MONTHYEARML18152B3571999-10-22022 October 1999 Requests Relief from Temporary Repair of Through Wall Leak Discovered on 30 Inch Component Cooling Heat Exchanger Discharge Pipe Associated with Service Water Sys Common to Surry Units 1 & 2 ML20217K4391999-10-18018 October 1999 Provides Response to RAI to Support USI A-46 Program Submittal for North Anna Power Station,Units 1 & 2.Rev 10 to BNL Rept 52361,encl ML20217H3301999-10-14014 October 1999 Forwards Rev 0 to COLR for North Anna 2 Cycle 14 Pattern Su. No New Commitments Intended by Ltr ML18152B3581999-10-14014 October 1999 Submits Response to Violations Noted in Insp Repts 50-280/98-201 & 50-281/98-201.Corrective Actions:Visual Insps Were Completed on Accessible Coatings Inside Containment for Both Units 1 & 2 ML18152B3541999-10-12012 October 1999 Requests Use of Code Case N-532 & N-619,per Provisions of 10CFR50.55a(a)(3).Detailed Info Supporting Request,Encl. Attachment 2 Includes Technical White Paper That Provides Further Technical Info ML20216K1681999-10-0101 October 1999 Forwards Vols I-VIII of Rev 35 to UFSAR for Naps.Rev Also Includes Update to Chapter 17 of Ufsar,Which Contains Operational QA Program.Changes to Program Description Do Not Reduce Commitments Contained Therein ML20212J9101999-10-0101 October 1999 Forwards SE Accepting Licensee 990916 & 27 Relief Requests IWE-3 for Plant.Se Addresses Only IWE-3 Due to Util Urgent Need for Relief.Requests IWE-7 & IWE-8 Will Be Addressed at Later Date ML18152B3391999-09-27027 September 1999 Forwards Revised Relief Request IWE-3,which Now Includes Addl Visual Exam Requirement After post-repair or Mod Pressure Testing Is Completed,Per Telcon with NRC ML18152B3401999-09-27027 September 1999 Requests That Ma Walker Be Removed from List of Individuals Scheduled to Take Exam IAW Guidance Provided in NUREG-1021, Operator Licensing Exam Stds for Power Reactors ML18152B3351999-09-24024 September 1999 Forwards SE Granting Relief Requested for Facility in Relief Request SR-026 Re ISI Programs ML20212G5091999-09-22022 September 1999 Forwards in Triplicate,Applications for Renewal of Licenses for Listed Individuals.Encls Withheld,Per 10CFR2.790(a)(6) ML18152B3381999-09-21021 September 1999 Forwards in Triplicate,Applications for Renewal of License for Bf Jurewicz & JW Heide.Without Encls ML18152B3331999-09-17017 September 1999 Forwards Revised 180-day Response to NRC GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML18152B6671999-09-17017 September 1999 Forwards Two NRC Forms 536,containing Info on Proposed Site Specific Operator Licensing Exam Schedules & Estimated Number of Applicants Planning to Take Exams And/Or Gfes,In Response to NRC Administrative Ltr 99-03 ML18152B3341999-09-16016 September 1999 Requests Relief from Specific Requirements of Subsection IWE of 1992 Edition with 1992 Addenda of ASME Section XI Re Containment Liner Examination Requirements,For North Anna & Surry Power Stations ML20216E6661999-09-10010 September 1999 Forwards Analysis of Capsule W Virginia Power North Anna Unit 1 Nuclear Power Plant Reactor Vessel Matl Surveillance Program, for Capsule Withdrawn on 980922 ML20211N2531999-09-0808 September 1999 Responds to Request to Exceed 60,000 Mwd/Mtu Lead Rod Burnup in Small Number of Fuel Rods in North Anna Unit 2.Informs That NRC Offers No Objection to Requested Use of Rods in Reconstituted Fuel Assembly.Se Supporting Request Encl ML18152B4501999-09-0808 September 1999 Submits in Triplicate,Application for Renewal of License for Rd Scherer,Iaw 10CFR55.57.Requests That Certification of Medical Exam by Facility Licensee,Nrc Form 396,be Withheld from Public Disclosure,Per 10CFR2.790(a)(6) ML20216F1381999-09-0808 September 1999 Forwards Retake Exam Repts 50-280/99-302 & 50-281/99-302 on 990824.One SRO Applicant Who Received re-take Operating Test Passed re-take Exam ML18152B4471999-09-0101 September 1999 Requests That NRC Remove Listed Labels from Distribution ML20211L9151999-09-0101 September 1999 Forwards Response to NRC Request for Comments Re Closure of