MONTHYEARML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request ML23279A2082023-10-0505 October 2023 Issuance of Formal RAIs - Vogtle, Units 1 and 2 - Proposed LAR and Proposed Alternative Request to Revise TS 3.4.14.1 and IST ALT-VR-02 (EPIDs L-2023-LLA-0061 and L-2023-LLR-0023) ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time ML23270B1912023-09-27027 September 2023 COL Docs - Update Vogtle Units 3&4 Acceptance Letter for LAR-22-002 Technical Specification 3.8.3, Inverters Operating ML23263A1042023-09-20020 September 2023 COL Docs - FW Fyi for Tomorrow'S Psm Meeting ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23257A0632023-09-13013 September 2023 NRR E-mail Capture - Acceptance Review of Southern Nuclear Operating Company'S License Amendment Request to Remove Combined License Appendix C ML23256A2682023-09-13013 September 2023 COL Docs - Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23248A3482023-09-0505 September 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 6 - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9172023-08-31031 August 2023 NRR E-mail Capture - (External_Sender) Re Question - Legal Contact(S) for Vogtle Electric Generating Plant, Units 3 & 4 ML23241A0452023-08-29029 August 2023 COL Docs - FW Draft LAR and Exemption Request Regarding Tier 1 and Tier 2 Requirements ML23229A2322023-08-17017 August 2023 COL Docs - FW Re LAR 22-002 Second Round RAI Approved ML23188A151 for Vogtle Units 3 & 4 ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23221A3982023-08-0909 August 2023 COL Docs - LAR 22-002 Second Round RAI Approved ML23188A151 ML23216A1592023-08-0404 August 2023 COL Docs - FW Acceptance Review - Requested Licensing Action Regarding TS Revision to Adopt WCAP-17661-P-A, Improved Relaxed Axial Offset Control and Constant Axial Offset Control Fq Surveillance TS (L-2022-LLA-0148 and L-2022-LLA-0149) ML23212A9642023-07-31031 July 2023 COL Docs - Action - Start of Annual Fees - Vogtle Unit 3 Completion of Power Ascension Testing and Declaration of Commercial Operations ML23216A0962023-07-26026 July 2023 Document Request for Vogtle 1 & 2 RP Inspection, Report No. 05000424/2023003 and 05000425/2023003 ML23220A0572023-07-26026 July 2023 Document Request for Vogtle Units 1 and 2 - Radiation Protection Inspection - Inspection Report 2023-03 ML23200A0112023-07-18018 July 2023 Document Request for Vogtle Unit 3 RP Inspection ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23193A7832023-07-12012 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) 2024-01-31
[Table view] |
Text
Vogtle PEmails From: Habib, Donald Sent: Tuesday, March 26, 2019 2:19 PM To: Chamberlain, Amy Christine Cc: Vogtle PEmails; Stutzcage, Edward; Dudek, Michael; Dixon-Herrity, Jennifer; Patel, Chandu; Ray, Sheila
Subject:
NRC Feedback from Today's Public Meeting (Vogtle Planned LAR on AP1000 Radiation Reconciliation)
Amy -
Below is additional NRC feedback from todays public meeting discussion about the planned LAR for detailed AP10000 radiation reconciliation.
Don Habib U.S. Nuclear Regulatory Commission Office of New Reactors Project Manager NRO/DLSE, Licensing Branch 2 O-8D13 301-415-1035 NRC Takeaway #1 -
Design basis radiation sources over 100 millicuries, that are associated with a component which is part of the plant design and requires radiation shielding and/or radiation protection controls, are included in the application. Specifically, NRC SRP Section 12.2 states, Descriptions should be provided for all radiation sources that require (1) shielding, (2) special ventilation systems, (3) special storage locations and conditions, (4) traffic or access control, (5) special plans or procedures, or (6) monitoring equipment. The source descriptions should include all pertinent information required for (1) input to shielding codes used in the design process, (2) establishment of related facility design features, (3) development of plans and procedures, (4) assessment of occupational exposure and (5) determination of radiation dose to electrical equipment important to safety as described in 10 CFR 50.49. Unless described within other sections of the SAR, source descriptions should include the methods, models and assumptions used as the bases for all values provided in SAR Section 12.2. A listing of isotope, quantity, form, and use of all required radiation sources containing byproduct, source, and special nuclear material exceeding 3.7 E+9 Bq (100 millicuries) that may warrant shielding design consideration, should be provided.
NRC Takeaway #2 -
The basis for requesting this information includes several regulations, including 10 CFR 52.47(a)(5) (for DCDs) and 10 CFR 52.79(a)(3) (for COLs), which requires that applications contain the kinds and quantities of radioactive materials expected to be produced in the operation and the means for controlling and limiting radioactive effluents and radiation exposure within the limits set forth in Part 20 of this chapter.
NRC Additional Suggestions -
In addition, the NRC staff identifies that the LAR should also discuss if there is a need for any inspections or work inside the tank; and any impacts on worker dose and worker dose estimates (depending how the worker 1
dose estimates in FSAR Section 12.4 were performed and the consideration of the radioactivity in the IRWST for how it may impact those numbers). This should also include whether there are any special radiation protection design features or controls associated with reducing the dose rate in and around the tank or reducing radiation exposure to workers in or around the tank.
2
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 435 Mail Envelope Properties (SN4PR0901MB2175A1044200F4AF00FA2C63975F0)
Subject:
NRC Feedback from Today's Public Meeting (Vogtle Planned LAR on AP1000 Radiation Reconciliation)
Sent Date: 3/26/2019 2:19:02 PM Received Date: 3/26/2019 2:19:05 PM From: Habib, Donald Created By: Donald.Habib@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None "Stutzcage, Edward" <Edward.Stutzcage@nrc.gov>
Tracking Status: None "Dudek, Michael" <Michael.Dudek@nrc.gov>
Tracking Status: None "Dixon-Herrity, Jennifer" <Jennifer.Dixon-Herrity@nrc.gov>
Tracking Status: None "Patel, Chandu" <Chandu.Patel@nrc.gov>
Tracking Status: None "Ray, Sheila" <Sheila.Ray@nrc.gov>
Tracking Status: None "Chamberlain, Amy Christine" <ACCHAMBE@southernco.com>
Tracking Status: None Post Office: SN4PR0901MB2175.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2808 3/26/2019 2:19:05 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: