ML18152A542

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/95-04 & 50-281/95-04 on 950213-17 & 21-24. No Violations or Deviations Noted.Major Areas Inspected:Isi, Flow Accelerated Corrosion & Feedwater Heater Replacement
ML18152A542
Person / Time
Site: Surry  Dominion icon.png
Issue date: 03/10/1995
From: Blake J, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18152A543 List:
References
50-280-95-04, 50-280-95-4, 50-281-95-04, 50-281-95-4, NUDOCS 9503200221
Download: ML18152A542 (16)


See also: IR 05000280/1995004

Text

Report Nos. :

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

50-280/95-04 and 50-281/95-04

Licensee:

Virginia Electric and Power Company

Glen Allen, VA

23060

Docket Nos.:

50-280 and 50-281

License Nos.:

DPR-32 and DPR-37

Facility Name:

Surry Power Station Units 1 and 2

y 13-17, and 21-24, 1995

  1. .,,,,, 1, ,~

Date Signed

Safety

SUMMARY

Scope:

This routine, unannounced inspection was conducted in the areas of Inservice

Inspection (ISI), Flow Accelerated Corrosion (FAC), and feedwater heater

replacement.

Results:

ISI procedures were well written and appropriate for their intended

application.

ISI examinations were performed satisfactorily.

ISI records

support the conclusion that examinations were conducted in accordance with

applicable procedures and regulatory commitments.

The licensee has

established and continues to implement an effective program to maintain high

energy carbon steel piping systems within acceptable wall thickness limits.

The Design control package for the Feedwater heater replacement was appropri-

ate to the circumstances.

Welding associated with the Feedwater heater

replacement was accomplished by properly qualified and certified welders in

accordance with properly qualified welding procedures using appropriately

certified welding filler material.

In the areas inspected, no violations or deviations were identified.

9503200221 6~866~80

~DR

ADOCK

PDR

Enclosure

1.

2.

Persons Contacted

Licensee Employees

REPORT DETAILS

  • J. Grace, Management Safety Review Committee
  • D. Grady, Inservice Inspection (ISI)/Nondestructive Testing &

Engineering Programs

  • T. Huber, ISI Engineer
  • M. Kacmarcik, Licensing Engineer
  • J. McCarthy, Assistant Station Manager
  • J. Price, Assistant Station Manager
  • C. Robinson Jr., Manager Inservice Inspection/Nondestructive Testing
  • E. Smith, Quality Assurance (QA) Manager

Other licensee employees contacted during this inspection included

craftsmen, engineers, mechanics, security force members, technicians, and

administrative personnel.

NRC Resident Inspectors

  • M. Branch, Senior Resident Inspector

L. Garner, Project Engineer

D. Karn, Resident Inspector

S. Tingen, Resident Inspector

  • Attended exit interview

Acronyms and initial isms used throughout this report are listed in the

last paragraph.

Inservice Inspection (ISI) (73051)

The inspector reviewed documents and records, and observed activities, as

indicated below, to determine whether ISI was being conducted in accor-

dance with applicable procedures, regulatory requirements, and licensee

commitments.

The applicable code for ISI, for Unit 1 is the ASME B&PV

Code,Section XI, 1989 Edition with no Addenda (89NA).

The applicable

code for ISI, for Unit 2 is the ASME B&PV Code,Section XI, 1980 Edition

with Winter 1980 Addenda (80W80) for the second ISI interval and the ASME

B&PV Code,Section XI, 89NA for the third ISI interval.

Unit 1 is

operating in fuel cycle 13, and the first, 40-month period; of the third,

ten-year interval (Pl,13) ending October 14, 2003.

Unit 2 is in

refueling outage (RFD) 12; the second outage of the third 40-month period

of the second ten-year interval ending June 19, 1995, (02,P3,I2) and

first outage of the first, 40-month period, of the third, ten-year

interval (Ol,Pl,I3) starting June 10 1994 and ending June 10, 2004.

The

licensee extended the second ten-year ISI interval for both Units 1 and 2

by 296 and 374 days respectively.