Review of Response to GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity ML18151A6301999-09-0101 September 1999 Submits Summary of 990812-13 Training Managers Conference on Recent Changes to Operator Licensing Program.Meeting Covered Changes to Regulations,Examination Stds,New Insp Programs & Other Training Issues.List of Attendees Encl ML20211J2211999-08-31031 August 1999 Approves Request to Remove Augmented ISI (Aii) Program for RCS Bypass Lines from North Anna Licensing Basis.Se Re Request to Apply LBB to Eliminate Augmented Insp Program on RCS Bypass Lines Encl ML18152B3701999-08-30030 August 1999 Informs That Virginia Electric & Power Co Hereby Granted Approval to Submit Original & One Paper Copy & 6 CD-ROM Copies of Updates to FSAR as Listed,In Response to ,Requesting Exception to 10CFR50.4(b)(6) 05000280/LER-1999-005, Forwards LER 99-005-00,per Plant TS Table 3.7.6.Rept Has Been Reviewed by Station Nuclear Safety & Operating Committee.Commitment Made by Util,Listed1999-08-27027 August 1999 Forwards LER 99-005-00,per Plant TS Table 3.7.6.Rept Has Been Reviewed by Station Nuclear Safety & Operating Committee.Commitment Made by Util,Listed ML20211H4131999-08-27027 August 1999 Informs That Util Revised Encl Bases for TS 2.2.1, Reactor Trip Sys Instrumentation Setpoints, Discussing Steam Flow/ Feed Flow Mismatch Portion of Steam Flow/Feed Flow Mismatch & Low SG Water Level Reactor Trip Setpoint ML18152B3691999-08-25025 August 1999 Forwards Copy of FEMA Region III Ltr to VA State Coordinator for Dept of Emergency Svcs.Ltr Provides Basis for Deficiency Identified During Plant Radiological Emergency Preparedness Exercise Conducted 990803 ML18152B3611999-08-23023 August 1999 Discusses GL 97-05, SG Tube Insp Techniques, Issued by NRC on 971217 & VEPCO Responses for Surry Power Station ,980910,981028,990428 & 990517.Forwards SE Supporting VEPCO Approach for Dispositioning Tubes with Avb Wear Signs ML20138B3241999-08-23023 August 1999 Forwards Draft Response to Question 1 Re NAPS USI A-46 ML18152B3811999-08-23023 August 1999 Forwards Safety Evaluation,Granting Relief Request IWL-3 Re ISI Programs,Per Util ML16342A8811999-08-23023 August 1999 Forwards Emergency Response Data Sys (ERDS) Implementation Documents for Listed Plants.Changes Should Be Made to ERDS as Soon as Possible.Without Encl ML18152B3851999-08-23023 August 1999 Forwards Revised TS Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in Ufsar.Ref to Applicable UFSAR Section Included in TS Basis ML18152B3651999-08-20020 August 1999 Requests Removal of License Condition from Sh Wightman Operator License SOP-21538.Updated NRC Form 396 Is Encl.Form NRC 396 Withheld,Per 10CFR2.790(a)(6) ML18152B3661999-08-20020 August 1999 Provides Medical Status Rept for E Washington,As Required by License Conditions.Summary of E Washington Current Physical Exam & Pertinent Lab Data Attached.Encl Withheld,Per 10CFR2.790(a)(6) ML18152B3681999-08-20020 August 1999 Submits 30-day Rept Re Two Instances in Which Conditions of Approval in Coc Were Not Observed in Making Shipment.Two Type B Shipments Using Model CNS 8-120B Package Were Made After Expiration of QA Program Approval Between 990531-0628 ML20211D9041999-08-20020 August 1999 Forwards Revised Pages to Third Ten Year ISI Program & Relief Requests, Replacing Pages in 990408 Submittal ML18152B3801999-08-18018 August 1999 Forwards Technical Rept NE-1206,Rev 0, Surry Unit 2,Cycle 16 Startup Physics Tests Rept, Summarizing Results of Physics Testing Program Performed After Initial Criticality on 990525 ML20211B3871999-08-17017 August 1999 Requests Permission to Routinely Discharge from SW Reservior to Waste Heat Treatment Facility Under Existing Vpdes Permit Through Outfalls 108 & 103.Discharges Are Scheduled to Commence on 990907,due to High Priority Placed on Project ML20210T0671999-08-13013 August 1999 Informs of Completion of Review of Proposed Revs of Schedule for Withdrawal of Rv Surveillance Capsules Submitted by VEPCO on 981217.Approves Proposed Revs.Forwards Safety Evaluation