MONTHYEARML24267A2552024-09-23023 September 2024 Change in the NRC Project Manager for the West Valley Demonstration Project IR 05000201/20240012024-05-0808 May 2024 West Valley Demonstration Project - Nuclear Regulatory Commission Monitoring Visit Report 05000201/2024001 ML23229A4712023-08-17017 August 2023 Change in the NRC Project Manager for the West Valley Demonstration Project IR 05000201/20230012023-03-28028 March 2023 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2023001 ML23038A0402023-03-15015 March 2023 New York State Energy Research and Development Authority Results of a Teleconference to Discuss Disposition of Historical Records Related to the Former Nuclear Fuel Services, Inc ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000201/20220032022-12-0606 December 2022 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2022003 IR 05000201/20220022022-09-28028 September 2022 West Valley Demonstration Project - U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2022002 IR 05000201/20210012022-08-10010 August 2022 West Valley Demonstration Project: U.S. Nuclear Regulatory Commission Monitoring Visit Report Nos. 05000201/2021001 and 05000201/2022001 ML22180A1892022-06-21021 June 2022 Notification of Temporary Change in Radiation Safety Officer Position for New York State Energy Research and Development Authority'S Radiation Protection Program for the Retained Premises of the Western New York Nuclear Service Center ML22145A2972022-05-0202 May 2022 Letter from J. Dean to M. Pagels, Et Al., West Valley Supplemental Environmental Impact Statement Final Scope Dated 5/2/2022 ML21349B3442021-12-17017 December 2021 U.S. Department of Energy West Valley Demonstration Project - Demolition Readiness of the Main Plant Process Building Decommission and Demolition Plan (Docket No. 50-201 (POOM-032) ML21245A2462021-11-0505 November 2021 NYSERDA Retained Premises Radiation Protection Plan Amendment Package ML21202A2122021-07-15015 July 2021 Response to NRC Letter: Request for Additional Information Regarding the License Amendment to Incorporate Updated Retained Premises Radiation Protection Requirements (EPID L-2020-LLA-0029), Dated June 3, 20 ML21118A0762021-06-0303 June 2021 NYSERDA - Request for Additional Information Regarding the License Amendment to Incorporate Updated Retained Premises Radiation Protection Requirements ML21126A0232021-04-27027 April 2021 Us Dept. of Energy, West Valley Demonstration Project, Air Dispersion Modeling Performed in Support of West Valley Demonstration Project (Wvdp) Main Plant Process Building (Mppb) Demolition Preparations ML21105A3522021-04-0505 April 2021 Notification of Change in Radiation Safety Officer for the New York State Energy Research and Development Authority'S Radiation Protection Program for the Retained Premises of the Western New York Nuclear Service Center ML21012A3072020-12-15015 December 2020 Responses to NRC Comments on the West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Work Plan, Revision 4 ML21012A2992020-12-14014 December 2020 West Valley Supplemental Environmental Impact Statement Schedule and Probabilistic Performance Assessment Technical Discussions IR 05000201/20200022020-11-0202 November 2020 U. S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2020002, West Valley Demonstration Project, West Valley, New York ML20311A2002020-10-28028 October 2020 Response to NRC Letter: Initial Review for NYSERDA Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001), Dated March 11, 2020 (EPID L-2020-LLA-0023), Dated March 30, 2020 ML20261H5452020-09-24024 September 2020 Change in the NRC Project Manager for the West Valley Demonstration Project ML20268B2372020-09-24024 September 2020 Change in the NRC Project Manager for the West Valley Demonstration Project ML20265A3552020-09-22022 September 2020 Comments on Rev.4 Main Plant Process Building Demolition & Decommissioning Plan ML20115E4972020-04-27027 April 2020 Second Round of Comments on U.S. Department of Energy West Valley Demonstration Project'S Final Study Document: Vitrification Facility Air Emissions During Open-Air Demolition, Measured Vs Predicted, WVDP-579, Rev. 0 (Docket No. 05000201 (P ML20084G6412020-03-30030 March 2020 Letter, A.Snyder to P. Bembia, NYSERDA, Initial Review for NYSERDA Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001), Dated March 11, 2020 ML20076C3102020-03-11011 March 2020 Resubmittal of Request for License Amendment: Retained Premises Radiation Protection Requirements ML20055E0492020-02-19019 February 2020 Response to Comments on U.S. DOE, Wvdp Air Study IR 05000201/20200012020-02-10010 February 2020 U.S. Nuclear Regulatory Commission Monitoring Visit Report 05000201/2020001, West Valley Demonstration Project, West Valley, New