ML18153C553

From kanterella
Jump to navigation Jump to search
Maint Assessment Insp Repts 50-280/91-03 & 50-281/91-03 on 910127-0201.No Violations or Deviations Noted.Major Areas Inspected:Followup Assessment of Issues Identified During Special Maint Team Insp Conducted in Spring 1990
ML18153C553
Person / Time
Site: Surry  Dominion icon.png
Issue date: 02/21/1991
From: Blake J, Girard E, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153C552 List:
References
50-280-91-03, 50-280-91-3, 50-281-91-03, 50-281-91-3, NUDOCS 9103050112
Download: ML18153C553 (9)


See also: IR 05000280/1991003

Text

-,

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report Nos.:

50-280/91-03 and 50-281/91-03

L icense*e: Virginia Electric and Power Company

5000 Dominion Boulevard

Glen Allen, VA 23060

.Docket Nos.:

50-280 and 50-281

License Nos.*:

DPR-32 and DPR-37

Facility Name:

Sec::tion

SUMMARY

Scope:

This special, announced inspection was a followup assessment of issues

identified durin9 the special maintenance team inspection conducted in the

Spring of 1990, (as reported in Report No. 50-280~281/90-07).

Results:

The assessment showed that the 1 i censee has made an effort to address the

concerns identified by the maintenance inspection team.

Increased emphasis, in*

the areas of allocation of resources, the role of risk in the maintenance process,

work prioritization, backlog controls, and post maintenance testing, was noted.

9103050112 910225

PDR

ADOCK 05000280

Q

PDR

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • R. Benthall, Supervisor Licensing
  • D. Cristian, Asst Station Manager for Operations and Maintenance
  • J *. Downs, Superintendent of Outage .and Planning
  • R. Gwaltney, Superintendent of Maintenance
  • D. Hart, Supervisor Quality Assurance
  • M. Kansler, Station Manager Surry
  • J. Price, Asst Station Manager for Safety and Licensing
  • R. Scanlan, Licensing Engineer
  • E. Smith Jr., Manager of Quality Assurance
  • T. Sowers, Superintendent of Engineering

Other licensee employees contacted during this inspection included

craftsmen, engineers, security force members,

technicians, and

administrative personnel.

NRC Restdent Inspector

  • S. Tingen, Resident Inspector
  • Attended exit interview

2.

Maintenance Ass~ssment Inspection (TI 2515/108)

This inspection was conducted to assess the effectiveness of corrective

actions taken, by the licensee, as a result of the Maintenance Team

Inspection (MTI) conducted during February and March 1990, at the Surry

Nuclear Plant as feported in R~port No. 50-280,281/90-07 *. The current

inspection of the Surry maintenance program was performed by a two-man

team during January and February 1991 utilizing the guidance given in NRc*

Temporary Instruction 2515/108.

The inspectors concentrated the assessment in the following areas: 1)

material condition of the plant; 2) maintenance areas that were evaluated

as poor, or missing, during the original inspection; and 3) areas that

were not evaluated during the original inspection.

Material Condition of the Plant is reflected in block No. 1.2 of the

Maintenance Inspection T~ee, "Perform Plant Walkdown Inspection."

Maintenance areas that were evaluated as poor, or missing, during the

original inspection were:

2

Section 3.3. Allocate Resources - Poor Implementation.

Sectio.n' 4.3. The Role of Risk in the Maintenance Process -

Missing

Program.

Section 5.5. Perform Work Prioritization - Poor Program

Section 5.7 Establish Backl_og Controls - Poor Performance

Section 5.9 Conduct Post Maintenance Testing~ Poor Program

Areas not evaluated during the o~iginal inspection that were assessed

this time included the. following:

Section 4.6. Safety Review of Maintenance Activities - Program.

3.

Previous Inspection Findings

The following adverse findings were identified by the MT! conducted at

the Surry site during February and March 1990:

.

.