ML18152B3781999-08-13013 August 1999 Forwards ISI Summary Rept for Surry Power Station,Unit 2 for 1999 Refueling Outage.Rept Provides Summary of Examination Performed During Outage for Third ISI Interval.No New Commitments Were Made 05000280/LER-1999-004, Forwards LER 99-004-00,IAW 10CFR50.73.Commitment Made by Util,Listed1999-08-13013 August 1999 Forwards LER 99-004-00,IAW 10CFR50.73.Commitment Made by Util,Listed ML20210Q9841999-08-12012 August 1999 Forwards Rev 1 to Vepc COLR for North Anna Unit 2,Cycle 13 Pattern Ud, Per TS 6.9.1.7.d.COLR Was Revised to Include Temp Coastdown Operation at End of Cycle 13 ML18152B3741999-08-11011 August 1999 Forwards Preliminary Accident Sequence Precursor Analysis of Operational Condition Which Was Discovered at Surry Power Station,Unit 1 on 980509 & Reported in LER for Review & Comment ML20210Q7661999-08-0606 August 1999 Requests Exception to 10CFR50.4 Requirement to Provide Total of Twelve Paper Copies When Submitting Surry & North Anna UFSAR Updates.Seek Approval to Submit Only Signed Original & One CD-ROM Version,Per Conversation with J Skoczlas ML18152B4081999-08-0606 August 1999 Forwards Response to NRC 990520 & 0525 RAIs Re North Anna & Surry Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML18152B4091999-08-0505 August 1999 Forwards Vepc semi-annual fitness-for-duty Program Performance Data Rept for 990101-990630,IAW 10CFR26.71(d) ML18152B3731999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006 at North Anna & Surry. Requests Info Re Individuals Taking Exam,Personnel Who Will Have Access to Exam.Sample Registration Ltr Encl ML20210N2921999-08-0505 August 1999 Discusses Which Submitted Proposed TSs Bases Change for Containment Leakage. Licensee Changes to Bases May Be Subj to Future Insps or Audits ML20210J8861999-08-0202 August 1999 Provides Clarification to Commitment Made in Identifying Extent by Which Existing Plant Design Complied with RG 1.97,specifically Re Variable, Radiation Exposure Rate ML18152B4051999-08-0202 August 1999 Forwards Insp Repts 50-280/99-04 & 50-281/99-04 on 990523-0703.No Violations Noted 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20212J9101999-10-0101 October 1999 Forwards SE Accepting Licensee 990916 & 27 Relief Requests IWE-3 for Plant.Se Addresses Only IWE-3 Due to Util Urgent Need for Relief.Requests IWE-7 & IWE-8 Will Be Addressed at Later Date ML18152B3351999-09-24024 September 1999 Forwards SE Granting Relief Requested for Facility in Relief Request SR-026 Re ISI Programs ML20216F1381999-09-0808 September 1999 Forwards Retake Exam Repts 50-280/99-302 & 50-281/99-302 on 990824.One SRO Applicant Who Received re-take Operating Test Passed re-take Exam ML20211N2531999-09-0808 September 1999 Responds to Request to Exceed 60,000 Mwd/Mtu Lead Rod Burnup in Small Number of Fuel Rods in North Anna Unit 2.Informs That NRC Offers No Objection to Requested Use of Rods in Reconstituted Fuel Assembly.Se Supporting Request Encl ML18151A6301999-09-0101 September 1999 Submits Summary of 990812-13 Training Managers Conference on Recent Changes to Operator Licensing Program.Meeting Covered Changes to Regulations,Examination Stds,New Insp Programs & Other Training Issues.List of Attendees Encl ML20211J2211999-08-31031 August 1999 Approves Request to Remove Augmented ISI (Aii) Program for RCS Bypass Lines from North Anna Licensing Basis.Se Re Request to Apply LBB to Eliminate Augmented Insp Program on RCS Bypass Lines Encl ML18152B3701999-08-30030 August 1999 Informs That Virginia Electric & Power Co Hereby Granted Approval to Submit Original & One Paper Copy & 6 CD-ROM Copies of Updates to FSAR as Listed,In Response to ,Requesting Exception to 10CFR50.4(b)(6) ML18152B3691999-08-25025 August 1999 Forwards Copy of FEMA Region III Ltr to VA State Coordinator for Dept of Emergency Svcs.Ltr Provides Basis for Deficiency Identified During Plant Radiological Emergency Preparedness Exercise Conducted 990803 ML16342A8811999-08-23023 August 1999 Forwards Emergency Response Data Sys (ERDS) Implementation Documents