ML18153A960

From kanterella
Jump to navigation Jump to search

Requests That Alternate Testing Identified in Relief Requests P-16 & V-46,be Extended Through End of Next Scheduled Surry Unit 1 Refueling Outage,Currently Scheduled for Third Quarter of 1995
ML18153A960
Person / Time
Site: Surry 
Issue date: 06/02/1994
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
94-324, TAC-M80297, TAC-M80298, NUDOCS 9406090161
Download: ML18153A960 (2)


Text

' '

\\

e e

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 June 2, 1994 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen, VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 INSERVICE TESTING PROGRAM ASME SECTION XI INSTRUMENTATION Serial No.

SPS/ETS Docket Nos.

License Nos.94-324 50-280 50-281 DPR-32 DPR-37 By NRC letter dated June 26, 1992, (TAC Nos. M80297 and M80298) Surry Power Station was granted interim relief from the requirements of Section XI of the ASME Boiler and Pressure Vessel Code for certain components in the service water side of the Main Control Room and Emergency Switchgear Room Air Conditioning System.

The basis for Relief Requests P-16 and V-46, in the Unit 1 lnservice Testing Program, was that flow and inlet pressure instrumentation needed to be purchased and installed before the Code requirements could be met. These instruments were to be purchased and installed by the second quarter of 1994 at which point compliance with the Code would be achieved.

Flow and inlet pressure instrumentation were installed during the recent Unit 1 refueling outage. However, extensive preservice testing of the flow instrumentation has revealed that the instruments are not reading the full system flow. The problem appears to be associated with instrument configuration and highly silted service water.

The preservice testing of the newly installed suction pressure gauges has produced erratic results. Additional evaluation is necessary to determine if either the the erratic pressure readings can be eliminated or the configuration must be redesigned.

An engineering effort has been initiated to redesign the flow instrumentation and to evaluate and possibly redesign the suction pressure gauge configuration.

The redesign of the flow instrument is planned to be completed and installed by the end of the next Surry Unit 1 outage. The evaluation and possible redesign and installation, if necessary, of the suction pressure configuration will also be completed by the end of the next Surry Unit 1 outage. In the interim, Surry Power Station requests that the alternate testing, identified in Relief Requests P-16 and V-46, be extended through the end of the next scheduled Surry Unit 1 refueling outage, currently scheduled for the third quarter of 1995. The alternate testing includes pump and condenser differential 9406090161 940602-~~.

~DR ADOCK 05000280 PDR

~-

e pressur~ for flow measurement and disassembly and inspection of the valves.

If you have any questions, please contact us.

Very truly yours, L/ovf/M-ev 'y CWc~

James P. O'Hanlon Senior Vice President-Nuclear cc:

U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, N.W.

Atlanta, Georgia 30323 Mr. Morris Branch NRC Senior Resident Inspector Surry Power Station