(Closed)

Violation, 50-280,281/90-07-0l, Failure to Follow Procedures

for Maintenance

The licensee response dated June 21, 1990, was considered acceptable by

. Region II. This item involved violation of procedural requirements f_ or

{l) verification of a drawing used in troubleshooting against the

controlled drawing to assure it was the correct change; (2) revision of

drawings to correct breaker capacity changes ttiat resulted from

modifications; (3)-controls on Operations Department measuring and test

equipment (M&TO; and (4) incorporation of vendor information. into

maintenance procedures (e.g., Limitorque Update 89-1 was not

  • incorporated).

The inspectors held discussions with cognizant licensee

personnel and verified examples of the corrective actiori~ stated in the

letter of response.

Three drawings previ~usly found to give incorrect

breaker amperages were verified to have been torrected (Drawing Nos.

11448-FE-llA, -llAC, and -llAE).

Operations M&TE located in a cabinet

near the control room and in the I&C instrument calibration lab was

examined and found to be properly identified and controlled.

Motor

operated valve maintenance procedures ECM-1503-1, ECM-1505-1, and O-MCM-

0305-02 were verified to contain changes based on Limitorque Maintenance

Update 89-1 (cited as not yet *incorporated into maintenance procedures in

the violation description).

The inspectors concluded that the licensee

had determined the full extent of the subject violation, performed the

necessary survey and follow-up actions, and developed the necessary*

corrective actions to preclude recurrence of similar circumstances. The

corrective actions identified in the letter of response had been

implemented.

(Closed)

Unresolved Item 50-280 ,281/90-07-02:

"EDG Day Tank Fuel

Transfer Line Analysis"

3

This i tern concerns a MTI Team observed difference between the

configuration (lack of flexible section) of a Day Tank fuel transfer line*

on the No. 3 Emergency Diesel Generator (EOG} and the same line on the

Nos. 1 and 2 EDGs.

The MTI Team asked for the basis for this difference,

in view of the fact that the applicable drawings indicated that the

flexible section should be included in all three lines. The licensee was

unable to find any documentation that would authodze/support the removal

of the flexible section from the No EOG.

It was presumed that at some

unknown time a maintenance activity necessitated the removal of that

transfer line.

Subsequently, it was further presumed that the flexible

section was lost or damaged, with no like replacement available, so a

ridged replacement was. installed.

As a result. of The MTI Team interest, the licensee performed an analysis

of this matter, documented in EWR 89-660E, and determined that EOG No. 3

was operable, but the lack of .flexibility could in time result in an

eventual fatigue failure.

With this concern in mind EWR 89-660 provided

a procedure for correction.

The replacement parts have been procured and

the work is awaiting a maintenance window for completion. This matter is

  • considered closed.

4.

Maintenance Assessment Results

Section 1.2. Perform Plant Walkdown Inspection.

The inspectors conducted a walkdown itispection of the vital plant areas

including the Auxiliary Building and the Service Water Low Level Intake.

A significant improvement in housekeeping was noted in the Fish Screen

Pump Structures.

The licensee has addressed many of the walkdown items

noted by the M1I Team however the Auxiliary Building lower levels still

needs improvement.

Five MTI Team items were identified with deficiency

.tags, but were not entered into the computer system so no action was or

could be taken.

Corrective action was tak~n on a number of specific

items but similar deficiencies exist in other areas.

Some examples are:*

missing fasteners in electrical boxes; missing washers on equipment; pipe

caps left adrift; uncollected leaks; corrosion on battery terminals;

loose battery connections; thermometer left in a battery;

inoperative

lighting; and portable wheeled. equipment not secured.

On balance the

inspectors noted some improvement, and consider housekeeping and material

condition in general satisfactory.

Section 3.3 Allocate Resources

The inspectors assessed the licensee's allocation of resou~ces through

general observations of plant materiel condition and more detailed

examination of the conditions of and actions being taken to maintain the

Instrument Air (IA) and the Heating, Ventilation and Air Conditioning

(HVAC) Systems.