The licensee notified the NRC of these

changes in VEPCO letters91-551 dated October 1, 1991, and 91-338 dated

July 11, 1991.

The dates of the third ten-year ISI intervals, for both

2

units, remain the same as originally scheduled.

The preceding explains

the dual interval status for Unit 2 during this outage.

Unit 1 was

granted a construction permit June 25, 1968, received its Operating

License May 25, 1972, and commenced commercial operations on December 22,

1972.

Unit 2 was granted a construction permit June 25, 1968, received

its Operating License on January 29, 1973, and commenced commercial

operations on May 1, 1973.

The licensee's nondestructive examination (NOE) personnel, augmented by

contract personnel from Virginia Corporation of Richmond (VCR) were

performing liquid penetrant (PT), magnetic particle (MT), and ultrasonic

(UT) examinations under the umbrella of the VEPCO Quality Assurance (QA)

Program.

Steam Generator (S/G) tubing eddy current (ET) examination data

acquisition and analysis and automated UT examination of the reactor

vessel, were being accomplished by the Westinghouse Company (~) under the

umbrella of the~ QA Program.

. a.

ISI Program Review, Units 1 and 2 (73051)

The inspector reviewed the following documents relating to the ISI

program to determine whether the plan had been approved by the

licensee and to assure that procedures and plans had been estab-

lished for the applicable activities.

Procedures were also reviewed

for technical content .

ID

11/17/94

11/17 /94

7/20/94

9/12/94

11/4/94

2/22/95

VPAP-0406

11/29/94

Procedures Reviewed

Rev.

Title

8

ISI Examination Plan Surry Power Station

Unit 2, Interval 2 Period 3 Items Remaining

to be Examined Sorted by Mark Number

4

ISI Examination Plan. Surry Power Station

Unit 2, Interval 3 Summary of Changes to

Plan Effective With Revision 4 To Plan

1

Surry Power Station Unit 2 Inservice

Inspection Program Interval 3

4

3

2

May 10, 1994 - May 9, 2004

Contractor:

Proficiency Training and

Examination

Surry Units 1 and 2 Inservice Testing

Program Plan Basis Document

10 Year Reactor Vessel Inservice Examination

Program Interval 2 Period 3 and Interval 3

Period 1

Consumable Material Evaluation

3

Procedures Reviewed

ID

Rev.

Title

VPAP-0701

5

Receiving and Receipt Inspection Services

1/23/95

2-NPT-RC-001

1

Inservice Inspection of Steam Generator

3/3/94

Tubes

2/2/95

Westinghouse Steam Generator Tube Eddy

Current Examination Plan

Procedures were well written and appropriate for their intended

application.

b.

Review of NOE Procedures, Units 1 and 2 (73052)

The inspector reviewed the procedures listed below to determine

whether these procedures were consistent with regulatory require-

ments and licensee commitments.

The procedures were also reviewed

for technical content.

ID

2-VIR-ISI-254

2/2/95

2-VIR-ISI-54

2/2/95

2-VIR-ISI-55

2/2/95

MRS-242 VEPl

3/5/92

NDE-6.3

10/29/93

NDE-6.4

9/22/93

NDE-6.6

10/4/93

NDE-7.2

10/4/93

Procedures Examined

Rev

Title/Subject

0

Remote Inservice Inspection for Reactor

Vessel for Surry Nuclear Power Plant

0

Manual Ultrasonic Examination for Reactor

Vessel Upper Shell to Flange Weld for

Surry Nuclear Power Plant

O

Manual Ultrasonic Examination for Reactor

Vessel Threads in Flange for Surry

Nuclear Power Plant

5

2

Eddy Current inspection of Preservice and

Inservice Heat Exchanger Tubes

Storage and Control of NDE Calibrated

Equipment, Calibration Standards &

Consumable Materials

2

Selection of Calibration Blocks for PSI

and ISI Ultrasonic Examination

O

General Requirements for Nondestructive

Examination (Third Interval)

