MONTHYEARND-18-1037, Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021)2018-08-10010 August 2018 Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021) Project stage: Request ML18241A2452018-08-29029 August 2018 COL Docs - LAR 18-021 Post-Submittal Presentation Project stage: Approval ML18243A0332018-08-31031 August 2018 COL Docs - Vogtle LAR-18-021 PORV Noise Mitigation - Acceptance Letter Project stage: Request ML18243A4922018-09-17017 September 2018 Summary of Public Meeting Held on August 30, 2018 (LAR-18-021) Project stage: Request ND-18-1277, Revision to Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021R1)2018-10-11011 October 2018 Revision to Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021R1) Project stage: Request ND-18-1332, Preliminary Amendment Request (Par): Power Operated Relief Valve (PORV) Noise Mitigation (PAR-18-021)2018-10-19019 October 2018 Preliminary Amendment Request (Par): Power Operated Relief Valve (PORV) Noise Mitigation (PAR-18-021) Project stage: Other ML18299A2762018-10-30030 October 2018 Notice of No Objection for Preliminary Amendment Request, Power Operated Relief Valve (PORV) Noise Mitigation (PAR-18-021), for the Vogtle Electric Generating Plant Units 3 and 4 Project stage: Other ML18313A0052018-11-0909 November 2018 COL Docs - Vogtle LAR-18-021 Final Audit Plan on Power Operated Relief Valve Noise Mitigation Project stage: Request ND-19-0127, Supplement to Revision to Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021R1S1)2019-02-15015 February 2019 Supplement to Revision to Request for License Amendment and Exemption: Power Operated Relief Valve (PORV) Noise Mitigation (LAR-18-021R1S1) Project stage: Supplement ML19065A2392019-03-12012 March 2019 Us NRC Audit Report Related to Vogtle Electric Generating Plant, Units 3 and 4 License Amendment Request (LAR) 18-021 Power Operated Relief Valve Noise Mitigation Project stage: Approval ML19063A8932019-04-18018 April 2019 Attachment - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 4, Amendment 157 Project stage: Approval ML19063A8922019-04-18018 April 2019 Amendment No. 157 - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 4 Project stage: Approval ML19063A8912019-04-18018 April 2019 Attachment - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 3, Amendment 159 Project stage: Approval ML19063A8902019-04-18018 April 2019 Amendment No. 159 - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 3 Project stage: Approval ML19063A8892019-04-18018 April 2019 Exemption - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 4 Project stage: Approval ML19063A8882019-04-18018 April 2019 Exemption - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 3 Project stage: Approval ML19063A8872019-04-18018 April 2019 Cover Letter - Vogtle Electric Generating Plant Units 3 and 4 (LAR-18-021) PORV Relief Valve Noise Mitigation, Amendments 159 & 157 Project stage: Approval ML19063A8862019-04-18018 April 2019 Issuance of Amendments and Granting of Exemptions Power Operated Relief Valve Noise Mitigation (LAR 18-021) Project stage: Request ML19063A8942019-04-18018 April 2019 Safety Evaluation - Vogtle Electric Generating Plant Units 3 and 4 (LAR-18-021) PORV Relief Valve Noise Mitigation, Amendments 159 and 157 Project stage: Approval 2018-08-29
[Table View] |
Text
ATTACHMENT TO LICENSE AMENDMENT NO. 159 TO FACILITY COMBINED LICENSE NO. NPF-91 DOCKET NO.52-025 Replace the following pages of the Facility Combined License No. NPF-91 with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Facility Combined License No. NPF-91 REMOVE INSERT 7
7 Appendix C to Facility Combined License No. NPF-91 REMOVE INSERT C-101 C-101 C-164 C-164 C-165 C-165
(7) Reporting Requirements (a)
Within 30 days of a change to the initial test program described in UFSAR Section 14, Initial Test Program, made in accordance with 10 CFR 50.59 or in accordance with 10 CFR Part 52, Appendix D, Section VIII, Processes for Changes and Departures, SNC shall report the change to the Director of NRO, or the Directors designee, in accordance with 10 CFR 50.59(d).
(b)
SNC shall report any violation of a requirement in Section 2.D.(3),
Section 2.D.(4), Section 2.D.(5), and Section 2.D.(6) of this license within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Initial notification shall be made to the NRC Operations Center in accordance with 10 CFR 50.72, with written follow up in accordance with 10 CFR 50.73.
(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 159, are hereby incorporated into this license.
(9) Technical Specifications The technical specifications in Appendix A to this license become effective upon a Commission finding that the acceptance criteria in this license (ITAAC) are met in accordance with 10 CFR 52.103(g).
(10) Operational Program Implementation SNC shall implement the programs or portions of programs identified below, on or before the date SNC achieves the following milestones:
(a)
Environmental Qualification Program implemented before initial fuel load; (b)
Reactor Vessel Material Surveillance Program implemented before initial criticality; (c)
Preservice Testing Program implemented before initial fuel load; (d)
Containment Leakage Rate Testing Program implemented before initial fuel load; (e)
Fire Protection Program
- 1.
The fire protection measures in accordance with Regulatory Guide (RG) 1.189 for designated storage building areas (including adjacent fire areas that could affect the storage area) implemented before initial receipt 7
Amendment No. 159
C-101 Amendment No. 159 Figure 2.2.1-1 Containment System
C-164 Amendment No. 159 Figure 2.2.4-1 (Sheet 1 of 3)
Steam Generator System
C-165 Amendment No. 159 Figure 2.2.4-1 (Sheet 2 of 3)
Steam Generator System