for Listed Plants.Changes Should Be Made to ERDS as Soon as Possible.Without Encl ML18152B3811999-08-23023 August 1999 Forwards Safety Evaluation,Granting Relief Request IWL-3 Re ISI Programs,Per Util ML18152B3611999-08-23023 August 1999 Discusses GL 97-05, SG Tube Insp Techniques, Issued by NRC on 971217 & VEPCO Responses for Surry Power Station ,980910,981028,990428 & 990517.Forwards SE Supporting VEPCO Approach for Dispositioning Tubes with Avb Wear Signs ML20210T0671999-08-13013 August 1999 Informs of Completion of Review of Proposed Revs of Schedule for Withdrawal of Rv Surveillance Capsules Submitted by VEPCO on 981217.Approves Proposed Revs.Forwards Safety Evaluation ML18152B3741999-08-11011 August 1999 Forwards Preliminary Accident Sequence Precursor Analysis of Operational Condition Which Was Discovered at Surry Power Station,Unit 1 on 980509 & Reported in LER for Review & Comment ML20210N2921999-08-0505 August 1999 Discusses Which Submitted Proposed TSs Bases Change for Containment Leakage. Licensee Changes to Bases May Be Subj to Future Insps or Audits ML18152B3731999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006 at North Anna & Surry. Requests Info Re Individuals Taking Exam,Personnel Who Will Have Access to Exam.Sample Registration Ltr Encl ML18152B4051999-08-0202 August 1999 Forwards Insp Repts 50-280/99-04 & 50-281/99-04 on 990523-0703.No Violations Noted ML18152B4021999-08-0202 August 1999 Discusses Closure of Review of Response to GL 92-01,Rev 1, Suppl 1, Rv Structural Integrity, for Plant,Units 1 & 2. Staff Released Info as Rvid Version 2 Based on Review ML20209E3711999-07-0202 July 1999 Forwards Insp Repts 50-338/99-03 & 50-339/99-03 on 990425-0605.Violations Being Treated as Noncited Violations ML18152B3951999-06-30030 June 1999 Informs That Effective 990706,GE Edison Has Been Assigned as Project Manager,Project Directorate II-1,for North Anna Power Station.Edison Will Continue in Assignment as Project Manager for Surry Power Station ML20196G2581999-06-23023 June 1999 Discusses Closure of GL 92-01,rev 1,suppl 1,reactor Vessel Structural Integrity IR 05000280/19990031999-06-18018 June 1999 Forwards Insp Repts 50-280/99-03 & 50-281/99-03 on 990411-0522.Two Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML18152B4321999-06-10010 June 1999 Forwards RAI Re Fire Analyses in Ipeee.Response Requested by 990705 ML18152B4191999-05-25025 May 1999 Advises That Structural Integrity Evaluation Provided 990330 Has Been Reviewed & Addl Info Requested.Staff Inquiries Encl in Form of RAI ML18152B4241999-05-25025 May 1999 Forwards Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Valves. Target Date of 990816 Was Agreed Upon for Response ML20206U7441999-05-20020 May 1999 Informs That NRC Unable to Conclude That NAPS Has Met Intent of Supplement 4 to GL 88-20.RAI Re Fire Area of IPEEE Encl. Response Requested within 90 Days of Submittal Date ML20207A8541999-05-20020 May 1999 Forwards RAI Re Licensee Listed Responses to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Response Requested within 90 Days of Submittal Date ML18152B4201999-05-20020 May 1999 Informs That on 990514,D Llewellyn & Author Confirmed Initial Operator Licensing Exam Schedule for Year 2000. Initial Exam Dates Rescheduled for Weeks of Sept 18 & 25, 2000 for Approx 11 Candidates for North Anna & 13 for Surry ML20217D6621999-05-14014 May 1999 Forwards NRC Operator Licensing Exams 50-280/99-301 & 50-281/99-301 (Including Completed & Graded Exams) for Tests Administered on 990329-0401 & 990412-15.Nine Candidates Passed (& One Failed) Exam ML18152B4151999-05-14014 May 1999 Informs That NRR Reorganized,Effective 990328.Forwards Organization Chart ML20206L4661999-05-10010 May 1999 Forwards SE Accepting Request to Delay Submitting Plant, Unit 1 Class Piping ISI Program for Third Insp Interval Until 010430,to Permit Development of Risk Informed ISI Program for Class 1 Piping ML20206P6401999-05-0505 May 1999 Refers to Public Meeting Conducted at North Anna Power Station on 990413 to Discuss Results of