MONTHYEARML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML23235A0422023-09-0505 September 2023 VC Summer SLRA Availability FRN ML18198A3002019-03-0808 March 2019 Combined License Termination Federal Register Notice ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 ML18276A1562018-10-0505 October 2018 Federal Register Notice of Corrected Orders of the Indirect License Transfer Issuance NRC-2018-0043, Federal Register Notice of Corrected Orders of the Indirect License Transfer Issuance2018-10-0505 October 2018 Federal Register Notice of Corrected Orders of the Indirect License Transfer Issuance ML18243A0872018-09-0505 September 2018 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License NPF-12, Proposed No Significant Hazards Consideration,(Exigent Circumstances) ML18243A1162018-09-0505 September 2018 Exigent 14-day FRN ML18173A1792018-08-0707 August 2018 OEDO-17-00070 - Notice of Issuance of Director'S Decision, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Japan C NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18067A1522018-03-26026 March 2018 Individual Federal Register Notice - Vogtle Electric Generating Plant Units 3 and 4 LAR 17-038 ML18017B0182018-03-0505 March 2018 Federal Register Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity for a Hearing ML18016A6452018-03-0505 March 2018 Transmittal Letter of Federal Register Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity for a Hearing ML17198A3292017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement Letter, Paul Gunter, Beyond Nuclear, Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Jap ML17200A0652017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement FRN, Paul Gunter, Beyond Nuclear, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and NRC-2017-0142, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: July 5,2017-06-19019 June 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: July 5, 2017 ML17153A3782017-06-19019 June 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: July 5, 2017 NRC-2017-0047, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: March 82017-03-0202 March 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: March 8, 201 ML17038A1292017-03-0202 March 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: March 8, 201 ML17003A2422017-01-24024 January 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: February 7, NRC-2016-0240, FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: De2016-11-22022 November 2016 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: Decembe ML16313A1592016-11-22022 November 2016 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: Decembe ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 NRC-2016-0180, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Publication Date: August 30, 20162016-08-18018 August 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Publication Date: August 30, 2016 ML16229A2552016-08-18018 August 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Publication Date: August 30, 2016 NRC-2016-0161, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 20162016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16215A2272016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16145A2252016-06-0707 June 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 2016 NRC-2016-0107, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 20162016-06-0707 June 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 2016 NRC-2016-0100, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 20162016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML16131A7952016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 NRC-2015-0204, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 20152015-08-21021 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 2015 ML15231A8382015-08-21021 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 2015 ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 ML15203A8332015-08-0303 August 2015 Withdrawal of an Amendment Request, Enclosure 1, Federal Register Notice NRC-2014-0271, Withdrawal of an Amendment Request, Enclosure 1, Federal Register Notice2015-08-0303 August 2015 Withdrawal of an Amendment Request, Enclosure 1, Federal Register Notice ML15148A3762015-06-0101 June 2015 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Published June 9, 2015 ML15120A2272015-05-0101 May 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 12, 2015 NRC-2015-0104, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication in April 28, 2015, Federal Register2015-04-20020 April 2015 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication in April 28, 2015, Federal Register ML15106A9162015-04-20020 April 2015 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication in April 28, 2015, Federal Register ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 ML15022A6532015-01-26026 January 2015 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 3, 2015 ML14303A3812014-10-31031 October 2014 Biweekly Sholly FRN - Application and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: November 12, 2014 2024-03-20
[Table view] |
Text
7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos.52-027 and 52-028; NRC-2008-0441]
South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station, Units 2 and 3 AGENCY: Nuclear Regulatory Commission.
ACTION: Termination of licenses.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is terminating the Virgil C. Summer Nuclear Station (VCSNS), Units 2 and 3, Combined Licenses (COLs) designated as NPF-93, and NPF-94, and their included licenses to manufacture, produce, transfer, receive, acquire, own, possess, or use byproduct material. By letter dated December 27, 2017, the South Carolina Electric & Gas Company (SCE&G) requested that the NRC terminate the VCSNS COLs. Although construction was initiated for VCSNS Units 2 and 3, nuclear materials were never possessed under these licenses. Consequently, the VCSNS site is approved for unrestricted use.
DATES: The letter terminating the VCSNS COLs was issued on March 6, 2019.
