2019 Framatome Inspection Schedule (Non-Safeguards)
ML18176A197
Person / Time
Site: Framatome ANP Richland
Issue date: 06/25/2018
From: Eric Michel
NRC/RGN-II/DFFI
To: Travis Tate
Framatome
References
Download: ML18176A197 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 June 25, 2018 Timothy Tate, Manager Environmental, Health, Safety, & Licensing Framatome Inc.

2101 Horn Rapids Road Richland, WA 99352-0130

SUBJECT:

FRAMATOME INC. - CALENDAR YEAR 2019 INSPECTION SCHEDULE

Dear Mr. Tate:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Framatome Inc. Richland facility for calendar year 2019.

The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of the inspector arrival onsite.

Please note that inspections related to safeguards are not included in this schedule. In addition, any regional initiative or other reactive inspection is not included. If circumstances arise which cause us to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact either Noel Pitoniak at (404) 997-4634 or Gregory Goff at (404) 997-4744 with any questions or concerns you may have regarding this letter or the inspection schedule.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 70-1257 License No. SNM-1227

Enclosure:

Framatome Inc. Richland 2019 Inspection/Activity Plan Calendar cc: (See page 2)

T. Tate 2 cc:

Ron Land, Vice President Manufacturing Framatome Inc.

2101 Horn Rapids Road Richland, Washington 99354 Calvin D. Manning, Manager Licensing and Compliance Framatome Inc.

2101 Horn Rapids Road Richland, Washington 99354 Mike Elsen, Director Office of Radiation Protection Department of Health PO Box 47827 Olympia, Washington 98504-7827 Mike.Elsen@doh.wa.gov Earl Fordham, Deputy Director Office of Radiation Protection Department of Health 309 Bradley Boulevard, Suite 201 Richland, Washington 99352

ML18176A197 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DFFI RII:DFFI SIGNATURE /RA/ /RA/

NAME GGoff NPitoniak DATE 6/ 22 /2018 6/ 22 /2018 6/ /2018 6/ /2018 6/ /2018 6/ /2018 6/ /2018 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO Framatome Inc. Richland (70-1257) 2019 Inspection/Activity Plan Calendar NRC Inspection 1 Dates March 4 - 8 Number of Inspectors 2 Inspection Procedures (IPs) IP 88015 Nuclear Criticality Safety Program (1)

IP 88020 Operational Safety (1)

NRC Inspection 2 Dates May 6 - 10 Number of Inspectors 3 Inspection Procedures (IPs) IP 88035 Radioactive Waste Processing, Handling, and Transportation (1)

IP 88030 Radiation Protection (1)

IP 88045 Effluent Control and Environmental Protection (1)

NRC Inspection 3 Dates August 5 - 9 Number of Inspectors 3 Inspection Procedures (IPs) IP 88015 Nuclear Criticality Safety Program (1)

IP 88025 Maintenance and Surveillance of Safety Controls (1)

IP 88070 Plant Modifications (1)

NRC Inspection 4 Dates October 28 - November 1 Number of Inspectors 5 Inspection Procedures (IPs) IP 88020 Operational Safety (1)

IP 88050 Emergency Preparedness (1)

IP 88054 Fire Protection (Triennial) (3)