6

General Requirements for Nondestructive

Examination (Second Interval)

4

Procedures Examined

ID

Rev

Title/Subject

NDE-MT-201

2

Magnetic Particle Examination

10/4/93

(Second Interval)

NDE-MT-202

2

Magnetic Particle Examination of Bolting

10/4/93

(Second Interval)

NDE-MT-601

0

Magnetic Particle Examination

10/4/93

(Third Interval)

NDE-MT-602

0

Magnetic Particle Examination of Bolting

10/4/93

(Third Interval)

NDE-PT-201

2

Liquid Penetrant Examination (Second

2/28/92

Interval)

NDE-PT-202

1

Liquid Penetrant Examination of Bolting

2/28/92

(Second Interval)

NDE-PT-203

0

Liquid Penetrant Examination for

2/28/92

Temperatures Less Than 60°F (Second

Interval)

NDE-PT-601

0

Liquid Penetrant Examination (Third

10/4/93

Interval)

NDE-PT-602

0

Liquid Penetrant Examination of Bolting

10/4/93

(Third Interval)

NDE-PT-603

0

Liquid Penetrant Examination for

10/4/93

Temperatures Less Than 60°F (Third

Interval)

NDE-UT-201

3

Manual Ultrasonic Examination of Piping

2/28/92

Welds (Second Interval)

NDE-UT-202

3

Ultrasonic Examination of Vessel Welds 2"

2/28/92

and Less in Thickness (Second Interval)

NDE-UT-203

3

Ultrasonic Examination of Vessel Welds

2/28/92

Greater Than 2" in Thickness (Second

Interval)

NDE-UT-204

2

Inservice Ultrasonic Examination of Class

2/28/92

1 Bolting (Second Interval)

NDE-UT-205

4

Ultrasonic Examination of Reactor Coolant

12/20/93

Piping Welds {Second Interval)

NDE-UT-207

0

Straight Beam Longitudinal Wave

4/3/91

Ultrasonic Examination of Loop Stop Valve

Piping (Second Interval)

NDE-UT-601

0

Manual Ultrasonic Examination of Piping

10/4/93

Welds {Third Interval)

5

Procedures Examined

ID

Rev

Title/Subject

NDE-UT-603

10/4/94

NDE-UT-604

5/4/94

NDE-UT-605

10/4/93

NDE-UT-606

10/4/93

SGPMS 002

1/3/94

O

Ultrasonic Examination of Vessel Welds

Greater Than 2" in Thickness (Third

Interval)

O

Ultrasonic Examination of Bolting > 2" in

Diameter (Third Interval)

0

Ultrasonic Examination of Reactor Coolant

Piping Welds (Third Interval)

0

Manual Ultrasonic Sizing of Flaw

Indications (Third Interval)

3 * Plant Specific Guidelines Eddy Current

Data Analysis, Training, and Testing

Procedures were well written and appropriate for their intended

application.

c.

Observation of Work and Work Activities, Unit 3 (73753)

The inspector observed work activities, reviewed certification

records of NOE equipment and materials, and reviewed NOE personnel

qualifications for* personnel who had been utilized in the ISI

examinations during this outage.

The observations and reviews

conducted by the inspector are documented belo"w.

Activities Observed

Liquid Penetrant Examination (PT)

The inspector observed PT examinations of the welds listed below.

The observations were compared with the applicable procedures and

the Code.

The inspector performed an independent evaluation of the

indications obtained, to confirm the NOE examiner's evaluation.

Liquid Penetrant Examinations Observed

Weld No.

Drawing No

System

1-09

1154B-WMKS-022Al

Safety Injection

1-10

1154B-WMKS-022Al

Safety Injection

1-11

ll 54B-WMKS-022Al

Safety Injection

1-12

1154B-WMKS-022Al

Safety Injection

l-09t

1148-WMKS-RC-10-l

Reactor Coolant

6

Liquid Penetrant Examinations Observed

Weld No.