North Anna Plant Performance Review.List of Attendees Encl ML20205S0321999-04-21021 April 1999 Forwards SER Accepting Util 980804 Requests for Relief from Certain Requirements of Subsections IWE & Iwl of 1992 Addenda of ASME Section Xi.Alternatives for IWE2,IWE4,IWE6 & IWL2,authorized Pursuant to 10CFR50.55a(a)(3)(ii) ML18152B6461999-04-14014 April 1999 Informs That Relief Requests IWE-2,4,5,6 & IWL-2 Re ISI Program Granted.Forwards SE Re Requests ML18152B6431999-04-13013 April 1999 Forwards SER Approving Util Requested Approval of Proposed Reactor Vessel Fluence Analysis Methodology Described in Topical Rept VEP-NFA-3 Subject to Listed Limitations ML20205Q2451999-04-12012 April 1999 Forwards Insp Repts 50-338/99-01 & 50-339/99-01 on 990131- 0313.Three Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML18152B6521999-04-0909 April 1999 Informs That on 990406,H Mccallum & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Dates Scheduled for Wks of 000925 & 1002 for Approx 13 Candidates ML20205T1411999-04-0909 April 1999 Informs That on 990407,A Royal & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Dates Scheduled for Wks of 000925 & 1002 for Approx 11 Candidates ML18153A3431999-04-0101 April 1999 Discusses Completion of Licensing Action for GL 97-04, Assurance of Sufficient NPSH for ECC & Containment Heat Removal Pumps. Info Re GL 97-04 Provided IR 05000280/19990011999-03-29029 March 1999 Forwards Insp Repts 50-280/99-01 & 50-281/99-01 on 990117-0227.Three Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20196K9891999-03-29029 March 1999 Confirms Plans to Hold Meeting on 990413 at North Anna Nuclear Information Center to Discuss North Anna Plant Performance Review ML20196L0021999-03-24024 March 1999 Discusses Plant Performance Review of North Anna Power Station Completed by NRC on 990205.Found Overall Performance at North Anna to Be Acceptable.Several Examples of Inadequate or Untimely Problem Resolution Were Noted ML20205B5641999-03-24024 March 1999 Forwards Audit Rept of North Anna Power Station,Units 1 & 2 Conducted on 990126-28 in Glen Allen,Va.Audit Team Assessment of Y2K Project Plan Identified Plan as well-structured,well Organized & Well Implemented ML18153A2691999-03-23023 March 1999 Advises of NRC Planned Insp Effort Resulting from Surry Plant Performance Review for Period March 1998 Through Jan of 1999.Historical Listing of Plant Issues & Details of Insp Plan for Next Eight Months Encl ML20207E1331999-03-0101 March 1999 Forwards Insp Repts 50-338/98-11 & 50-339/98-11 on 981220- 990130.No Violations Noted.Util Conduct of Activities at North Anna Power Station Generally Characterized by Safety Conscious Plant Operations & Good Maintenance ML20203F8681999-02-16016 February 1999 Forwards Request for Addl Info Re Util 970527 plant-specific Summary Rept in Response to USI A-46 Program at North Anna Power Station,Units 1 & 2 ML18152B5361999-02-16016 February 1999 Forwards SER Approving Use of ASME Code Case N-498-1 at Surry Unit 1.Code Case Provides for Alternate Rules for 10-year Hydrostatic Pressure Testing for Class 1,2 & 3 Systems,Section Xi,Division 1 of ASME Code IR 05000280/19980101999-02-12012 February 1999 Forwards Insp Repts 50-280/98-10 & 50-281/98-10 on 981206-0116.No Violations Noted ML18152B5391999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Either Ltr Indicating No Candidates or Listing of Candidates for Exam ML20196K3681999-01-21021 January 1999 Discusses Closure of Tasks Re Generic Implication of part- Length Control Rod Drive Mechanism Housing Leak at Prairie Island,Unit 2 & Anna Power Station,Units 1 & 2 ML20199K3221999-01-14014 January 1999 Forwards Insp Repts 50-338/98-10 & 50-339/98-10 on 981108- 1219.No Violations Identified.Conduct of Activities at North Anna Power Station Generally Characterized by safety-conscious Plant Operations 1999-09-08
[Table view] |
Text
e e
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555--0001 Mr. J.P. O'Hanlon Senior Vice President - Nuclear Virginia Electric and Power Company 5000 Dominion Blvd.
