Post Fukushima Seismic and Flood Hazard Reevaluation Status 2019-01-07
ML19011A372
Person / Time
Issue date: 01/07/2019
From: Robert Bernardo
Beyond-Design-Basis Management Branch
To:
Bernardo J, NRR/DLP, 415-2621
References
Download: ML19011A372 (3)


Text

January 7, 2019 Post Fukushima Flooding and Seismic Hazard Reevaluation Status Flooding Hazard Reevaluation

- The licensees for all operating power reactor sites have completed their hazard reevaluation and have submitted their Flood Hazard Reevaluation Reports (FHRR).

- The NRC used a graded approach to address flood hazard results that exceed the current design basis.

- The NRC expects that the licensees for 47* operating reactor sites will submit a focused evaluation (FE) to address local intense precipitation and to leverage available physical margin. The licensees for 43 operating reactor sites have provided their focused evaluations. The NRC expects the remaining FEs to be submitted by mid-2019.

- The NRC expects that the licensees for five operating power reactor sites will submit integrated assessments (IA) to address the reevaluated flooding hazard impact on their sites. The licensees for four operating power reactor sites have submitted an integrated assessment. The fifth IA (which involves a probabilistic storm surge analysis) is expected in 2019.

Seismic Hazard Reevaluation

- The licensees for all operating power reactor sites have completed their hazard reevaluation and have submitted their Seismic Hazard and Screening Reports (SHSR).

- The NRC used a graded approach to address seismic hazard results that exceed the current design basis.

- The licensees for 34 operating power reactor sites completed the expedited seismic evaluation process (ESEP) screening and evaluation.

All of the expected ESEP reports have been submitted.

- The NRC expects that the licensees for 18 operating power reactor sites will complete a seismic probabilistic risk assessment (SPRA). The licensees for 8 sites have submitted their SPRA. The NRC expects the remaining SPRAs to be completed by the end of 2019.

- The NRC requested that the licensees for 49 operating power reactor sites submit one or more limited scope evaluations (i.e., high frequency evaluations and spent fuel pool evaluations). All of the limited scope evaluations have been submitted.

Mitigation Strategies Assessments

- The licensees for 59 out of 60* operating power reactor sites have submitted their Flood Hazard mitigation strategies assessment (MSA).

- The licensees for 50 out of 60* operating power reactor sites have submitted their Seismic Hazard MSA. The remaining seismic MSAs depend on insights to be developed as part of the SPRA process.

  • The NRC granted Entergy's requests to defer the submittal date for remaining seismic and flooding reevaluation activities for Pilgrim and Indian Point to a date beyond the planned permanent shutdown in 2019 and 2021. The NRC is evaluating FENOCs request to defer the submittal date for the FE for Perry to a date beyond the permanent shutdown in 2021.

A table with the status of the hazard reevaluations is provided on the following pages. Site names that are highlighted in dark green have completed all post-Fukushima activities and the NRC has issued a completion letter.

January 7, 2019 Flooding and Seismic Hazard Reevaluation Status for Operating Reactors - Regions I and II

January 7, 2019 Flooding and Seismic Hazard Reevaluation Status for Operating Reactors - Regions III and IV