Drawing No

System

1-lOt

1148-WMKS-RC-10-l

Reactor Coolant

1-18.t

1148-WMKS-RC-10-l

Reactor Coolant

l-19t

1148-WMKS-RC-10-l

Reactor Coolant

l-20t

1148-WMKS-RC-10-l

Reactor Coolant

l-2lt

1148-WMKS-RC-10-l

Reactor Coolant

The inspector noted, during the PT examination of welds marked (t),

that the licensee pre-cleaned and applied penetrant in accordance

with their procedures and consistent with the ASME Code.

After

approximately five minutes, of the penetrant dwell time, islands

appeared in the penetrant where the dye did not wet the inspection

area of interest.

The licensee installed a drape over the

inspection area to preclude contaminates from dripping from above,

and made two more attempts with progressively more aggressive pre-

cleaning methods with the same negative results.

The licensee

indicated that they were able to conduct an acceptable examination

only after they secured the ventilation in the cubical containing

the piping.

The above demonstrates that the licensee and their

contractor will take whatever measures are required to conduct

meaningful examinations.

During the first attempt to PT examine the welds indicated above,

the Health Physics (HP) technician who was providing continuous

coverage for the examinations being conducted in this locked

radiation area, was struck in the head by a falling wrench.

The

technician was not wearing a hard hat and sustained a laceration to

the scalp which required a number of stitches.

Hard hats were

available but their use was optional in the containment building.

By the end of this inspection the licensee had acquired additional

hard hats and mandated their use in all but Foreign Material

Exclusion areas of the containment building.

The inspector noted that the licensee had applied a Hazard

Identification System label to each individual can of penetrant

material.

These labels, in most cases, were applied such that the

material type and batch number on the manufacturers label were

covered.

The Hazard Identification System labels included hazard

information, procurement information, and in most cases, but not

all, material batch numbers.

The inspector's concern is that the

batch number transfer process, if accomplished, introduces the

potential for error and the eventual loss of traceability for the PT

materials.

The licensee indicated that would look into the matter.

The inspector reviewed the certification documentation for the PT

cleaner, developer and penetrant (See Table 1 below).

~l

7

The inspector reviewed the certification, qualification, and visual

acuity documentation for the PT examiners (See Table 2 below).

The examinations were performed satisfactorily.

Magnetic Particle Examination (MT)

The inspector observed MT examinations of the welds listed below.

The observations were compared with the applicable procedures and

the Code.

The inspector performed an independent evaluation of the

indications obtained, to confirm the NOE examiner's evaluation.

Magnetic Particle Examinations Observed

Weld No.

Drawing No

System

1-24

2-26

ll 548-WKS208A5

ll 548-WKS208A5

Main Steam

Main Steam

Relative to the MT examinations above, the inspector noted that

although marginally acceptable contrast was obtained between the red

MT powder and the dark brown tightly adhering oxide coating on one

of the welds examined, significantly better cohtrast would have been

obtained had grey powder been used .

The inspector reviewed the certification documentation for the MT

powder, the yoke, and the 10 Lbs. test weight (See Table 1 below).

The inspector reviewed the certification, qualification, and visual

acuity documentation for the MT examiners (See Table 2 below).

The examinations were performed satisfactorily.

Ultraso_nic Examination (UT)

The inspector observed UT examinations of the welds listed below.

The observations were compared with the applicable procedures and

the Code.

The inspector performed an independent evaluation of the

indications obtained, to_confirm the NOE examiner's evaluation.

Weld No.

1-09

1-10

Ultrasonic Examinations Observed

Drawing No

System

ll 48-WKS-022Al

1148-WKS-022Al

Safety Injection

Safety Injection

I

I

I

8

Ultrasonic Examinations Observed

Weld No.

Drawing No

System

1-11

1148-WKS-022Al

Safety Injection

1-12

1148-WKS-022Al

Safety Injection

1-24

11548-WKS-2018A5

Main Steam

The inspector observed data acquisition for the automated ultrasonic

examination of reactor vessel ,;C" hot leg nozzle to vessel weld

employing the H Ultrasonic Data Recording and Processing System

(UDRPS).