Glen Allen, Virginia 23060 August 23, 1999
SUBJECT:
NORTH ANNA POWER STATION UNITS 1 AND 2, AND SURRY POWER STATION UNITS 1 AND 2 RE: ASME SECTION XI RELIEF REQUEST, SUBSECTION IWL (TAC NOS. MA4823, MA4824, MA4857, AND MA4858)
Dear Mr. O'Hanlon:
The purpose of this letter is to grant the relief you requested for North Anna Power Station, Units 1 and 2, and Surry Power Station, Units 1 and ?, in relief request IWL-3 related to your inservice inspection programs.
In your letter dated February 11, 1999, you stated that Surry Power Station, Units 1 and 2, are presently in the third 10-year inservice inspection (ISi) interval, and the examinations are conducted to meet the requirements of the 1989 Edition of American Society of Mechanical Engineers (ASME)Section XI. Also, you stated that North Anna Power Station, Units 1 and 2, are presently in the second 10-year ISi interval, and examinations are conducted to the requirements of the 1983 Edition, Summer 1983 Addenda, and 1986 Edition of ASME Section XI, respectively. In a Federal Register (FR) notice dated August 8, 1996 (61 FR 41303), NRC amended Title 1 O of the Code of Federal Regulations (1 O CFR) Section 50.55a to incorporate, by reference, the 1992 Edition of the Code with the 1992 Addenda of Subsections IWE and IWL. The effective date of the amended rule was September 9, 1996. Pursuant to 10 CFR 50.55a(a)(3), your letter dated February 11, 1999, requested relief from certain requirements of Subsection IWL of the 1992 Edition, 1992 Addenda of ASME Section XI.
Those requirements are related to the certification program and qualification requirements for personnel involved in examining concrete surfaces.
Based on our evaluation of your relief requests, we have concluded that, for North Anna Units 1 and 2, and Surry Units 1 and 2, the proposed alternative provides an acceptable level of quality and safety. Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), the proposed alternative is authorized. The staff's evaluations and conclusions are contained in Enclosures 1 and 2.
~,
r 9908260108 990823 I
PDR ADOCK 05000280
-,I G
PDR
--~'-'~
J. P. O'Hanlon The staff has completed its evaluation of this matter, therefore, we are closing TAC Nos.
MA4823, MA4824, MA4857 and MA4858.
Sincerely, Richard L. Emch, Jr., Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338, and 50-339
Enclosures:
North Anna Safety Evaluation Surry Safety Evaluation cc w/encls: See next page
Virginia Electric & Power Company Mr. J. Jeffrey Lunsford County Administrator, Louisa County P.O. Box 160 Louisa, Virginia 23093 Donald P. Irwin, Esq.
Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, Virginia 23219 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, Virginia 23209 Old Dominion Electric Cooperative 4201 Dominion Boulevard Glen Allen, Virginia 23060 J. H. McCarthy, Manager Nuclear Licensing and Operations Support Virginia Electric and* Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, Virginia 23060 Office of the Attorney General
. Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission 1024 Haley Drive Mineral. Virginia 23117 Senior Resident Inspector Surry Power Station, US Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Robert B. Strobe, M.D., M.P.H.
State Health Commissioner Office of the Commissioner Virginia Department of Health P.O. Box 2448 Richmond, Virginia 23218 W. R. Matthews Site Vice President North Anna Power Station Virginia Electric and Power Company P.O. Box 402 Mineral, Virginia 23117 J.P. O'Hanlon Senior Vice President - Nuclear Virginia Electric and Power Co.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, Virginia 23060 I
Mr. Eugene S. G~c:'heck Site Vice President Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road.
Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683