The IA System (Containment IA in particular) and .the

HVAC System were cited in the MTI as representing examples where

inadequate resources _had been allocated.

Based on their assessment the

inspectors concluded that the licensee's allocation of restiurces should

now be rated satisfactory in program ~nd implementation.

4

Walkdowns of the IA and HVAC Systems' along with other areas of the plant

revealed generally good equipment appearance.-

Some unsatisfactory

conditions were observed~ as described with regard to Section 1.2 above,

but these were considered mi nor as compared to the overa 11 plant

condition.

In some instances both IA and HVAC equipment showed age, as

through rust and other corrosion that had clearly occurred over a long

period of time.

With few exceptibns loose scale from the corrosion had

been removed and paint had been applied where appropriate to improve

appearance.

Some small air leaks were observed in the HVAC System.

Recent IA and HVAC improvements were observed such as new valves and

fittings at some locations in the IA lines, new ducting and bearings for

HVAC equipment, etc.

Discussions with the IA system engineer revealed that the Containment IA

continued below industry standards but that actions were being undertaken

to significantly improve its air quality.* These actions would apparently

require one or two refueling outages.

The licensee plans to replace the

current Containment IA source with Turbine Building IA, which has

relatively good air quality capabilities.

The Turbine Building IA has

sufficient capacity and could now be easily connected to provide

Containment IA.

However, Containment IA is currently recycled and use of

Turbine Building IA would not include recycling, requiring removal of the

air through th~ Containment vacuum system.

Recent testing indicated that

the Unit 1 vacuum system could not remove sufficient air.

This was

believed due to leaks in the system or insufficient pumping capacity,

which cannot be assessed or corrected during operation.

The system

engineer indicated they intend to perform maintenance on the Unit 2

Containment vacuum system during the refueling outage later this year and

perform the test to determine if it can accommodate Turbine Building IA.

The inspectors found evidence of various actions undertaken to maintain

and improve the IA System in the fourth quarter 1990 system engineers

report and in the record of work orders completed on the system since

November 1, 1990.

The record showed 93 work orders completed on the

system, over half of which were preventiv~ maintenance.

Discussions with the HVAC system engtneer indicated overall improvements

in the system but that some areas of significant weakness remained.

A

review of the licen.see's five year plan revealed planned and/or already

undertaken work such as fan motor replacements, upgrading, etc.

The

inspectors also noted scheduled improvements to many other systems in

this plan (e.g., the Emergency Diesel Generator Air Start System).

Recent significant HVAC work included Main Control Room and Emergency

Switchgear Room air conditioning improvements under Design Change 90-15.

The inspectors observed evidence of some of the improvemerits, such as

Unit 1 relay room HVAC equipment modifications which had reportedly

reduced temperatures and the rate of relay failures.

Negative

indications of the application of resources to the HVAC System included

preventive maintenance not being performed due to a lack of personnel,

delays due to a lack of parts, and the large number of work orders

currently open.

The inspectors review of a computer printout of the

licensee's current backlog of HVAC System work orders revealed about 450

5*

open work orders, which appears high compared to the 102 that. were

reportedly (system engineer's report) completed.the last quarter of 1990.

About 25 percent of the work orders closed during that quarter were for

preventive maintenance and the current backlog was found to contain a

similar number.

The system engineer informed the inspectors that

preventive maintenance work orders were no longer *being accomplished as

near the end of 1990 due to insufficient personnel (in subsequent dis-

. cussions with plant management the inspectors were informed that this

condition would be remedied).

Approximately 30 of the work orders in

the current backlog were awaiting receipt of parts.

The inspectors found .that the licensee had not prepared any formal

evaluation of the condition or maintenance needs of the _IA or HVAC

Systems either in response to the MTI or as part of the system engineers

normal activities.

The inspectors considered this a weakness and

licensee management was informed of their concern.

