Text
-*
Docket Nos. 50-280, 50-281, 50-338, 50-339 License Nos. DPR-32, DPR-37, NPF-4, NPF-7 Virginia Electric and Power Company ATTN:
Mr. W. L. Stewart Senior Vice President - Power 5000 Dominion Boulevard Glen Allen, VA 23060 Gentlemen:
SUBJECT:
MEETING
SUMMARY
- SURRY POWER STATION, DOCKET NOS. 50-280 AND 50-281 NORTH ANNA POWER STATION, DOCKET NQS. 50-338 AND 50-339 This letter concerns the meeting conducted at your request in the Region I I office on January 16, 1990, and attended by NRC personnel and members of your staff. A summary and list of attendees are enclosed.
In accordance with Section 2.790 of the NRC's "Rules 6f Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room.
Should you have any need to discuss these matters further, please feel free to contact us.
Enclosure:
Meeting Summary w/Attachment cc w/encl:
E. W. Harrell Vice President - Nuclear Operations Virginia Electric & Power Company 5000 Dominion Boulevard Glen Allen, VA 23060 cc w/encl:
(Cont'd on Page 2) 900215027~ 90Qj_:_-_~1 F'DR Ar,r,1--D*
F
~-J~ 05000280 pr,,::.
Sincerely, r;*'*
J. Philip Stohr, Director Division of Radiation Safety and Safeguards
Vitginia* Electric and Power Company cc w/encl:
cont'd J.P. 0 1Hanlon Vice President - Nuclear Services Virginia Electric & Power Company 5000 Dominion Boulevard Glen Allen, VA 23060 M. R. Kansler Station Manager SL1rry Power Station P. 0. Box 315 Surry, VA 23883 R. F. Saunders, Manager Nuclear Licensing Virainia Electric & Power Co.
5000 Dominion Boulevard Glen Allen, VA 23060 Sherlock Holmes, Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, VA 23683 W. T. Lough Virginia Corporation Commission Division of Energy Regulation P. 0. Box 1197 Richmond, VA 23209 Michael W. Maupin Hunton and Williams P.O. Box 1535 Richmond, VA 23212 C. M. G. Buttery, M.D., M.P.H.
Department of Health 109 Governor Street
. Richmond, VA 23219 Attorney General Supreme Court Building 101 North 8th Street Richmond, VA 23219 G. E. Kane, Station Manager North Anna Power Station P. 0. Box 402 Mineral, VA 23117 cc w/encl:
(Cont'd on Page 3) 2
Virginia* Electric and Power Company cc w/encl:
cont'd Executive Vice President Old Dominion Electric Cooperative Innsbrook Corporate Center 4222 Cox Road, Suite 102 Glen Allen, VA 23060 William C. Porter, Jr.
County Administrator Louisa County P. 0. Box 160 Louisa, VA 23093 Patrick A. O'Hare Office of the Attorney General Supreme Court Building 101 North 8th Street Richmond, VA 23219 Commonwealth of Virginia bccw/encl:
Document Control De~k NRC Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 78-A Mineral, VA 23117 NRC Resident Inspector U.S. Nuclear Regulatory Commission Route 1, Box 166 Surry, VA 23883
~ss
,~
O ~ WSartor
~
llZ,~90 DCollins l(P/90 3
RI~~-
PFi~dri ckson 1~/90
ENCLOSURE Meeting Summary On January 16, 1990, representatives of Virginia Electric and Power Company met with NRC personnel in Atlanta, Georaia.
Licensee representatives described the meeting as a status report on the emergency preparedness upgrade program. This meeting was the third presentation made regarding EP program improvements since the end of the prior SALP assessment period.
Licensee representatives emphasized during this meeting the progress of their actions by noting that 121 previously designated detail task items had been completed.
These actions continue to address the 19 functional areas for improvement i~entified during an earlier briefing. Discussion alsb addressed the status of the Corporate and Site (Surry and North Anna) EP staff recruitment as well as actions ongoing to correct augmentation response times.
A 1 icensee representative indicated a letter to the NRC was forthcoming that included withdrawal of a previous request to the NRC made concerninq augmentation revisions.
Other issues of mutual interest were discussed in the area of emergency preparedness.
Discussions addressed the routine inspection at Surry Power Station the week of January 8, 1990, and the perception of the program progress.
No commitments were requested; however, a licensee representative indicated that the list of tasks completed would be matrixed aaainst the 19 functional areas to assess progress made in the functional areas and provided to Region II.
Attachment:
List of Attendees
i ATTACHMENT NRC - Virginia Power Mariagement Meeting on January 16, 1990 Virginia Electric and Power Company J. P. O'Hanlon, Vice President - Nuclear Services D. A. Sommers, Supervisor - Licensing J.E. Collins, Supervisor - Emergency Preparednes5 Nuclear Regulatory Commission D. M. Collins, Chief, Emergency Preparedness and Radiological Protection Branch, Division cf Radiation Safety and Safeguards (DRSS)
W. H. Rankin, Chief, Emergency Preparedness Section, DRSS P. E. Fredrickson, Chief, Reactor Projects Section 2A, Division of Reactor Projects W. M. Sartor, Senior Radiation Specialist, DRSS M. J. Morgan. Examiner, Division of Reactor Safety