MONTHYEARML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staffs Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230112023-08-25025 August 2023 Comprehensive Engineering Team Inspection Report 05000269/2023011 and 05000270/2023011 and 05000287/2023011 IR 05000269/20230052023-08-25025 August 2023 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2 and 3 (Report 05000269/2023005, 05000270/2023005, and 05000287/2023005) IR 05000269/20230022023-07-28028 July 2023 Integrated Inspection Report 05000269/2023002, 05000270/2023002 and 05000287/2023002 ML23208A0972023-07-27027 July 2023 Subsequent License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000269/20230102023-07-19019 July 2023 Biennial Problem Identification and Resolution Inspection Report 05000269/2023010 and 05000270/2023010 and 05000287/2023010 and Notice of Violation ML23178A0682023-07-0303 July 2023 Audit Plan Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 & 3 Systems Section XI, Division 1 ML23132A2392023-06-0101 June 2023 Summary of the April 2023 Remote Environmental Audit Related to the Review of the Subsequent License Renewal Application ML23144A0192023-05-25025 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report (O3R31) IR 05000269/20230012023-05-12012 May 2023 Integrated Inspection Report 05000269/2023001 and 05000270/2023001 and 05000287/2023001 ML23121A0552023-05-0303 May 2023 Acknowledgement of Withdrawal Request to Revise TS 5.5.2 Containment Leakage Rate Testing Program ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23117A0432023-04-20020 April 2023 Framatome, Inc., Part 21 Notification of Existence of a Defect ML23075A0732023-04-0505 April 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement (EPID Number L-2021-SLE-0002) ML23045A1332023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Achp Letter ML23045A1402023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Shpo Letter ML23045A1432023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - State Tribe Letter ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML23069A1102023-03-10010 March 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23061A1772023-03-0303 March 2023 Notification of Oconee Nuclear Station Comprehensive Engineering Team Inspection - NRC Inspection Report 05000269/2023011, 05000270/2023011 and 05000287/2023011 IR 05000269/20220062023-03-0101 March 2023 Annual Assessment Letter for Oconee Nuclear Nuclear Station, Units 1, 2 and 3 (NRC Inspection Report 05000269/2022006, 05000270/2022006, and 05000287/2022006) ML23039A1632023-02-0808 February 2023 Requalification Program Inspection ML23037A0772023-02-0606 February 2023 402 Cyber Notification and RFI Letter Final IR 05000269/20220042023-02-0202 February 2023 Integrated Inspection Report 05000269 2022004 and 05000270/2022004 and 05000287/2022004 ML22363A3942023-01-12012 January 2023 Subsequent License Renewal Environmental Report Supplement - Proposed Review Schedule ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22321A0492022-12-0808 December 2022 Issuance of Amendment Nos. 426, 428 and 427, Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9, Increase Flexibility in Mode Restraints ML22329A1042022-11-29029 November 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report ML22321A1582022-11-22022 November 2022 Summary of Conference Call Regarding the Fall 2022 Steam Generator Tube Inspections ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000269/20220032022-11-0707 November 2022 Integrated Inspection Station 05000269/2022003 and 05000270/2022003 and 05000287/2022003 ML22301A0112022-11-0303 November 2022 Request for Withholding Information from Public Disclosure Regarding the SLR Application - September 2, 2022 ML22298A0752022-10-27027 October 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application Duke Energy Letter Dated July 25, 2022 ML22264A0322022-10-20020 October 2022 _Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Duke Energy Letter Dated July 8, 2022 IR 05000269/20220112022-09-26026 September 2022 NRC Inspection Report 05000269/2022011 and 05000270/2022011 and 05000287/2022011 ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22222A0072022-09-14014 September 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi ML22234A0062022-08-30030 August 2022 SLRA - Closed Public Meeting Summary - August 18, 2022 2024-02-01
[Table view] |
See also: IR 05000269/2019410
Text
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
December 7, 2018
Mr. Ed Burchfield, Jr.
