Forwards Insp Repts 50-280/91-18 & 50-281/91-18 on 910609-0705 & Notice of Violation.Concerns Raised That Violation Involved Failure to Follow &/Or Provide Adequate Procedures for Filling & Venting RCS
ML18153C697
Person / Time
Site: Surry  Dominion icon.png
Issue date: 07/31/1991
From: Sinkule M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18153C698 List:
References
NUDOCS 9108160220
Download: ML18153C697 (3)


See also: IR 05000280/1991018

Text

JUL 3 1 1991

Docket Nos. 50-280, 50-281

License Nos. DPR-32, DPR-37

Virginia Electric and Power Company

ATTN: Mr. W. L. Stewart

Senior Vice President - Nuclear

5000 Dominion ~oulevard

Glen Ailen, VA

23060

Gentlemen:

SUBJECT:

NOTICE OF VIOLATION

(INSPECTION REPORT NOS. 50-280/91~18 AND 50~281/91-18)

This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by

Mr. M. W. Branch of this office on June 9 - July 6, 1991.

The inspection

included a review of activities authorized for your Surry facility.

At the

conclusion of the inspection, the findings were discussed. with those members of

your staff identified in the enclosed inspection report.

Areas examined during the inspection are identified in the report.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative rec*ords, interviews with personnel, and observation of

activities in progress.

Based on the results of this inspection, certain activities appeared to be in

violation of NRC requirements, as specified in the enclosed Notice of Violation

(Notice).

We are concerned about the violation in that there was a failure to

follow and/or to provide adequate procedures for evolutions associated with

filling and venting the reactor coolant system.

In the examples cited, it

appears that the implementation of your new policies associated with procedural

adherence and the adequacy of an upgraded procedure mai not provide you with

adequate controls over plant evolutions.

You are required to respond to this letter and should follow the instructions

specified in the enclosed Notice when preparing your response.

In your

response, you should document the specific actions taken and any additional

actions you pl~n to prevent recurrence. After reviewing your response to this

Notice, including your proposed corrective actions* and the results of future ,

inspections, the NRC will determine whethe( further NRC enforcement action is

necessary to ensure compliance with NRC regulatory requirements.

In accordance with 10 CFR 2. 790 of the NRC' s "Rules of Practice

11

, a copy of

this letter and its enclosures will be placed in the NRC Public Document Room.

The responses directed by this letter and the enclosed Notice are not subject

to the clearance procedures of the Office of Management and Budget as required

by the Paperwork Reduction Act of 1980, Pub. L. No.96-511.

~108160210 91073]

PDR

ADOCK 05000280

Q

PDP

..JL r..),' (j \\_' it5 *


,* .. ---,, !'

.

~ 0

t [ {

Virginia Electric and Power Company

2

JUL 3 1 1991

Should you have any questions concerning this letter, please contact us.

Sincerely,

ORlGTNAL SIGtJEO BY

MARYi~-.! ,V. SlNKULE

Enclosures:

1.

Notice of Violation

2.

NRC Inspection Report

cc w/encls:

E. W. Harrell

Vice President - Nuclear Operations

Virginia Electric & Power Company

5000 Dominion Boulevard

Glen Allen, VA* 23060

J. P. 0

1Hanlon

Vice President - Nuclear Services

Virginia Electric & Power Company

5000 Dominion Boulevard

Glen Allen, VA

23060

M. R. Kansler

Station Manager

Surry Power Station

P. 0. Box 315

Surry, VA

23883

M. L. Bowling, Jr., Manager

Nuclear Licensing

Virginia Electric & Power Co.

5000 Dominion Boulevard

Glen Allen, VA

23060

Sherlock Holmes, Chairman

Marvin V. Sinkule, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Board of Supervisors of Surry County

Surry County Courthouse

Surry, VA

23683

(cc w/encls cont

1d - see page 3)

~I

Virginia Electric and Power Company

(cc w/encls cont'd)

Dr. W. T. Lough

Virginia State Corporation

Commission

Division of Energy Regulation

P. 0. Box 1197

Richmond, VA

23209

Michael W. Maupin

Hunton and Williams

P. 0. Box 1535

Richmond, VA

23212

C. M. G. Buttery,*M.D., M.P.H.

State Health Commissioner

Office of the Commissioner

Virginia Department of Health

P. 0. Box 2448

Richmond, VA

23218

Attorney General

Supreme Court Building

101 North 8th Street

Richmond, VA

23219

Commonwealth of Virginia

b..cc w/ enc 1 s:

~ocument Control Desk

P. Fredrickson, RI!

B. Buckley, NRR

NRC Resident Inspector

U.S. Nuclear Regulatory Commission

Route 1, Box 166

Surry, VA

23883

NRC Resident Inspector

U.S. Nuclear Regulatory Commission

Route *2, Box 78-A

Mineral, VA

23117

RII:DRP

tJ.(

ARuff

07/}i/91

RII~

PFr~dr\\tkson **

0713;/91