ADDRESSES: Please refer to Docket ID NRC-2008-0441 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0441. Address questions about NRC Docket IDs in Regulations.gov to Krupskaya Castellon; telephone: 301-287-9221; e-mail: Krupskaya.Castellon@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document.
- NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: William (Billy) Gleaves, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-5848; e-mail: Bill.Gleaves@nrc.gov.
SUPPLEMENTARY INFORMATION:
- l. Background The NRC issued COLs NPF-93, and NPF-94, to SCE&G for VCSNS Units 2 and 3 on March 30, 2012 (ADAMS Package Accession Nos. ML113190371 and ML113190715, respectively). Since issuance of the licenses, SCE&G has procured construction materials and has begun construction on the site. By letter dated August 17, 2017 (ADAMS Accession No. ML17229B487), the NRC received formal notification from SCE&G that VCSNS Units 2 and 3 construction had been stopped and the COLs placed in terminated status, consistent with the Commissions policy statement on deferred and terminated plants. In that letter, SCE&G indicated that it would follow-up with a request to disposition its COLs. SCE&Gs stoppage of construction activities 2
at VCSNS Units 2 and 3, on July 31, 2017, coincided with the departure of most construction workers, support personnel, and managers.
By letter dated December 27, 2017 (ADAMS Accession No. ML17361A088),
SCE&G informed the NRC that it is requesting withdrawal of the COLs, and the included title 10 of the Code of Federal Regulations (10 CFR) parts 30, 40, and 70 licenses for VCSNS Units 2 and 3. Co-licensee Santee Cooper responded to SCE&Gs request for withdrawal of the VCSNS Units 2 and 3 COLs in its January 8, 2018, letter to the NRC (ADAMS Accession No. ML18010A068). Santee Cooper requested that NRC not take action on SCE&Gs COL withdrawal request for 180 days, or such time as might be necessary for Santee Cooper to evaluate whether to seek transfer of the VCSNS Units 2 and 3 COLs. Santee Cooper also raised questions regarding the appropriate regulation for COL withdrawal and the rights of co-licensees in a withdrawal action.
By letter dated January 25, 2018, SCE&G requested an order approving the indirect transfer and control of operating licenses and combined licenses for the VCSNS, Units 1, 2, 3, and the associated Independent Spent Fuel Storage Facility due to the proposed merger between SCANA Corporation and Sedona Corporation, a South Carolina corporation and subsidiary of Dominion Energy. In that letter (ADAMS Accession No. ML18025C035) SCE&G noted that it had previously requested NRC withdraw the combined licenses for VCSNS, Units 2 and 3, and that it sought the indirect transfer of those COLs to the merged corporation if the merger occurred before the COL termination was approved by NRC. The merger between Dominion Energy, Inc., and SCANA Corporation was approved by NRC on August 30, 2018 (ADAMS Accession No. ML18355A996). SCE&Gs obligations as a co-owner and operator under the licenses for VCSNS, Units 1, 2, 3, and the associated Independent Spent Fuel Storage Facility did not change under the merger.
3
By letter dated July 23, 2018, Santee Cooper informed the NRC that it expected the Santee Cooper Board of Directors to resolve the issue of termination of the VCSNS Units 2 and 3 COL on August 20, 2018 (ADAMS Accession No. ML18206A230). The letter further stated that the senior Santee Cooper management would recommend that the VCSNS Units 2 and 3 COLs be terminated. By letter dated January 29, 2019 (ADAMS Accession No. ML19038A225), Santee Cooper informed the NRC that Santee Coopers Board of Directors consented to SCE&Gs request to terminate the VCSNS COLs.
II. License Termination Termination of COLs issued under 10 CFR part 52 is controlled by 10 CFR 52.110, Termination of license. As discussed in Current NRC Staff Views on Applying the 1987 Policy Statement on Deferred Plants (ADAMS Accession No. ML18065B257),
the NRC staff does not apply the requirements for termination in 10 CFR 52.110 to plants that have not begun operation. Requirements for termination of the included licenses under sections 30.36, 40.42, and 70.38 of 10 CFR include the submission of NRC Form 314, or equivalent information. The staff finds that SCE&G met these requirements through the information provided as part of its December 27, 2017, submission.