These observations were made at the remote data

acquisition site and at the local control site inside the

containment building.

The inspector reviewed the 17 preliminary

indications identified to date.

The inspector reviewed the certification documentation for the UT

instruments, transducers, and couplant (See Table 1 below).

The inspector reviewed the certification, qualification, and visual

acuity documentation for the UT examiners (See Table 2 below).

The examinations were performed satisfactorily.

Eddy Current Testing (ET) Steam Generator. (S/G) Tubing

The licensee performed 100% bobbin coil examination (tube sheet to

tube sheet) of the non-plugged tubes in the "A" S/G, and Rotating

Pancake Coil (RPC) examinations of 301 tubes from 6" below to 6

11

above the top of the tube sheet (secondary side).

Five tubes were plugged in the one generator examined by the

licensee, this outage, as indicated below.

The inspector observed ET data acquisition activities.

The

observations were compared with the applicable procedures and the

Code.

The analysis was being conducted at the W Pittsburgh

facility, and thus not available for observation.

The inspector

reviewed the RPC data for the ten most significant indications .


---- -

- ---=- - =- =-=--- .=--=---==-~ -- - -

S/G

A

B

C

Total

S/G

A

B

C

Total

Notes:

AVB

-

MBM

-

EB

0

@

0

9

Surry Unit l Plugging History

Preservice

1984

1986

1990

1

3MBM

0

0

1

1 MBM

2MBM

0

0

0

2EI)*

20

2

4

4

2

Surry Unit 2 Plugging History

Preservice

1985

1993

1

l

0

0

0

2AVB

1

0

0

2

1

2

Anti-Vibration Bar

Manufacturing Buff Mark

1995

50

0

0

5

1992

2AVB

0

0

2

Total

7.

2

1

10

1994

0

4AVB

0

4

1 Obstruction - plugged and 1 MBM - Tube Pull

Top of Tube Sheet Indication - Tube Pull

Foreign Object O.D.

1 Obstruction

1 Single Axial Indication >40

1 Multiple Axial Indication >40

2 Non-Quantifiable Indications

The examinations were performed satisfactorily.

Thermally Treated Inconel Alloy 600 Mechanical Tube Plugs

Total

6

8

4

18

Westinghouse notified the licensee, by letter OG-94-107 dated December

30, 1994, of recent field experience with Alloy 600 thermally treated,

mechanical S/G tube plugs that would necessitate a revision to the

corrosion algorithm presented in WCAP-12244. The revised algorithm was

10

incorporated in WCAP-12244, Revision 3.

The licensee has identified

four plugs, in Unit 1 S/Gs, that have 1992 required repair dates (Unit 1

S/G A - three plugs, S/G B - one plug).

Only one plug was identified in

Unit 2 S/Gs, which had a 2010 required repair date.

Table 1

NDE Equipment and Consumables Records Examined

Equipment/Consumables

Serial No/ Heat No./ Lot No./

Batch No.

PT

PT

PT

MT

Cleaner

Developer*

Penetrant. .

Red.No. 8 Powder

44-G4

426-G6

311-C47, 42-H47

92G027

MT 10 LBS. Test Weight

Block #15

922194

MT Yokes

UT Instruments

UT Transducers

93137807, 93137907, W09746,

W09748, and Wl0792

04872, 17259, 011038, MI4208,

33608, 33616,88-582, 93-798,93-408, 93-675,88-568, 93~

797, H4107,93-677, 93-796,93-411, and H4108

UT Couplant

092071

ET MIZ-18 Remote Data Acqui-

sition Units (RDAU)

W0724, W0982, and W05051

ET Calibration Standards

MGT-007-94, MGT-005-94, AV-

015-89, AV-014-89, Z-2430, Z-

1938, Z-5219, AB-010-88, AB-

004-88

ASME B&PV Code,Section V, 89NA paragraph T-625(b) states:

"When examining austenitic stainless steel or titanium,

all materials shall be analyzed individually for chlorine

and fluorine contents ... " T-625 further requires that the

analysis for chlorine be accomplished in accordance with

ASTM D 808 or SE-165 annex 2 and the analysis for fluorine

be accomplished in accordance with SE-165 annex 3, both

reported as a percentage of the residue by weight.* All

but one of the certification documents, provided by the

licensee, reported the halogen family contaminants in the

PT consumables as total halogens or as chlorine only.

