MONTHYEARML22250A4722023-04-17017 April 2023 DG 5079 (RG 5.83 Rev 1) Regulatory Analysis ML21155A0042021-07-22022 July 2021 Regulatory Analysis for Regulatory Guide 1.29, Seismic Design Classification for Nuclear Power Plants ML20168A8932021-04-0101 April 2021 Regulatory Analysis for DG-1371, Proposed Revision 6 of RG 1.26, Quality Group Classifications and Standards for Water-, Steam-, and Radioactive-Waste-Containing Components of Nuclear Power Plants ML20192A2302020-12-10010 December 2020 Regulatory Analysis for DG 1361 RG 1.89 Revision 2 RA - Environmental Qualification of Certain Electrical Equipment Important to Safety for Nuclear Power Plants ML20282A2992020-12-0404 December 2020 Regulatory Analysis for DG-3055, Rev 0, Regulatory Guide (RG) 3.76, Implementation of Aging Management Requirements for Spent Fuel Storage Renewals ML20210M0442020-10-28028 October 2020 Regulatory Analysis: Draft Regulatory Guide DG-1288 - an Approach for Plant-Specific, Risk-Informed Decisionmaking for Inservice Inspection of Piping (Proposed Revision 2 of Regulatory Guide 1.178, Dated September 2003) ML20195A1742020-09-17017 September 2020 Regulatory Analysis ML20055G8242020-08-0707 August 2020 Regulatory Analysis for DG 1363 for Rev 4 to Regulatory Guide (RG) 1.105 - Setpoints for Safety-Related Instrumentation ML20078K9252020-08-0505 August 2020 Regulatory Analysis for DG-1370 Proposed Revision 1 of Regulatory Guide (RG) 1.191, Titled, Fire Protection Program for Nuclear Power Plants During Decommissioning ML20034F2542020-07-0101 July 2020 Reg Guide 7.4 New Reg Analysis-Leakage Tests on Package for Shipment of Radioactive Material ML20105A2162020-07-0101 July 2020 Regulatory Analysis for DG-1372, Rev 4 of RG 1.136 Design Limits, Loading Combinations, Materials, Construction and Testing of Concrete Containments ML14161A6242020-02-12012 February 2020 Regulatory Analysis for Draft Regulatory Guide 3036 ML19213A3432019-09-30030 September 2019 Draft Regulatory Analysis (DG)-1341 - Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses ML19108A4622019-07-31031 July 2019 Regulatory Analysis ML19045A4322019-05-31031 May 2019 Draft Regulatory Guide DG-1356 (Rg 1.187 Rev 2), Guidance for Implementation of 10CFR50.59 Changes, Tests and Experiments - Regulatory Analysis ML19042A1832019-03-31031 March 2019 Regulatory Analysis ML18093A6762019-02-28028 February 2019 DG-1328 Regulatory Analysis ML18158A3012019-01-31031 January 2019 Regulatory Analysis DG-1352 ML18087A1672018-10-31031 October 2018 DG-4019 Reg Analysis ML18016A1302018-08-31031 August 2018 Regulatory Anlaysis DG-5061 ML18086A6852018-06-30030 June 2018 DG-1351 RA ML16358A1562017-03-31031 March 2017 DG-1285 Regulatory Analysis ML15237A3852015-12-0707 December 2015 Regulatory Analysis for DG-4025 ML14310A3382015-09-0303 September 2015 Regulatory Analysis for DG-5049 ML14119A2822015-06-24024 June 2015 Regulatory Analysis DG-1305 ML14356A2472015-04-10010 April 2015 Regulatory Analysis for DG-1314 ML14218A8612014-11-18018 November 2014 Regulatory Analysis, Draft Regulatory Guide DG-5036, Fitness for Duty Programs at New Reactor Construction Sites ML14139A3202014-06-27027 June 2014 Regulatory Analysis for Rg 3.75, Corrective Action Programs for Fuel Cycle Facilities (Proposed New Regulatory Guidance) ML13144A8422013-10-0404 