Text
July 2, 2018 MEMORANDUM TO: Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation FROM: Ekaterina Lenning, Project Manager /RA/
Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF JUNE 14, 2018, CLOSED MEETING WITH WESTINGHOUSE ELECTRIC COMPANY TO DISCUSS RESTART OF WCAP-15942-P-A/WCAP-15942-NP-A, SUPPLEMENT 1, REVISION 1, MATERIAL CHANGES FOR SVEA-96 OPTIMA2 FUEL ASSEMBLIES, TOPICAL REPORT (EPID: L-2018-TOP-0012)
On June 14, 2018, a closed meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and Westinghouse Electric Company (Westinghouse) representatives.
The purpose of the meeting was to discuss the restart of the NRC review of WCAP-15942-P-A/WCAP-15942-NP-A, Supplement 1, Revision 1, Material Changes for SVEA-96 Optima2 Fuel Assemblies, Westinghouse Topical Report (TR). Westinghouse presented supplemental information for their request to restart the NRC review of the WCAP-15942-P-A/WCAP-15942-NP-A, Supplement 1, Revision 1. By letter dated June 13, 2018, Westinghouse submitted a request for restart of the NRC review of WCAP-15942-P-A/WCAP-15942-NP-A, Supplement 1, Revision 1, TR and presentation slides (Agencywide Documents Access and Management System Accession No. ML18164A341).
CONTACT: Ekaterina Lenning 301-415-3151
ML18177A168, Pkg.; ML18144A575, Notice; ML18177A239, Memo *concurrence via email NRC-001 OFFICE NRR/DLP/PLPB/PM NRR/DSS/SNPB/BC* NRR/DLP/PLPB/BC NRR/DLP/PLPB/PM NAME ELenning SKrepel DMorey ELenning DATE 6/26/18 6/26/18 7/2/18/18 7/2/18