From the report provided the inspector, it could not be

determined whether the PT consumables were consistent with

the 89NA Edition of ASME B&PV Code Section V applicable to

11

the PT examination of welds 1-09, 1-10, 1-11 and 1-12 on

Drawing 11548-WMKS-0122Al.

The licensee is pursuing a

clarification in this matter.

Table 2

Qualification, Certification, and Visual Acuity Records

Examined

Examiner

PRC

MOH

PEMc

JOO

AJD

HRH

SFR

WJS

SHT

RGC

WDG

PGM

DLR

KLS

DGT

JMC

UT-II

UT-II

UT,. II I

UT-II

MT-II

MT-II

MT-II I

MT-II

Method-Level

PT-II

VT(l,2,3)-II

PT-II

PT-III

VT(l,2,3)-III

PT-II

ET-IIA *

ET-III

ET -I IA

ET-III

ET-IIA

ET -I IA

ET-II

ET-II

ET-II

ET-I

ET-II

ET-IIA

MSM

ET-IIA

RAS

ET-IIA

JTS

ET-I IA

TFS

ET-IIA

AM

UT-1

UT-I

MT-I

UT -I I IL

MT -II

UT-II

MT- I I

UT- I I

MT- I I

PT-II

PT-II

PT-II

DWS

SAS

AWM

KOH

JHJ

JWB

UT-III

UT-II

MT -I II

PT -II I

,

,

I'

12

Records support the conclusion that examinations were conducted in

accordance with applicable procedures and regulatory commitments.

Within the areas examined, no violations or deviations were identified.

3.

Flow Accelerated Corrosion (FAC) (49001)

The licensee has established a FAC inspection program which implements

the CHECWORKS EPRI (Electric Power Research Institute) computer code,

industry experience, and previous inspection data as predictive tools

for determining and prioritizing inspection locations.

The inspector

conducted interviews with licensee and contractor personnel and reviewed

records as indicated below.

Observations/Findings

During RFO 12, the licensee planned to examine 97 locations in their FAC

program.

At this writing the licensee had identified three FAC degraded

components.

Two components will be replaced this outage, one will be

repaired this outage and replaced at the next refueling outage.

Two of

the three replaced component's wall thickness had been reduced below

code Minimum (2-FW-PPS-l Code Minimum 0.965"

Actual Measured Minimum

0.767", 2-FW-PPS-4 Code Minimum 0.965"

Actual Measured Minimum 0.887").

The inspector reviewed the Wall Thickness Engineering Evaluations for

the below listed components.

Wall Thickness Engineering Evaluations Examined

Component

Component

System

Disposition

Identification

Type

2-SD-PSF2-298

6" goo Elbow

Steam Drain

Reinspect in 2005

2-SD-PSF2-297

6" goo Elbow

Steam Drain

Reinsoect in 2000

2-SD-PSF2-282

6" goo Elbow

Steam Drain

Reinspect in 1999

2-MS-PSFl-33

5" 45° Elbow

Main Steam

Reinspect in 1999

2-SD-PSF2-296

6" goo Elbow

Steam Drain

Reinspect in 2006

2-SD-PSFl-45

6" 45° Elbow

Steam Drain

Reinspect in 2006

2-SD-PSFl-44

6" 45° Elbow

Steam Drain

Reinspect in 2006

2-SD-PSF2-281

6" goo Elbow

Steam Drain

No further inspection

required unless opera-

tional conditions or

criteria change .