York ML20042D4972020-02-0606 February 2020 Western New York Nuclear Service Center - Request for License Amendment: Retained Premises Radiation Protection Requirements (LAR-20-001) ML19319A2932019-12-0404 December 2019 Comments on U.S. Department of Energy West Valley Demonstration Project Final Study Document: Vitrification Facility Air Emissions During Open-Air Demolition, Measured Vs Predicted, WVDP-579 ML19267A2102019-09-12012 September 2019 U.S. Department of Energy West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 3 ML20265A3952019-06-19019 June 2019 June 19, 2019 Letter from Brian C. Bower to Amy Snyder, West Valley Main Plant Process Building, Rev. 3 IR 05000201/20190012019-06-18018 June 2019 U.S. Nuclear Regulatory Commission Monitoring Visit Report 05000201/2019001, West Valley Demonstration Project, West Valley, Ny ML19149A2362019-05-30030 May 2019 NRC Response Letter to DOE-WVDP on the Main Process Plant Demolition Work Plan ML19149A5552019-05-28028 May 2019 Vaughan Letter on CSM Corrections Needed - 5-28-19 ML18282A5232018-11-0707 November 2018 NRC Response to Nyserda'S Requests for Clarification of License Responsibility ML18290A5662018-11-0101 November 2018 Response to NYSERDA 10 CFR 50.59 Evaluation IR 05000201/20180022018-10-25025 October 2018 U. S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2018002, West Valley Demonstration Project, West Valley, New York ML18262A2542018-09-12012 September 2018 NYSERDA Letter Dated September 12, 2018 Requesting Clarification License Responsibility ML18236A3882018-08-27027 August 2018 U.S. Department of Energy West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 1, Dated February 27, 2017 ML18179A3992018-07-26026 July 2018 Response Letter - the U.S. Army Corps of Engineers Buffalo District Design - Level Sediment Sampling and Analysis Plan - Springville Dam and Cattaraugus Creek Sediment Sampling, Dated April 2018 ML18222A2192018-06-19019 June 2018 NRC Solar Letter IR 05000201/20180012018-06-0707 June 2018 U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2018001. West Valley, Demonstration Project, West Valley, New York ML18192C1592018-05-0202 May 2018 May 2, 2018 Letter from NYSERDA Regarding Conforming CSF-1 to Current Site Conditions ML18087A6662018-04-0909 April 2018 Cover Letter TER for Wvnsnsc Off-Site Evaluation IR 05000201/20170012018-02-22022 February 2018 U.S. Nuclear Regulatory Commission Monitoring Visit Report No. 05000201/2017001, West Valley Demonstration Project, West Valley, New York ML18092A0562018-02-0505 February 2018 U.S. Department of Energy West Valley Demonstration Project (DOE-WVDP) Responses to U.S. Nuclear Regulatory Commission (NRC) Comments on DOE-WVDP Main Plant Process Building (Mppb) Decommissioning & Demolition (D&D) Plan ML17347A1252018-01-16016 January 2018 Letter to Us Army Corps of Engineers - NRC Comments on Springville Dam Sampling and Analysis Plan ML17270A1192017-09-28028 September 2017 NRC Comments on the U.S. DOE West Valley Demonstration Project Main Plant Process Building Decommissioning & Demolition Plan, WVDP-586, Revision 1 (Docket No. 05000201 (POOM-032) 2024-09-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 1, 2018 Paul Bembia, Director West Valley Site Management New York State Energy Research and Development Authority 9030-B Route 219 West Valley, NY 14171-9500
SUBJECT:
EVALUATION OF THE INSTALLATION AND SUBSEQUENT OPERATION, MAINTENANCE AND REMOVAL OF A SOLAR PHOTOVOLTAIC FACILITY ON A NON-IMPACTED AREA OF THE LICENSED AREA, REVISION 0, DATED JUNE 2018
Dear Mr. Bembia:
The U.S. Nuclear Regulatory Commission (NRC) staff is responding to the New York State Energy Research and Development Authoritys (NYSERDA) June 19, 2018, letter (Agencywide Documents Access and Management System [ADAMS] Accession No. ML18222A219) requesting that the NRC staff conduct a screening of NYSERDAs information package, titled Evaluation of the Installation and Subsequent Operation, Maintenance, and Removal of a Solar Photovoltaic Facility on a Non-Impacted Area of the WNYNSC (Western New York Nuclear Service Center) (ADAMS Accession No. ML18222A218) and provide comments or questions related to the submitted information package. Within the information package, NYSERDA included its Title 10 of the Code of Federal Regulations (10 CFR) 50.591 evaluation (Section 4.0) for this proposed activity to determine if a license amendment must be obtained from the NRC. Since your 10 CFR 50.59 evaluation concluded that the proposed activity was within the licensing safety envelope, there was no need to seek specific NRC approval or comments. The NRC staff reviewed this package as a courtesy, however future NYSERDA 10 CFR 50.59 evaluations should be reviewed during the inspection process.
