Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201/622-7000 Director of Nuclear Reactor R U.S. Nuclear Regulatory Comm' Washington, D.C.
20555 Attention:
Mr~ Karl Kniel, Light Water Rea Gentlemen:
DOCKET NO. 50-272 SALEM GENERATING STATION UNIT NO. 1 September 7, 1976 FACILITY OPERATING LICENSE REQUEST FOR AMENDMENT DPR-70
.,,..,,,-*,-*- ***-**,.,,.-"7°'"'";':::>..,0.,,
l it
We have reviewed the attachment to license No. DPR-70 which identi-fies certain preoperational tests, startup tests, and other items which were to be deferred at the time of core load but to be satis-factorily completed prior to proceeding to certain specified oper-ational modes.
The attachment, as written, makes it impossible to accomplish certain tests required to be complete prior to proceed-ing from Operational Mode 4 (hot shutdown) to Mode 3 (hot standby) because of coolant temperature limitations in Mode 4.
We hereby request that Attachment 1 to the license be amended to allow startup *to proceed in an orderly fashion.
The required changes are enclosed for your consideration.
The requested changes involve the order of test completion for five (5) tests and the sequence of testing the snubbers.
It deletes the test requirement for snubbers on the feedwater system and for Maintenance Proce-dures required for operation since these are outside the scope of this license.
The changes made in this Amendment do not alter the evaluations and determinations made by PSE&G that there will be no adverse effect on the health and safety of the public or station personnel as the result of deferral of these items.
91-92 The Energy People
\\,
95-2001 300M 8* 75
, 9-7-76 Additional copies of this request for a license amendment as re-quired by 10CFR 50.90 will be submitted separately.
Sinqerely yours,
-*1/J Sr*
-r (.
Frank I,-. Librizzi:
General Manager -
Electric Production
ATTACHMENT 1 TO LICENSE DPR-70 Incomplete Preoperational Tests, Startup Tests, and Other Items Which Must Be Completed This attachment identifies certain preoperational tests, startup tests, and other items which must be completed to the Commission's satisfaction prior to proceeding to certain specified Operational Modes.
Public Service Electric and Gas Company shall not proceed beyond the authorized Operational Modes without prior written authorization from the Commission.
A.
Public Service Electric and Gas Company may at the license issue date proceed directly to Operational Mode 6 (initial fuel loading), and may subsequently proceed to Operational Mode 5 (cold shutdown)
- B.
Prior to proceeding to Operational Mode 4 (hot shutdown),
Public Service Electric and Gas Company shall test the response times of primary sensors in the reactor coolant system per SUP 20.1.
Subsequent to the verification by the Office of ~Inspection and Enforcement of the acceptable completion of this item, and upon written authorization by the Commission, Public Service Electric and Gas Company may proceed to Operational Mode 4 (hot shutdown).
C.
Prior to proceeding to Operational Mode 3 (hot standby), Public Service Electric and Gas Company shall complete the following items:
- 1.
Testing operation ::: of RHR pump recirculation valves 11RH29 and 12RH29 per SUP 50.0.
- 2.
Testing motor winding temperatures of RHR pump motors Nos. 11 and 12 per SUP 12.
- 3.
Testing the following snubbers per SUP 50.4:
RHRH ll-29A RHRH ll-29B RHRH 12-34B RHRH 12-34C
- 4.
Testing the boron recycle system per SUP 10.5.
- 5.
Demonstrate beta dosimetry capability.
- 6.
Testing process radiation monitors, excluding those required for fuel loading, per SUP 21.
I 1*-**
I I :
STATE OF NEW JERSEY
)
SS.:
COUNTY OF ESSEX FREDERICK W. SCHNEIDER, being first duly sworn, deposes and says:
That he is the Vice President -
Production of Public*
Service Electric and Gas Company, the Applicant herein; that he has read the foregoing amendment and knows the contents thereof, and that the statements and matters set forth therein are true and correct to the best of his knowledge, information and belief.
Sworn and subscribed to before me this 10th day of September, 1976
~~
ANNA SCHAPER
. NOTARY PUBLIC OF NEW JERSEY My Commission Expires Apr. 8, 1980
/