2-SD-PSF2-255

4.5" 90°

Steam Drain

Reinspect in 2000

Elbow

-..=-=---~-==---=-=--

-13

Wall Thickness Engineering Evaluations Examined

Component

Identification*

2-BD-PSF2-65

2-SD-PSFR-50

2-FW-PPS-4

2-FW-PPS-4

Component

Type

3.5" 90°

Elbow

2"x4" Con-

centric Re-.

ducer

18" Pipe

18" Pipe

System

Blowdown

Steam Drain

Feedwater

Feedwater

Dispositio*n

No further inspection

required unless opera-

tional conditions or

criteria change.

No further inspection

required unless opera-

tional conditions or

criteria change.

Replace

Replace

The licensee has established and continues to implement an effective

program to maintain high energy carbon steel piping systems within

acceptable wall thickness limits.

Within the areas examined, no violations or deviations were identified.

4.

Feedwater Heater Replacement (55050)

The inspector reviewed procedures, observed work activities and reviewed

selected documents as indicated below, to evaluate the licensee's

performance in the replacement of the Unit 2 Feedwater heaters.

The

Feedwater heaters were built.to the requirements of ASME Code Section

VIII 1986, and installed in accordance with ANSI B31.l-1967.

The inspector reviewed, for technical adequacy Design Change Packige 87-

13-2, "Replacement of First and Second Point Feedwater Heaters and Fifth

Point External Drain Coolers.

11

The inspector observed welding in

progress as indicated below.

The inspector reviewed certification

documentation attesting to the qualification and maintenance of qualifi-

cation for the.welders observed.

The inspector reviewed the welding

filler material Certified Material Test Reports (CMTR)s.

The inspector

reviewed the Welding Procedure Specification (WPS) and the supporting

Procedure Qualification Records (PQR)s.

The documents were examined for

compliance with licensee procedures and Sections II and IX of the ASME

B&PV Code.

Welding Fi 11 er Material CMTRs Examined

Type

Size

Heat/Lot No.

E-7018

3/32"

91201/292814

E-7018

1/8"

T28061/2C430A01

5 .

103,

14

Welder's Qualification Certification

Documentation Examined

WA-4801, AN-3560 and RM-9660

WPSs Examined

WPS

. PQR

Revision E, 05/91

101 Revision B 9/7/82

102 Revision A 1/25/85

103 1/28/85

105 Revision B 8/27 /82

The Design control package for the Feedwater heater replacement was

appropriate to the circumstances.

Welding associated with the Feedwater

heater replacement was accomplished by properly qualified and certified

  • welders in accordance with properly qualified welding procedures using*

appropriately certified welding filler material.

Within the areas examined, no violations or deviations were identified.

Exit Interview

The inspection scope and results were summarized, on February 24, 1995,

with those persons indicated in paragraph 1.

The inspector described

tbe areas inspected.

Although reviewed during this inspection, propri-

etary information is not contained in this report.

Dissenting comments

were not received from the licensee.

6.

A~ronyms and Initialisms

ANSI

ASME

AVB

B&PV

CMTR

DPR

EPRI

ET

FAC

ID

ISI

MBM

MT

NOE

No.

NRC

p. E.

PQR

American National Standards Institute

American Society of Mechanical Engineers

Anti-Vibration Bar

Boiler and Pressure Vessel

Certified Material Test Report

Demonstration Power Reactor

Electric Power Research Institute

Eddy Current

Flow Accelerated Corrosion

Identification

Inservice Inspection

Manufacturing Buff Mark

Magnetic Particle

Nondestructive Examination

Number

Nuclear Regulatory Commission

Professional Engineer

Procedure Qualification Record

PS I

PT

QA

RC

RDAU

Rev.

RFO

RPC

S/G

UT

VCR

VEPCO

w

WPS

15

Preservice Inspection

Liquid Penetrant

Quality Assurance

Reactor Coolant

Remote Data Acquisition Unit

Revision

Refueling Outage

Rotating Pancake Coil

Steam Gener,ator

Ultrasonic

Virginia Corporation of Richmond

Virginia Electric Power Company

Westinghouse

Welding Procedure S~ecification