1 NRR-DMPSPEm Resource From:
Saba, Farideh Sent:
Monday, September 17, 2018 3:01 PM To:
David.Turberville@adph.state.al.us Cc:
Venkataraman, Booma; Ronewicz, Lynn; Clayton, Beverly; Jordan, Natreon
Subject:
State Consultation: Request for Comments on Browns Ferry Units 1, 2, and 3 to Revise Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program" Attachments:
SKM_C36818091714530.pdf Importance:
High Tracking Tracking:
Recipient David.Turberville@adph.state.al.us Venkataraman, Booma Ronewicz, Lynn Clayton, Beverly Jordan, Natreon
Dear Mr. Turberville,
The NRC is finalizing license amendments for Browns Ferry Nuclear Plant, Units 1, 2, and 3. In accordance with Title 10 of the Code of Federal Regulations, Section 50.91(b), I am notifying you of the proposed issuance of these amendments. The amendments are in response to Tennessee Valley Authoritys license amendment request dated August 15, 2017 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML17228A490), as supplemented by letters dated February 5, 2018 (ADAMS Accession No. ML18036A901); March 27, 2018 (ADAMS Accession No. ML18087A426); and July 27, 2018 (ADAMS Accession No. ML18208A587). The amendments revise Technical Specification 5.5.12, Primary Containment Leakage Rate Testing Program, at Browns Ferry Nuclear Plant, Units 1, 2, and 3, by adopting Nuclear Energy Institute (NEI) 94-01, Revision 3 A, Industry Guideline for Implementing Performance Based Option of 10 CFR
[Title 10 of the Code of Federal Regulations] Part 50, Appendix J, as the implementation document for the performance based Option B of 10 CFR Part 50, Appendix J. The proposed changes allow the licensee to extend the Type A containment integrated leak rate testing interval from 10 years to 15 years, and the Type C local leakage rate testing intervals from 60 months to 75 months.
The license amendment request was published in Federal Register on November 21, 2017 (82 FR 55415).
Please see the attached document. No public comments were received.
Please let us know, if you have any comments on behalf of the State of Alabama for the above amendment.
Please contact me if you have any questions.
- Regards, Farideh E. Saba, P.E.
Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8B01A Farideh.Saba@NRC.GOV
2
Hearing Identifier:
NRR_DMPS Email Number:
576 Mail Envelope Properties (Farideh.Saba@nrc.gov20180917150000)
Subject:
State Consultation: Request for Comments on Browns Ferry Units 1, 2, and 3 to Revise Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program" Sent Date:
9/17/2018 3:00:55 PM Received Date:
9/17/2018 3:00:00 PM From:
Saba, Farideh Created By:
Farideh.Saba@nrc.gov Recipients:
"Venkataraman, Booma" <Booma.Venkataraman@nrc.gov>
Tracking Status: None "Ronewicz, Lynn" <Lynn.Ronewicz@nrc.gov>
Tracking Status: None "Clayton, Beverly" <Beverly.Clayton@nrc.gov>
Tracking Status: None "Jordan, Natreon" <Natreon.Jordan@nrc.gov>
Tracking Status: None "David.Turberville@adph.state.al.us" <David.Turberville@adph.state.al.us>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1826 9/17/2018 3:00:00 PM SKM_C36818091714530.pdf 2762377 Options Priority: