Forwards SER Approving Util Requested Approval of Proposed Reactor Vessel Fluence Analysis Methodology Described in Topical Rept VEP-NFA-3 Subject to Listed Limitations
ML18152B643
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 04/13/1999
From: Edison G, Kalyanam N
NRC (Affiliation Not Assigned)
To: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18152B644 List:
References
RTR-REGGD-XX.XXX, TASK-*****, TASK-RE GL-92-01, GL-92-1, TAC-MA0555, TAC-MA0556, TAC-MA0576, TAC-MA0577, TAC-MA555, TAC-MA556, TAC-MA576, TAC-MA577, NUDOCS 9904160216
Download: ML18152B643 (4)


Text

..

Mr. J. P. O'Hanlon Senior Vice President -~lear Virginia Electric and Power Company 5000 Dominion Blvd.

Apri l 13, 199.

Glen Allen, Virginia 23060

SUBJECT:

NORTH ANNA POWER STATION, UNITS 1 AND 2, AND SURRY POWER STATION, UNITS 1 AND 2-REACTOR VESSEL FLUENCE ANALYSIS METHODOLOGY (GENERIC LETTER 92-01, REVISION 1, SUPPLEMENT 1)

(TAC NOS. MA0555, MA0556, MA0576, AND MA0577)

Dear Mr. O'Hanlon:

The purpose of this letter is to approve your proposed Reactor Vessel Fluence Analysis Methodology for referencing in licensing actions for North Anna Power Station, Units 1 and 2, and Surry Power Station, Units 1 and 2.

In your letter dated June 18, 1998, you submitted information and requested approval of your proposed reactorvessel fluence analysis methodology described in the topical report VEP-NAF-3, Reactor Vessel Fluence Analysis Topical Report. Our approval of this methodology is subject to the following limitations:

4.

it is applicable only to the Surry and North Anna plants;

5.

if the assumed load factor of 0.90 changes and the method is used for the estimation of projected fluence values, the value of the load factor will be adjusted accordingly; and

6.

the licensee will assure compliance with draft regulatory guide DG-1053 when it is published in its final form.

Our safety evaluation of the proposed methodology is.enclosed. Any questions may be directed to G. E. Edison at 301-415-1448 or to N. Kalyanam at 301-415-1480.

Sincerely, Original signed by:

Gordon E. Edison, Sr. Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-338, 50-339, 50-280, and 50-281

Enclosure:

As stated cc w/encl: See next page FILE NAME - G:\\SURRY\\0576L TR.WPD OFFICE PM:PDII NAME DATE COPY Sincerely, Original signed by:

N. Kalyailam, Project Manager, Section 1 Project Directorate 11 Division of Licensing Project Management Office of Nuclear Reactor Regulation Distribution:

See next page SC:PDII REmch r-1 9904160216 990413 1

PDR ADOCK 05000280

\\

I i

P PDR

e e

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 13, 1999 Mr. J. P. O'Hanlon Senior Vice President - Nuclear Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060

SUBJECT:

NORTH ANNA POWER STATION, UNITS 1 AND 2, AND SURRY POWER STATION, UNITS 1 AND 2 - REACTOR VESSEL FLUENCE ANALYSIS METHODOLOGY (GENERIC LETTER 92-01, REVISION 1, SUPPLEMENT 1)

(TAC NOS. MA0555, MA0556, MA0576, AND MA0577)

Dear Mr. O'Hanlon:

The purpose of this letter is to approve your proposed Reactor Vessel Fluence Analysis Methodology for referencing in licensing actions for North Anna Power Station, Units 1 and 2, and Surry Power Station, Units 1 and 2.

. In your letter dated June 18, 1998, you submitted information and requested approval of your proposed reactor vessel fluence analysis methodology described in the topical report VEP-NAF-3, Reactor Vessel Fluence Analysis Topical Report. Our approval of this methodology is subject to the following limitations:

1.

it is applicable only to the Surry and North Anna plants;

2.

if the assumed load factor of 0.90 changes and the method is used for the estimation of projected fluence values, the value of the load factor will be adjusted accordingly; and

3.

the licensee will assure compliance with draft regulatory guide DG-1053 when it is published in its final form.

Our safety evaluation of the proposed methodology is enclosed. Any questions may be directed to G. E. Edison at 301-415-1448 or to N. Kalyanam at 301-415-1480.

Sincerely, Gordon E. Edison, Sr. Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-338, 50-339, 50-280, and 50-281

Enclosure:

As stated cc w/encl: See next_page Sincerely,

~~

N. Kalyanam, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation

Virginia 6:lectric & Power Company Mr. J. Jeffrey Lunsford County Administrator, Louisa County P.O. Box 160 Louisa, Virginia 23093 Donald P. Irwin, Esq.

Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, Virginia 23219 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, Virginia 23209 Old Dominion Electric Cooperative 4201 Dominion Boulevard Glen Allen, Virginia 23060 J. H. McCarthy, Manager Nuclear Licensing and Operations Support Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, Virginia 23060 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission 1024 Haley Drive Mineral, Virginia 23117 Senior Resident Inspector Surry Power Station, US Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 e

Robert B. Strobe, M.D., M.P.H.

State Health Commissioner Office of the Commissioner Virginia Department of Health P.0. Box 2448 Richmond, Virginia 23218 W. R. Matthews Site Vice President North Anna Power Station Virginia Electric and Power Company P.O. Box 402 Mineral, Virginia 23117 J.P. O'Hanlon Senior Vice President - Nuclear Virginia Electric and Power Co.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, Virginia 23060 Mr. Eugene S. Grecheck Site Vice President Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683

Di~tributi~n for letter dated Apri 1 13, 1999 m~aet i::n:e_ ~::.

PUBLIC PD II Rdg.

J. Zwolinski H. Berkow E. Dunnington G. Edison N. Kalyanam R. Caruso L. Lois e-mail RCN - SE only OGC ACRS R. Haag, RII