October 2013 Regulatory Analysis for Draft Regulatory Guide 1271 ML12300A3282013-10-0404 October 2013 Regulatory Analysis for Rg 1.79.1, Initial Test Program of Emergency Core Cooling Systems for Boiling-Water Reactors, (Draft Was Issued as DG-1277, Dated June 2012) ML13140A0392013-06-27027 June 2013 Regulatory Analysis for DG-1272, Standard Format and Content for Post-Shutdown Decommissioning Activities Report ML12228A5912012-11-15015 November 2012 Reg Analysis to DG-1294, Pre-Operational Testing of Onsite Electric Power Systems to Verify Proper Load Group Assignments, Electrical Separation, and Redundancy ML12220A0442012-09-21021 September 2012 Regulatory Analysis to Rg 1.92, Rev. 3 Combining Modal Responses and Spatial Components in Seismic Response Analysis. ML12013A0892012-05-31031 May 2012 Regulatory Analysis for DG-1285 ML1035104582012-04-30030 April 2012 Regulatory Analysis to Regulatory Guide 1.218 ML1023803112011-12-31031 December 2011 Regulatory Analysis for DG-4021, General Site Suitability Criteria for Nuclear Power Stations ML1121600132011-10-31031 October 2011 Regulatory Analysis to Rg 1.159, Rev. 2 ML1121016102011-08-0505 August 2011 Guidance for the Assessment of Beyond-Design-Basis Aircraft Impacts (Draft Was Issued as DG-1176 Dated July 2009) (New Regulatory Guide) ML1101300462011-08-0505 August 2011 Regulatory Analysis for DG-4016, Terrestrial Environmental Studies for Nuclear Power Stations (Proposed Revision 2 of Regulatory Guide 4.11, Dated August 1977) ML1033706592011-04-30030 April 2011 Regulatory Analysis, Regulatory Guide 3.67, Standard Format and Content for Emergency Plans for Fuel Cycle and Materials Facilities ML1018005172010-12-31031 December 2010 Regulatory Analysis for Rg 5.80, Pressure-Sensitive and Temper-Indicating Device Seals for Material Control and Accounting of Special Nuclear Material. ML1017203112010-12-15015 December 2010 Regulatory Analysis to Regulatory Guide 4.16, Revision 2 ML1027203352010-10-0404 October 2010 Regulatory Analysis to DG-1196, Qualification for Cement Grouting for Prestressing Tendons in Containment Structures ML1017403272010-08-31031 August 2010 Draft Regulatory Guide 1228, (Revision 1 of Regulatory Guide 1.179), Standard Format and Content of License Termination Plans for Nuclear Power Reactors (Regulatory Analysis) ML1018900472010-07-31031 July 2010 Regulatory Analysis to Regulatory Guide 1.216 Containment Structural Integrity Evaluation for Internal Pressure Loadings Above Design-Basis Pressure. ML1015403482010-06-17017 June 2010 Regulatory Analysis on Rg 1.62, Manual Initiation of Protective Actions, Revision 1 ML1013203172010-06-14014 June 2010 Regulatory Analysis for Revision 3 of Regulatory Guide 1.152 2023-04-17
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
REGULATORY ANALYSIS DRAFT REGULATORY GUIDE DG-1356 GUIDANCE FOR IMPLEMENTATION OF 10 CFR 50.59 CHANGES, TESTS, AND EXPERIMENTS (Proposed Revision 2 of Regulatory Guide 1.187)
- 1. Statement of the Problem The U.S. Nuclear Regulatory Commission (NRC) is considering revising Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59 Changes, Tests, and Experiments to endorse, with exceptions, industry guidance to comply with the requirements of 10 CFR 50.59 when performing a digital instrumentation and control modification.
