consumers Power company Palisades Nuclear Plant: Route 2, Box 154, Covert, Michigan 49043
\\R\\egulatory Docket File February 7, 1977 USNuclear Regulatory Commission Mail and Records Section Washington, D.C., 20555 Re:
LICENSE REPORT OF MONTHLY DPR-20,
.Docket No. 50-255 Gentlemen:
Enclosed is a copy of the Monthly Operating Data for the Palisades Nuclear Plant for the month of January 1977.
William E. Adams General Engineer cc:
JGKeppler, NRC RBDeWitt RB Sewell RLRosenfeld DEVanFarowe, Div. of Radiological Health Lansing, Mich.
Document Control
- l423 r.:..*
")
(
.. I APPENDIX C
~.
DOCKET NO. __
5_0-_2_5_5 __
UNIT __
P_a_l_i_sa_d_e_s_
2_-_7-_7_7 __ _
COMPLETED BY __
D_I_Bo_l_l_n_o_w_
AVERAGE.DAILY UNIT POWER LEVEL MONTH January 1977
. AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)
DAY
(.MWe~net) 1 664 17*
359 2
667 18 245 3
669 19 606
.4 673 20 657 5
669 21
. 648 6
649 22 659 7
145 23 661 8
430 24
. 6§6 9
522 25 668 10 637 26 662 11 569
- 27.
656 173 646 12 28 628 638 13 29 657 307 14 30 1!i
. 658 31 317" 647 16 DAILY UNIT POWER LEVEL FORM INSTRUCTIONS On this form, list the average daily unit power level in MWe-net for each day in the reporting month.
Compute to the nearest whole meg:.iwatt.
These figures will be used to plot a graph for each reporting month. Note that by using maximum.
dependable capacity for the net e!.:ctric::il rating of the unit. there may b~ occasions when the daily
- average power level exceeds the I 00% line (or the n:strictcd power level* line). In such cases. the
_)average daily unit power o:.itput shed should be footnokd to cxpbin the ap-parcnt anomaly.
1 1.IKI
~;
~-~--...~--:
.. ~:~;:.-=---~-~~--~---"I'..-:
...........,..,,.........,,.,...,......... ~~*-.'""**--.. ""'* --~.*
~-
.C.-. ***~.*:?";"
APPENDIX D UNIT _P_a_l_i_s_a_d_e._s __ ~
DATE___,F~e~b~.'-=""7rl,'-"1~9~7~7--
616-764=8913 CO'.'tlPLETE!:l BY __.D.._I.... B~o.....-.1.._l n....,....ci_..w __ _
DOCKET NO.
50-255
~
OPERATING STATCS
- 1.
REPORTING PERIOD: ___ 7,_7,_0=1=-0=1=---------- THROUGH __
7._7.._,0.._l.._3.,..1..__ ________ _
HOt;RS IN REPORTl:-:G PERIOD: ___
7.._4_,_,_4 ________________________ _
.2.
CURRENTLY ACTHORIZED POWER LEVEL (!\\1Wth) 2200 MAX. DEPENDABLE CAPACITY (MWe-NET}
635
- 3.
LOWEST POWER LEVEL TO WHICH SPECIFICALLY RESTRICTED (IF ANY) (MWe-NET): ______ ~----
- 4.
REASO~S FOR RESTRICTION (IF ANY):
CW.!ULATIVE THIS REPORTING PERIOD YR TO DATE TO DATE S.
HOURS REACTOR WAS CRITICAL...*.....*...
730
- 6.
REACTOR RESERVE SHUTDOWN HOURS..***..
- 7.
HOURS GENERA TOR ON LINE...*.**.**.****
720.6
- 8.
lJNJT RESER\\"E SHUTDOWN HOURS.....*.***.
. 9.
GROSS THER'.'t!AL ENERGY.
GENERATED ('.'tiWH) *.*****..*.***.**.*. ".
.l.d.26,488 IO.
GROSS ELECTRICAL ENERGY
- 11.
-GENERATED ('.'tl\\YH) *** : *****************
NET ELECTRICAL ENERGY GENERA TED
(!\\tWH) ***********.*****************
RL\\CTOR AVAILABILITY FACTOR (I)....*....
