Unit 4 - Completion Plan for Uncompleted ITAAC 3.3.00.07d.lll.a (Index Number 803)
ML18191B340
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/09/2018
From:
Southern Nuclear Operating Co
To:
Office of New Reactors
Shared Package
ML18191B337 List:
References
ITAAC 3.3.00.07d.lll.a, ND-18-0813
Download: ML18191B340 (3)


Text

U.S. Nuclear Regulatory Commission ND-18-0813 Enclosure 2 Page 1 of 3 Southern Nuclear Operating Company ND-18-0813 Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.lll.a [Index Number 803]

U.S. Nuclear Regulatory Commission ND-18-0813 Enclosure 2 Page 2 of 3 ITAAC Statement Desion Commitment 7.d) Physical separation Is maintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables.

Inspections. Tests. Analvses Inspections ofthe as-bullt raceways that routeClass 1E cables will be performed to confirm that the separation between raceways that routeClass 1E cables ofdifferent divisions, and between racewaysthat routeClass 1Ecables and racewaysthat routenon-Class1Ecables Isconsistent with the following:

III) Where minimum separation distances are not maintained, the circuits are run In enclosed raceways or barriers are provided.

Acceptance Criteria Resultsofthe Inspection will confirm that the separation between racewaysthat routeClass 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables Is consistent with the following:

lll.a) Where minimum separation distances are notmetInside containment, the circuits are run In enclosed raceways or barriers are provided.

ITAAC Completion Description Multiple ITAAC are performed to ensure that physical separation Ismaintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables. In accordance with this ITAAC, physical separation for circuits thatdo notmeetthe separation distance criteria of ITAAC 3.3.00.07d.ll.a may be provided byenclosed racewaysor barriers. Forcircuits requiring enclosed racewaysor barriers, the subject ITAAC requiresInspections ofthe raceways that route Class 1E cables and raceways that route non-Class 1E cables Inside containment to confirmthat circuits are run Inenclosed raceways or have barriers provided. The Class 1E cables and racewaysand non-Class1 E cables Inside containment are designed to be appropriately separated In accordancewith APP-GW-E1-001 (Reference 1). Installation specifications provided tothe constructor Identify the separation criteria, consistent with the ITAAC commitment.

Class 1E electrical cables, raceways, and barriers are Installed In accordance with design drawings. Installation specifications Issued for construction and work package requirements.

Completed raceway Installation, In-progress and completed cableInstallation, completed cable terminations, and barriers are Inspected to ensure the separation Installation specifications are satisfied. Inspections are performed In accordance with the Construction Quality Verification Program 26139-000-4MP-T81C-N7101 (Reference 2). Thecompleted Inspection records documentthe satisfactory separation between raceways that routeClass 1E cables ofdifferent divisions, and between raceways that routeClass 1E cables and raceways that route non-Class 1E cables.

U.S. Nuclear Regulatory Commission ND-18-0813 Enclosure 2 Page 3 of 3 Cable Separation Reports XXX (References 3 and 4) identify the inspection reports associated withthe raceway separation inspections and confirmthat the separation between raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with th^following:

Where minimum separation distances are not maintained inside containment, the circuits are run in enclosed raceways or barriers are provided.

Exceptions to the subject ITAAC are not included within the scope of this ITAAC and are addressed withinthe scope of ITAAC 3.3.00.07d.iv.a (Enclosure 3) or ITAAC 3.3.00.07d.v.a (Enclosure 4).

The Cable Separation Reports (References 3 and 4) are availablefor NRC inspectionas part of the Unit 3 and Unit 4 ITAAC 3.3.00.07d.iii.a Completion Packages (References 5 and 6, respectively).

List of ITAAC Findings Inaccordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performeda review of all ITAAC findings and associated correctiveactions.

This review found no relevant ITAAC findings associated with this ITAAC.

References favailable for NRC inspection)

1. APP-GW-E1-001, Electrical Systems Design Criteria 2.

26139-000-4MP-T81C-N7101, Bechtel Construction Quality Verification Program 3.

Unit 3 Cable Separation Report XXX 4.

Unit 4 Cable Separation Report XXX 5.

3.3.00.07d.iii.a-U3-CP-Rev0, ITAAC Completion Package 6.

3.3.00.07d.iii.a-U4-CP-Rev0, ITAAC Completion Package 7.

NEI 08-01, "Industry Guideline forthe ITAAC Closure Process Under 10 CFR Part 52"