Along with their December 27, 2017, request to terminate the COLs, SCE&G provided a site redress plan to address the environmental impacts associated with the structures and materials remaining from the partial construction of the site. SCE&G estimates that less than 40 percent of the construction at the site was completed. Most of the environmental impacts outlined in the redress plan include the removal of equipment and structures associated with the halted construction of VCSNS Units 2 and
- 3. SCE&G stated that materials and structures removed would be above grade or in areas that have previously experienced substantial ground disturbance for the original 4
construction of the plant. Some structures and equipment would be abandoned in place.
Redress would also include the removal of oil and lubricants associated with the construction activities in accordance with all applicable federal, state, or local laws and regulations. SCE&G stated that it would conduct periodic site inspections to ensure that none of the equipment or materials are causing environmental, health, or safety problems. SCE&G also stated that it would continue to maintain the site in compliance with all applicable environmental regulations and permit conditions after the termination of the COLs.
As no nuclear materials have been possessed under these licenses, there is no need for a site radiation survey to be conducted under 10 CFR parts 30, 40, or 70. With no radiological contamination associated with the licenses, the VCSNS site may be released for unrestricted use pursuant to 10 CFR 20.1402.
III. Environmental Review SCE&G seeks to terminate the VCSNS Units 2 and 3 COLs, for which nuclear material under these licenses was never brought onsite. Terminating a COL is a licensing action that would ordinarily require an environmental assessment under 10 CFR 51.21, unless a categorical exclusion in 10 CFR 51.22(c) applies and no special circumstances under 10 CFR 51.22(b) exist. Actions listed in 10 CFR 51.22(c) were previously found by the Commission to be part of a category of actions that does not individually or cumulatively have a significant effect on the human environment.
The categorical exclusion identified in 10 CFR 51.22(c)(20) includes:
Decommissioning of sites where licensed operations have been limited to the use of -
(i) Small quantities of short-lived radioactive materials; 5
(ii) Radioactive materials in sealed sources, provided there is no evidence of leakage of radioactive material from these sealed sources; or (iii) Radioactive materials in such a manner that a decommissioning plan is not required by 10 CFR 30.36(g)(1), 40.42(g)(1), or 70.38(g)(1) and the NRC has determined that the facility meets the radiological criteria for unrestricted use in 10 CFR 20.1402 without further remediation or analysis.
This categorical exclusion captures decommissioning activities at sites where contamination from radioactive material is determined to be nominal. In the case of VCSNS Units 2 and 3, no associated radiological contamination exists because nuclear material under these licenses was never brought on site. As a result, a decommissioning plan for this site is not required by 10 CFR 30.36(g)(1), 40.42(g)(1), or 70.38(g)(1), and the site meets the radiological criteria for unrestricted use in 10 CFR 20.1402 without further remediation or analysis. Further, no special circumstances under 10 CFR 51.22(b) apply. The factors listed in 10 CFR 51.22(c)(20) are consistent with the circumstances here because there is no radiological impact associated with the VCSNS COLs, which is even less than the nominal impacts anticipated by the categorical exclusion. Therefore, application of the categorical exclusion to the termination of the VCSNS COLs is warranted. Consequently, in accordance with 10 CFR 51.21, an environmental assessment is not required for the termination of COLs NPF-93 and NPF-94, and their included 10 CFR parts 30, 40, and 70 licenses.
IV. Conclusion As discussed above, the Commission has determined that the VCSNS COL termination request meets the categorical exclusion criteria set forth in 6
10 CFR 51.22(c)(20) and that the unrestricted use criteria pursuant to 10 CFR 20.1402 are met. The Commission grants SCE&Gs request to terminate the COLs designated as NPF-93 and NPF-94, and their included 10 CFR parts 30, 40, and 70 licenses for VCSNS Units 2 and 3. This license termination was effective upon SCE&Gs receipt of NRCs termination letter, dated March 6, 2019 (ADAMS Accession No. ML18198A299).
Dated at Rockville, Maryland, this 8th day of March, 2019.
For the Nuclear Regulatory Commission.
/RA/
Chandulal P. Patel, Acting Chief, Licensing Branch 2, Division of Licensing, Siting, and Environmental Analysis, Office of New Reactors.