October 22, 2018 MEMORANDUM TO: Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors FROM: Jordan Hoellman, Project Manager /RA/
Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors
SUBJECT:
SUMMARY
OF A PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY ON SEPTEMBER 13, 2018 The U.S. Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with Southern Nuclear Operating Company (SNC) on September 13, 2018. The purpose of the meeting was to discuss issues associated with the safety review of licensing actions for SNCs Vogtle Electric Generating Plant (VEGP) Units 3 and 4.
The meeting notice can be found in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML18229A013. The meeting notice is also posted on the NRC public website. Enclosures 1 and 2 are the meeting agenda and attendance list for the meeting, respectively. The other documents referenced during the discussion can be found at the ADAMS Accession Nos. given below:
- SNCs draft proposed Alternative Section for Request for Alternative ALT-06 - ML18254A248
Watchdog Timer and Common Q Design - ML18254A249 Description Changes (PUBLIC)
- Pre-submittal Presentation for LAR 18-023 - ML18254A253
- Revised draft Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)
Notification (UIN) for ITAAC 2.3.04.02.ii [Index - ML18256A293 No. 328]
CONTACT: Jordan Hoellman, NRO/DLSE (301) 415-5481
J. Dixon-Herrity Summary of Meeting:
On September 13, 2018, staff from the NRC conducted a public meeting with representatives from SNC to discuss issues associated with the safety review of licensing actions for SNCs VEGP Units 3 and 4. Specifically, the meeting discussed (1) pre-submittal information regarding ALT-06, (2) pre-submittal information regarding LAR 18-023, and (3) SNCs revised UIN for ITAAC Index No. 328.
The first topic discussed was pre-submittal information regarding ALT-06. The staff noted that there have been multiple pre-submittal interactions with SNC on this topic and thanked SNC for their efforts in developing this alternative request. SNC discussed the draft proposed alternative section of ALT-06, noting that the alternative proposes to eliminate the volumetric examination requirement for the austenitic stainless steel valve material on pipe-to-valve welds. SNC discussed that AP1000 design features implemented on the VEGP Units 3 and 4 valve-to-pipe welds has a smooth transition from the valve to pipe, which improves inspectability by providing better access to the far side of the weld volume. With these design features, it was possible to qualify a VEGP Units 3 and 4 specific ultrasonic examination procedure, which is based on the requirements of the latest version of PDI-UT-2. SNC discussed that 25 mock-ups were developed using the valve-to-pipe configurations at VEGP Units 3 and 4 to support development of the new VEGP Units 3 and 4 specific ultrasonic examination procedure. The staff noted that they understood SNCs request and provided comments on the draft alternative section. The staff commented that, to improve clarity, the request should include a paragraph that details the differences between the VEGP Units 3 and 4 specific procedure and PDI-UT-2. SNC stated that they understood the staffs comments and noted that they plan to submit ALT-06 by the end of September 2018.
The second topic discussed was pre-submittal information regarding LAR 18-023. SNC provided an overview of the LAR and walked through the pre-submittal presentation, noting that the changes proposed in LAR 18-023 are needed to allow installation of cabinets and panels in the PMS that are impacted by the proposed changes. LAR 18-023 proposes to revise the Updated Final Safety Analysis Report (UFSAR) to accurately describe the design and use of the watchdog timers (WDTs) in the processor module of the Common Q platform portion of the PMS. SNC noted that the safety function and operability of the processor module is not adversely impacted by the proposed changes. SNC discussed that NSAL 17-2, AC160 Processor Module Stall Timers Not Activated as Described in Licensing Basis, identifies that the software stall timer within the AC160 software is not enabled as per WCAP-16097-P-A, Rev. 3, Common Q Topical Report (TR), and a cycle time in the Common Q TR does not meet the as-built system. An extent of condition identified additional changes to WCAP-16097, and the changes were discussed with the NRC in 2017. SNC discussed that LAR 18-023 also proposes changes to the design description of the Common Q platform identified in the extent of condition review for NSAL 17-2 and that Westinghouse Electric Company (Westinghouse) plans to submit generic changes to the Common Q TR at a later date. The staff expressed concerns with SNC proceeding to make site-specific generic changes to the Common Q TR independently. The staff noted that in the 2017 discussion, Westinghouse presented that the generic changes to the Common Q TR would be requested by Westinghouse and then licensees would request that the approved TR would be incorporated into their licensing bases.
Although previous technical exchange meetings had occurred in 2017 between the staff, SNC, and Westinghouse, concerning the exact functionality and description of the WDTs, the understanding of how the staffs concerns were addressed was not evident in the documentation provided for the pre-submittal meeting. The staff explained that the language and diagram describing and depicting the overall WDT function were ambiguous. The staff also
J. Dixon-Herrity expressed concerns that information describing each of the WDT sub-functions within the overall WDT function may lead to a prolonged evaluation period as well as requests for additional information by the staff to ensure the staff understands the design details of each WDT function prior to making a safety determination. As a result, the timeline proposed by SNC for the submittal and potential approval of the LAR may be impacted. SNC stated that they understood the staffs concerns and noted that the request and timing of the request is tied to the construction activity associated with the proposed changes. The staff acknowledged SNCs construction-related concerns.
The third topic discussed was SNCs revised UIN for ITAAC Index No. 328. The staff noted that SNCs revised UIN addresses the staffs concerns. SNC stated that they plan to formally submit the UIN for staff review.
At the end of each topic discussed, there was an opportunity for the public to provide comments and ask questions. There were no questions or comments from members of the public.
In the closed portion of the LAR 18-023 pre-submittal discussion, the proprietary details of SNCs request were discussed.
Docket Nos.: 052-025 052-026
Enclosure:
As stated cc w/encls: See next page
ML18282A092 *via e-mail NRC-001 OFFICE PM: DLSE/LB4 LA: DLSE/LB4 BC: DLSE/LB4 PM: DLSE/LB4 NAME JHoellman (c) RButler (c) JDixon-Herrity (c) JHoellman (s)
DATE 10/22/18 10/18/18 10/22/18 10/22/18 AGENDA FOR PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Thursday, September 13, 2018 9:00 a.m. - 11:00 a.m.
PURPOSE: To discuss issues associated with the safety review of licensing actions for Southern Nuclear Operating Companys (SNC) Vogtle Electric Generating Plant (VEGP) Units 3 and 4.
OPEN Time Topic Led By 9:00 a.m. Opening Remarks NRC 9:05 a.m. Discussion of pre-submittal information NRC/SNC regarding Request for Alternative ALT-06 9:40 a.m. Opportunity for Public Comment PUBLIC/NRC 9:40 a.m. Discussion of pre-submittal information NRC/SNC/Westinghouse regarding License Amendment Request (LAR)18-023 10:00 a.m. Opportunity for Public Comment PUBLIC/NRC CLOSED 10:00 a.m. Discussion of proprietary details related NRC/SNC/Westinghouse to pre-submittal information regarding License Amendment Request (LAR)18-023 OPEN 10:40 a.m. Discussion of SNCs Revised NRC/SNC Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Notification (UIN) for ITAAC Index No. 328 11:00 a.m. Opportunity for Public Comment PUBLIC/NRC 11:00 a.m. Adjourn Enclosure 1
PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION Thursday, September 13, 2018 9:00 a.m. - 11:00 a.m.
List of Attendees Name Organization Representing the Nuclear Regulatory Commission Jordan Hoellman NRO/DLSE/LB4 John Honcharik
- NRO/DEI/MCB Matt Mitchell NRO/DEI/MCB Richard Stattel NRR/DE/EICB Bill Roggenbrodt NRO/DEI/ICE Jack Zhao NRO/DEI/ICE Jim Gaslevic NRO/DCIP/HOIB Chris Welch
- NRO/DCIP/HOIB Tim Lupold NRO/DEI/MEB Tuan Le
- NRO/DEI/MEB Representing Industry Neil Haggerty Southern Nuclear Operating Company (SNC)
Corey Thomas
- SNC Stephanie Agee
- SNC Wes Sparkman
- SNC Tom Petrak
- SNC Bob Hirmanpour
- SNC Amy Chamberlain
- SNC Amy Aughtman
- SNC Mark Humphry
- SNC Calviin Marrow
- SNC Greg Wilson
- SNC Rick Paese Westinghouse Electric Company (Westinghouse)
Warren Oddess-Gillette
- Westinghouse Chris Phillips
- Westinghouse Representing Public Steve Franzone
- = participated via teleconference Enclosure 2
Vogtle Units 3 & 4 Mailing List (Revised 08/16/2018) cc:
Office of the Attorney General Resident Inspector 40 Capitol Square, SW Vogtle Plant Units 3 & 4 Atlanta, GA 30334 8805 River Road Waynesboro, GA 30830 Resident Manager Oglethorpe Power Corporation Mr. Barty Simonton Alvin W. Vogtle Nuclear Plant Team Leader 7821 River Road Environmental Radiation Program Waynesboro, GA 30830 Air Protection Branch Environmental Protection Division Southern Nuclear Operating Company, Inc. 4244 International Parkway, Suite 120 Document Control Coordinator Bin N-226-EC Atlanta, GA 30354-3906 3535 Colonnade Parkway Birmingham, AL 35243 George B. Taylor, Jr.
2100 East Exchange Pl Anne F. Appleby Atlanta, GA 30084-5336 Olgethorpe Power Corporation 2100 East Exchange Place Brian H. Whitley Tucker, GA 30084 3535 Colonnade Parkway, Bin N-226-EC 42 Inverness Center Parkway, BIN B237 County Commissioner Birmingham, AL 35243 Office of the County Commissioner Burke County Commission Mr. Michael Yox Waynesboro, GA 30830 Site Regulatory Affairs Director Vogtle Units 3 & 4 Mr. Wayne Guilfoyle 7825 River Road, Bin 63031 Commissioner District 8 Waynesboro, GA 30830 Augusta-Richmond County Commission 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Page 1 of 3
Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
ALPUGH@southernco.com (Amanda Pugh) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)
G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)
JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)
John.Bozga@nrc.gov (John Bozga)
Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kmstacy@southernco.com (Kara Stacy)
KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) markus.popa@hq.doe.gov (Markus Popa)
Page 2 of 3
Vogtle Units 3 & 4 Mailing List Matthew.Williams@hq.doe.gov (Matthew Williams) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)
Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price)
MKWASHIN@southernco.com (MKWashington) mlgraves@southernco.com (Michelle Graves)
MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi)
RJB@NEI.org (Russell Bell)
Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
TomClements329@cs.com (Tom Clements)
Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)
Page 3 of 3