The inspectors had

anticipated that reports of system status and proposals for correction of

deficiencies or impending deficiencies in system capabilities would be

summarized on a periodic basis, perhaps annually, as a routine system

engineering function.

  • *

The inspectors judged the licensee's program for allocation of resources

and its implementation to be satisfactory taking into account the

specific IA and HVAC System findings noted above as-well-as their

observations of the condition of other plant systems and equipment.*

Section 4.3 The Role of Risk in.the Maintenance Process

The inspectors assessed the licensee's program for considering risk in

prioritizing ma_intenance by discussions with cognizant personnel, such as

the corporate Director of .Maintenance Support; and by reviewing the

prioritization process prescribed in the station administrative procedure

for work requests and work orders ( Procedure No. VPAP-2002).

The

inspectors found that the 1 i censee

I s current programmatic requirements

did not provide for any detailed consideration of.risk in prioritizing

maintenance, but that they did (through VPAP-2002) take into account risk

to a limited degree.

The highest priority (Priority 1) was specified to

be assigned to work items which would place a unit in a Limiting

Condition for Operation; affect Technical Specifications; potentially

cause the loss of the unit, redundant systems, or equipment; or *

potentially endanger station personnel or the public. The second hi~hest

was assigned to work whose immediate completion was less critical but

still involved some risk, such as work items that affect or could

potentially affect system or equipment degradation.

The inspectors

judged these requirements to provide a satisfactory consideration of risk

but with need for improvement.

More detai 1 ed understanding and

categorization of priorities on the basis of risk appears desireable.

Also, as noted in the Section 5.5 discussion below, the licensee has not

formally established scheduling requirements based on priority.

The

licensee was found to have work in process to more formally consider risk

in maintenance as through development of reliability centered maintenance.

6

Section 4.6 Safety Review of Maintenance Activities

The inspectors assessed the licensee's program for integration of safety

  • into the maintenance process through discussions with the plant

Supervisor of Safety and Loss Prevention and examination of examples of

documented programmatic instructions.

The program was shown to be

prescribed in the risk management portion of the corporate Policy and

Procedure Manual.

Based on discussions with the supervisor referred to

above, the program implemented at Surry included the following:

A full time supervisor and one contractor, as-well-as two part-time

coordinators to fmplement the program

Safety orientation provided to new employees

First aid teams manned by volunteers

A computerized accident report

Walkdowns utilizing checklists to identify unsafe conditions and

employee practices (unsafe practices observed are recorded and the

involved individual is corrected the first time the practice is

observed - the individual's supervisor is notified in the event of

recurrence)

.

.

Weekly safety meetings for each department except Admi ni strati ve

Services

Quarterly trend reports to identify any significant adverse trends

The inspectors reviewed.the checklist used in walkdowns and found that it*

contained individual items to be checked which included assurance of

proper lighting and ventilation, storage of hazardous materials, use of

electrical tools, fire equipment, etc.

The inspectors also examined an

example of a completed trend report, which appeared to . be properly

completed and informative.

Based on their discussion and review of the safety program as described*

above, the inspectors judged that the licensee had a good program for

integration of safety into the maintenance process.

Section 5.5. Perform Work Prioritization

The MTI identified, as a significant weakness, the fact that the licensee

had no effective prioritization program which was the basis for the

rating of "Poor" for the area of Perform Work Prioritization - Program.

The MTI Team noted that the prioritization scheme as it existed in

February 1990 considered only time as the basis for maintenance

prioritization, and did not consider any of the following factors:

Technical Specification LCO limitations; safety of equipment; safety of

personne 1; or impact on unit generation capacity.

The l i cerisee has

overhauled the maintenance work manag~ment system, which is documented in

7

VAP-2002, Work Request and Work Orders

11

, dated 07 /01/90.

VAP-2002

considers the factors that the MTI Team i dent.i fi ed as * absent in the

previous prioritization scheme.