The NRC staff reviewed the section of the evaluation entitled Documentation that the Area Identified for the Project is Non-Impacted in order to assess NYSERDAs justification for concluding that the area is non-impacted. NUREG 1575 Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM), Revision 1 (ADAMS Accession Nos. ML003761445 and ML003761454),2 defines non-impacted areas as areas that have no reasonable potential for residual contamination. The NRC staff noted that the 53.6-acre property identified for 1
The 10 CFR 50.59 rule controls changes, tests, and experiments performed by a 10 CFR Part 50 licensee. The 10 CFR 50.59 regulations provide a threshold for determining when NRC approval of changes, tests, or experiments is required.
2 NUREG-1575 provides detailed guidance for planning, implementing, and evaluating environmental and facility radiological surveys conducted to demonstrate compliance with a dose- or risk-based regulation. The MARSSIM guidance focuses on the demonstration of compliance during the final status survey following scoping, characterization, and any necessary remedial actions. The NRC staff believes that the use of this guidance is appropriate even though NYSERDA is not at this time submitting an application for the release of any portion of the licensed area.
P. Bembia 2 construction appears to fit the MARSSIM definition of non-impacted based on the NRC staffs review of the historical site information provided by NYSERDA. Also, the data from the aerial gamma radiation surveys have not identified any radioactivity levels substantially above background levels in the proposed solar photovoltaic facility area. The NRC understands that the proposed solar photovoltaic facility would be located more than 300 feet from the potentially impacted underground areas surrounding the Bulk Storage Warehouse. The NRC concurs that this distance would provide a sufficient buffer to conclude that the 53.6-acre selected area is likely non-impacted. The NRC staff understands that the solar photovoltaic facility would be located more than 100 feet from the nearest hydrofracture test well in order to provide adequate working space for Phase 2 decommissioning activities. While these distances appear adequate to prevent the land areas from becoming radiologically impacted, NYSERDA must ensure controls and procedures are implemented to prevent the area from being impacted by current and future decommissioning activities.
The NRC staff also reviewed NYSERDAs 10 CFR 50.59 determination that provided NYSERDAs conclusion that construction of a solar photovoltaic facility on the NRC Retained Premises3 would not require an amendment to its 10 CFR Part 50 license, NRC License No.
CSF-0001, based on the 10 CFR 50.59 evaluation. NYSERDA appears to have correctly followed the guidance in Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, Revision 1 (ADAMS Accession No. ML003759710).
The U.S. Department of Energy (DOE), under the West Valley Demonstration Project (WVDP)
Act, continues to conduct active decommissioning of the reprocessing facility. Based on NYSERDAs information package, the NRC staff understand that NYSERDA would establish protocols to authorize workers access to the facility, as needed, in order to maintain the function of the Exclusion Area as described in the final safety analysis report (FSAR). The NRC staff suggest that NYSERDA review its license to determine whether there are any additional requirements of the license that would need to be followed. NYSERDA is responsible for safely conducting work activities (whether they be conducted by NYSERDA or others) in the NRC Retained Premises in accordance with its license irrespective of whether a license amendment is required.4 Further, the NRC staff note that the NRC Retained Premises remains subject to inspection.
Also, the NRC noted that in the DOEs August 8, 2017, letter to NYSERDA that was included as Appendix G of NYSERDAs information package, DOE stated that, Based on the information you have provided, EMCBC-WV (DOE Environmental Management Consolidated Business Center - West Valley) sees no violation to Section 4.02 of the Cooperative Agreement.
EMCBC-WV expressly reserves it[s] right to re-evaluate its position if a fully detailed design package for the CDG Solar Facility project becomes available. Similarly, the NRC may examine any completed design package that becomes available for further evaluation of the project and to verify that License Condition No. 7.D. continues to be met.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public 3
NRC Retained Premises - licensed area consisting of the WNYNSC not including the DOE WVDP Retained Premises and the State-Licensed Disposal Area.
4 Unless DOE takes responsibility under Section 4.12 of the Cooperative Agreement between DOE and NYSERDA.
P. Bembia 2 Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
If you have any questions or need any additional information regarding our comments, please contact me at 301-415-6822.
Sincerely,
/RA/
Amy M. Snyder, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards cc:
C. Davis, Town of Ashford B. Bower, DOE S. Gavitt, NYSDOH T. Rice, NYSDEC N. Shaw, NYSERDA J. Dean, NYSERDA
ML18290A566 *via email OFFICE RI/DNMS RI/DNMS NMSS/DUWP NMSS/DUWP NAME KWarner RPowell ASnyder CHolston 9/14/18, DATE 9/10/18 10/23/18 10/3/18, 10/9/18 10/17/18 and 10/18/18 NMSS/DUWP NMSS/DUWP OFFICE OGC BWatson ASnyder NAME LSClark DATE 10/31/18 10/18/18 11/01/18