UNIT AVAILABILITY FACTOR (2).**.*.******
l'NITCAPACITY FACTOR (3) *...*..*....*..
UNIT FORCED OUTAGE RATE (4) *.....***...
445,510 418,883.
. 98.1%
- 96. 9%.
88.7%
3.1%
730 2*2 !000. 9 720.6 282544.8 1,426,488 34,109,472 445 2 510
- 10 2 630 2 710 418,883 9,947,562
. 98.1%
49.3.%.
96.9%
~6-1%-
88 7%
j5.8%
3.1%
47.3%.
- 12.
- 13.
- 14.
- 15.
- 16.
SHl'TDOWNS SCHEDULED TO BEGIN IN.NEXT 6 MONTHS (STATE TYPE, DATE, AND DURATION OF EACH):
- 17.
- 18.
(l)
IF Sltt:T DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP=------------~
UNITS IN TEST ST.:\\ TUS (PRIOR TO Cm.l:.1ERCIAL OPERATION) REPORT THE FOLLOWING:
REACTOR A \\'AILABILITY FACTOR t=NIT AVAILABILITY FACTOR INITIAL CRITICALITY INITIAL ELECTRICAL POWER GENERATION COMMERCIAL OPERATION HOURS REACTOR WAS CRITICAL HOURS IN REPORTING PERIOD x 100 HOURS GENERATOR ON Ll:O-:E
XlOO HOURS IN REPORTl:-:G PERIOD DATE LAST FORECAST DATE ACHIEVED l
(3) l'NIT (',\\P,\\CITY FACTOR t~
H>
C'ITFORCEDOl'TAGERATE NFT FLFCTRIC\\L POWFR GF~ERATED MAX. DEPENDABLE CAPACITY (MWc-NET) X HOURS IN REPORTING l'ERIOU
- J 1
- J FORCED OUTAGE HOURS
~x100 HOURS GENERATOR ON LI;-;E +FORCED OliTAGE HOURS 1.16-D-l
_,..,.~....__....,~..,_.....-<_..,_,~---..,,.._'"""",...,._.-..,......-~.-.. ~_....,...,.._.,..._ -V"!'.,.,.*"+
..... -...,-.. *=**--""'.l'"'<<,_.u~+,;,....-...,...,,.P_,...,.. ~*_-::>,.,.,_,_,_
.......--......,.,.-..... 1--.0-.....,.............. _"'__.'" ""'* -..,.:*.*..,......-. "t:.C..,.,. *""'°*.,..,..,..,.,,_,...,....,_.~.,.
\\
.. ~-~,....._
- -*,:__.:...__.~-*.
'*" t
/T"'\\}
~
.(:_)
- , *... [
APPENDIX E DOCKET NO.
. 50-255 i * ~ r UNIT SHUTDOWNS UNIT NAME Palisades
\\ *
[*
I DATE 2-7-77 COMPLETED BY DIBollnow I'
REPORT MONTH _J_a:n_u_a_r-=-y_l 9;...;7....:.7 __
TYPE METHOD OF F*FORCED DURATIPN SHUTTING DOWN NO.
DATE S*SCHEDULED * (HOU.RS)
REASON (1)
THE REACTOR (2)
COR R.ECTIVE ACTIONS/COMMENTS 1
770111 F
10.7 A
2 Cooling Tower Pump Trip 2
770117
. F 7.5 A
2 Heater Drain Pump Trip/
3 770117 F
5.2 H
3 Feedwater Pump Trip
\\
\\
r (1) REASON (2) METHOD.
A**EQUIPMENT FAILURE'(EXPLAIN)
I-MANUAL
~.I.
B* MAINT. OR TEST 2-MANUAL C-REFUELING SCRAM D-REGULATORY RESTRICTION 3-A UTOMA TIC E-OPERATOR TRAINING AND SCRAM LICENSE EXAMINATION F-ADMINISTRATI YE G--Ol'ERATIONAL ERROR (EXPLAIN)
H-OTHER (EXPLAIN)
SUMMARY
Plant operated at a nominal 100% power, ~ooling tower."icing continues to restrict maximum electrical generation.
t*