Specifically, NRC inspections of documentation for digital instrumentation and control (I&C) plant modifications that some licensees have prepared using guidance in NEI 01-01, Electric Power Research Institute (EPRI) TR-102348, Revision 1, Guideline on Licensing Digital Upgrades (ADAMS Accession No. ML020860169), identified inconsistencies in the performance and documentation of some licensees engineering evaluations. Additionally, in response to Staff Requirements Memorandum (SRM)-SECY-16-0070 Staff Requirements-SECY-16-0070-Integrated Strategy to Modernize the Nuclear Regulatory Commissions Digital Instrumentation and Control Regulatory Infrastructure (ML16299A157), the NRC staff has engaged the public, NEI, and industry representatives to improve the guidance for applying 10 CFR 50.59 to digital I&C-related design modifications as part of a broader effort to modernize the NRCs regulatory infrastructure for I&C. This proposed revision to RG 1.187 will improve 10 CFR 50.59 guidance for digital I&C-related design modifications.
The objectives of 10 CFR 50.59 are to ensure that licensees evaluate proposed changes to their facilities for their effects on the licensing basis of the plant, as described in their updated final safety analysis reports, and obtain prior NRC approval for changes that meet specified criteria as having a potential impact upon the basis for issuance of the operating license. This draft guide proposes to endorse, with exceptions, the principles in Nuclear Energy Institute (NEI) 96-07, Appendix D, Supplemental Guidance for Application of 10 CFR 50.59 to Digital Modifications, which describes approaches to address challenges concerning digital technology implementation under 10 CFR 50.59.
- 2. Objective The objective of this regulatory action is to update NRC guidance and provide licensees with an approach to demonstrate compliance with the 10 CFR 50.59 requirements for digital instrumentation and control modifications.
- 3. Alternative Approaches The NRC staff considered the following alternative approaches:
- 1. Do not revise Regulatory Guide 1.187, Revision 1
- 2. Withdraw RG 1.187, Revision 1
- 3. Revise Regulatory Guide 1.187, Revision 1
Alternative 1: Do Not Revise Regulatory Guide 1.187 Under this alternative, the NRC would not revise or issue additional guidance, and the current guidance would be retained. By letter dated November 5, 2013 (ADAMS Accession No. ML13298A787), the NRC staff indicated that the current industry guidance for 10 CFR 50.59 screening and evaluation of digital I&C systems was inadequate, and contributed to several licensees having improperly performed 10 CFR 50.59 evaluations for modifications of I&C systems using digital technologies. If NRC does not take action, NEI 96-07, Appendix D would not be endorsed by the NRC and the industry would be left with potential regulatory uncertainty when conducting digital I&C modifications.
Alternative 2: Revise Regulatory Guide 1.187 Under this alternative, the NRC would withdraw this RG. Withdrawal of the guide would eliminate the important guidance already provided to industry regarding the implementation of 10 CFR 50.59, which allows licensees to make changes to their facilities and procedures as describe in the FSAR, without prior NRC approval. It would also eliminate the only readily-available description of the methods the NRC considers acceptable for demonstrating compliance with 10 CFR 50.59.
Alternative 3: Revise Regulatory Guide 1.187 Under this alternative, the NRC would revise Regulatory Guide 1.187. This revision would endorse, with exception and clarifications, NEI 96-07, Appendix D as an acceptable approach for screening criteria when conducting digital I&C modifications. The impact to the NRC would be the costs associated with preparing and issuing the regulatory guide revision.
The impact to the public would be the voluntary costs associated with reviewing and providing comments to NRC during the public comment period. The value to NRC staff and its licensees would be the benefits associated with enhanced efficiency and effectiveness in using a common guidance document as the technical basis for implementing 10 CFR 50.59 for digital I&C modifications. It would also reduce current regulatory uncertainty in conducting digital I&C modifications and result in a state in which the nuclear power industry can perform digital upgrades under the 10 CFR 50.59 licensing process.
- 4. Conclusion Based on this regulatory analysis, the NRC staff concludes that revision of Regulatory Guide 1.187 is warranted. The action will enhance reactor safety by giving guidance for digital I&C modifications. It could also lead to cost savings for the industry, especially with regard to the use of digital equipment, while improving regulatory predictability.