attendees and a copy of the poster boards displayed at the meeting.
Docket Nos. 05200025 and 05200026
Enclosures:
- 1. List of Attendees
- 2. Poster Boards CONTACT: George Khouri, RII/DCO/B1 404-997-4457
ML19123A349 OFFICE RII:DCO NAME G. Khouri DATE 5/ 1/2019