There does. not appear to be a clear

connection however, between prioritization and scheduling in the present

scheme.

The inspectors consider the new scheme to be a considerable

improvement over the previous scheme, however the priority codes appear

to be too broad to be an effective tool in scheduling work.

Section 5.7 Establish Backlog Controls.

The MTI, identified as a significant weakness, the ineffective control of

the maintenance backlog, as evidenced by an increasing backlog, which was

the basis for a rating of

11 Poor

11 for the area of'Establish Backlog

Control - Implementation.

The. licensee has, since the MTI, made a

concerted effort to enforce the maintenance

11 Plan of the Day

11 (POD) work

schedule.

During the MTI in March of 1990 the licensee was completing

approximately 40% of the items scheduled in the POD., by January of 1991

they are completing approximately 85-90% of POD scheduled items.. The

average age of non outage Corrective Maintenance (CM) Work Orders (WOs)

in January 1990, was approximately 183 days (from a population of 2756),

the average age of non outage C_M WOs in December 1990 was 255 days ( from

a population of 2700).

While the total non outage backlog *(including

both Corrective Maintenance (CM) and Preventive Maintenance (PM)) has

increased by approximately 10% over the past year, the PM to CM ratio has

doubled.

The average daily WO completion rate has increased from 40 to

46 over the peri ad of the last year.

The CM backlog represented

approximately 84 days of work In January 1990, and represents

approximately 77 days of work in January 1991.

It appears that the

licensee is better managing the maintenance backlog as evidenced by_

higher scheduled work completion, doubled PM to CM ratio, the increase in

the WO completfon rate, and the decrease in the time to work off the

backlog.

It does appear that the nature of the backlog is changing in

that the average age is increasing, indicating that the newer WOs are

worked first.

Section 5.9 Conduct Post Maintenance Testing

The MTI, identified as a significant weakness, the lack of an adequately

defined Post Maintenance Test (PMT) program, which was particularly poor

in the electrical maintenance area, and was the basis for a rating of

11 Poor

11 for the area of Conduct Post Maintenance Testing - Program.

At

the end of the MTI, the licensee orally committed, to the Team, that as

temporary corrective action, which would be immediately implemented, they

would require qualified electrical system engineers to specify all PMT on

followers involving electrical work, until their new program is

implemented.

The preceding was documented in NRC Report 50-280,281/90-

07.

It was the NRC

I s understanding that an engineer qualified in

electrical testing (not necessarily a degreed electrical engineer) would

specify electrical PMT.

The licensee, not wanting to require a degreed

electrical engineer to specify electrical PMT, only required a system

engineer to specify electrical PMT (no mention of electrical testing

experience was made).

The licensee documented the same in VEPCO letter

8

Serial No. 90-329A dated October 26, 1990.

Subsequently, the licensee

has established, reviewed a.nd approved, by engineers qualified in

electrical testing, among others, a program with a generic matrix for the

selection of appropriate PMT for electrical maintenance work, for use by

planning personnel who are not engineers qualified in electrical testing.

The licensee indicated that they will implement a computer based matrix

with 10,640 of approximately 13,000 specific Q-List components, by April

15, 1991.

The licensee indicated that they would add the remaining 2,360

Q-L ist components as opportunity, and funds permit. It appears that the

PMT program definition inadequacies have been marginally corrected by the

generic matrix,* and should be fully corrected by the specific computer

based matrix~

There 1till remains a question as to the adequacy of the

electrical PMT specified prior to the implementation of the generic

matrix.

This issue will be examined by a region based electrical

inspector qualified in electrical testing.

5.

Exit Interview

The inspection scope and results were summarized on February 1, 1991,

with those persons indicated in paragraph 1.

The inspectors described

the areas inspected and discussed in detail the inspection results.

Although reviewed during this inspection, proprietary inf~rmation is not

contained in this report. Dissenting comments were not received from the

licensee.

        • -*-. --- - .