Site Vice President
Oconee Nuclear Station
Duke Energy Carolinas, LLC
7800 Rochester Highway
Seneca, SC 29672-0752
SUBJECT: OCONEE NUCLEAR STATION - INFORMATION REQUEST FOR THE CYBER-
SECURITY INSPECTION AND NOTIFICATION TO PERFORM INSPECTION
05000269/2019410, 05000270/2019410, and 05000287/2019410.
Dear Mr. Burchfield:
On April 8, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin an inspection in
accordance with Inspection Procedure (IP) 71130.10P Cyber-Security, Revision 0 Oconee
Nuclear Station. The inspection will be performed to evaluate and verify your ability to meet the
Milestone 8 (i.e., full implementation) requirements of the NRCs Cyber-Security Rule, Title 10,
Code of Federal Regulations (CFR), Part 73, Section 54, Protection of Digital Computer and
Communication Systems and Networks. The onsite portion of the inspection will take place
during the weeks of April 8, 2019, and April 22, 2019. The information gathering trip coincide
with Catawbas information gathering trip the week of January 14th, 2019.
Experience has shown that these types of inspections are extremely resource intensive, both for
the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the
site and to ensure a productive inspection for both parties, we have enclosed a request for
documents needed for the inspection. These documents have been divided into four groups.
The first group specifies information necessary to assist the inspection team in choosing the
focus areas (i.e., sample set) to be inspected by the cyber-security IP. This information should
be made available via secure site (i.e., Sharepoint, Certrec) no later than January 14, 2019.
The inspection team will review this information and, by February 11, 2019, will request the
specific items that should be provided for review.
The second group of additional requested documents will assist the inspection team in the
evaluation of the critical systems and critical digital assets (CSs/CDAs), defensive architecture,
and the areas of the licensees CSP selected for the cyber-security inspection. This information
will be requested for review via secure site (i.e., Sharepoint, Certrec) before March 11, 2019.
The third group of requested documents consists of those items that the inspection team will
review, or need access to, during the inspection. Please have this information available by the
first day of the onsite inspection, April 4, 2019.
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
E. Burchfield 2
The fourth group of information is necessary to aid the inspection team in tracking issues
identified as a result of the inspection. It is requested that this information be provided to the
lead inspector as the information is generated during the inspection. It is important that all of
these documents are up to date and complete in order to minimize the number of additional
documents requested during the preparation and/or the onsite portions of the inspection.
The lead inspector for this inspection is Melana Singletary. We understand that our regulatory
contact for this inspection is Sam Adams of your organization. If there are any questions about
the inspection or the material requested, please contact the lead inspector at
404-997-4752 or via e-mail at Melana.Singletary@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a
request for information or an information collection requirement unless the requesting document
displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding,
of the NRC's "Rules of Practice," a copy of this letter and its enclosure will not be available
electronically for public inspection in the NRCs Public Document Room or from the Publicly
Available Records (PARS) component of the NRC's Agencywide Documents Access and
Management System (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Scott M. Shaeffer, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No.: 50-269, 50-270, 50-287
License No.: DPR-38, DPR-47, DPR-55
Enclosure:
Security Inspection Document Request
cc: See Page 3
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
E. Burchfield 3
cc:
Mr. Chris Wasik
Regulatory Affairs Manager
Oconee Nuclear Station
Duke Energy Carolinas, LLC
7800 Rochester Highway
Seneca, SC 29672
Mr. Mark McNeely
Director, Nuclear Security Operations
Oconee Nuclear Station
Duke Energy Carolinas, LLC
7800 Rochester Highway
Seneca, SC 29672
OFFICIAL USE ONLY - SECURITY RELATED INFORMATION
___ML 18346A030 _ SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII/DRS/EB1 RII:DRS/EB1
SIGNATURE MJS6 SMS
NAME MSINGLETARY SSHAEFFER
DATE 12/7/2018 12/7/2018
E-MAIL COPY? YES NO YES NO