ML19044A390

From kanterella
Jump to navigation Jump to search

Acceptance Review of Notice of General Electric Parent Company Guarantee of Funds for Decommissioning
ML19044A390
Person / Time
Site: Vallecitos Nuclear Center, 07000754, 07001113, 07200001, Vallecitos
Issue date: 02/21/2019
From: Ty Naquin
NRC/NMSS/DFCSE/FLB
To: Murray S
Global Nuclear Fuel
Naquin T
References
EPID L-2019-LNS-0002
Download: ML19044A390 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 21, 2019 Mr. Scott P. Murray, Manager Licensing and Liabilities Global Nuclear Fuel - Americas 3901 Castle Hayne Road P.O. Box 780 - M/C K-84 Wilmington, NC 28401

SUBJECT:

ACCEPTANCE REVIEW OF NOTICE OF CANCELLATION FROM CHIEF FINANCIAL OFFICER OF GENERAL ELECTRIC COMPANY PARENT GUARANTEE OF FUNDS FOR DECOMMISSIONING (ENTERPRISE PROJECT IDENTIFIER L-2019-LNS-0002)

Dear Mr. Murray:

By letter dated January 7, 2019 (Agencywide Documents Access and Management System

[ADAMS] Accession Number ML19014A161), you provided a notice of cancellation of General Electric Company (GE) Parent Guarantee of Funds for Decommissioning.

The U.S. Nuclear Regulatory Commission (NRC) staff has performed an acceptance review of your submittal to determine if the application contains sufficient technical information to allow the NRC staff to conduct the detailed technical review. Based on this review, completed February 11, 2019, the NRC staff concludes the submittal contains information in sufficient detail to enable the staff to conduct its detailed review. Accordingly, the NRC staff has established a schedule for this review which includes the issuance of requests for additional information (RAIs) by March 15, 2019. The NRC staff anticipates completing its review and developing a Safety Evaluation Report to address the submittal by the end of April 2019 or 4 weeks after adequate response to any RAIs, if any. In addition, the NRC staff estimates that completing the review and making an independent assessment of the proposed application will require approximately 20 staff hours.

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

S. Murray 2 If you have any questions, feel free to contact Tyrone Naquin at (301) 415-7352, or via e-mail to Tyrone.Naquin@nrc.gov.

Sincerely,

/RA/

Tyrone D. Naquin, Project Manager Fuel Facility Licensing Branch Division of Fuel Cycle, Safety, Safeguards, and Environmental Review Office of Nuclear Material Safety and Safeguards Docket Nos.:

70-1113, 70-0754, 72-0001 50-018,50-070, 50-073, 50-183 License Nos:

SNM-1097, SNM-960, SNM-2500 DR-1, TR-1, DPR-1, R-33

S. Murray 2

SUBJECT:

ACCEPTANCE REVIEW OF NOTICE OF CANCELLATION FROM CHIEF FINANCIAL OFFICER OF GENERAL ELECTRIC COMPANY PARENT GUARANTEE OF FUNDS FOR DECOMMISSIONING (ENTERPRISE PROJECT IDENTIFIER L-2019-LNS-0002)

DATED: February 21, 2019 DISTRIBUTION: FCSE r/f CMckenney/PAB T.Grice/RII ADAMS Accession Number: ML19044A390

  • via email OFC FCSE/FFLB FCSE/FFLB FCSE/FFLB FCSE/FFLB NAME TNaquin TBrockington JZimmerman TNaquin DATE 02/ 13 /2019 02/14/2019 02/15/2019 02/21/2019 OFFICIAL RECORD COPY