MONTHYEARML18149A2582018-05-25025 May 2018 Letter to P. Sewell Receipt of Application for Amendment Request of Certificate of Compliance No. 9342 for the Model No. VERSA-PAC - Acknowledgement Letter Project stage: Other ML18270A0932018-09-26026 September 2018 Letter to P. Sewell Application for Amendment Request of Certificate of Compliance No. 9342 for the Model No. Versa-Pac - Request for Additional Information (W/Enclosure) Project stage: RAI ML19029A1272019-01-24024 January 2019 Enclosure 2: Safety Evaluation Report (Letter to P. Sewell Revision No. 13 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package) Project stage: Approval ML19029A1232019-01-24024 January 2019 Package: Letter to P. Sewell Revision No. 13 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package Project stage: Request ML19029A1262019-01-24024 January 2019 Letter to P. Sewell Revision No. 13 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package Project stage: Other ML19029A1252019-01-24024 January 2019 Enclosure 1: Certificate of Compliance (Letter to P. Sewell Revision No. 13 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package) Project stage: Other 2018-09-26
[Table View] |
|
---|
Category:Letter
MONTHYEARML23093A0742023-04-12012 April 2023 Letter - Rev No. 18 CoC No. 9342 Model No. Versa-Pac Transpo Pkg ML23054A1782023-02-23023 February 2023 Orano USA, LLC Transfer of Certificate Holder of NRC Certificate of Compliance No. 9342 for Radioactive Material Packages Model No. Versapac in Two Configurations: VP-55 and VP-110 ML22280A1422022-11-0909 November 2022 Letter - P. Sewell Rev No. 17 CoC No. 9342 for the Model No. Versa-Pac Transpo Package ML22209A1902022-07-28028 July 2022 Orano Tli - Requesting a Supplemental Change to the Application for Amendment of License USA/9342/AF-96 for Model No. Versa-Pac ML22194A7922022-07-13013 July 2022 Orano Tli Submittal of Revision 13 to the Versa-Pac Safety Analysis Report ML22171A0022022-06-17017 June 2022 Orano Tli, Submittal of Response to the Request for Additional Information (Rai), Issued on May 3, 2021, for Revision 13 to the Versa-Pac Safety Analysis Report ML22171A0032022-06-17017 June 2022 Orano Tli, Application for Withholding Proprietary Information from Public Disclosure ML22096A1252022-05-0303 May 2022 Letter and RAI - Daher-TLI, 2022 Amd ML21356B7082021-12-22022 December 2021 Orano Tli, Submittal of Application for Amendment of License ML21236A2112021-09-0303 September 2021 Letter to P. Sewell Revision No. 16 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package ML21195A2832021-07-14014 July 2021 Daher-TLI, Application for Withholding Proprietary Information from Public Disclosure ML21195A2822021-07-14014 July 2021 Daher-TLI, Submittal of Response to the Request for Additional Information (Rai), Issued on June 2, 2021, for Revision 12 to the Versa-Pac Safety Analysis Report ML21153A0442021-06-0202 June 2021 Letter to P. Sewell Application for Amendment Request of Certificate of Compliance No. 9342 for the Model No. Versa-Pac - Request for Additional Information (W/Enclosure) ML21050A2352021-02-19019 February 2021 DAHER-TLI - Affidavit ML21049A1352021-02-17017 February 2021 DAHER-TLI - Submission of Application for Amendment of License USA/9342/AF-96 for Model No. Versa-Pac ML20139A0362020-05-26026 May 2020 Letter-P. Sewell Revision No. 15 of Certificate of Compliance No. 9342 for the Model No. VERSA-PAC Transportation 71-9342.r15 ML19151A2462019-05-28028 May 2019 Letter to P. Sewell Revision No. 14 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package ML19029A1262019-01-24024 January 2019 Letter to P. Sewell Revision No. 13 of Certificate of Compliance No. 9342 for the Model No. Versa-Pac Transportation Package ML18270A0932018-09-26026 September 2018 Letter to P. Sewell Application for Amendment Request of Certificate of Compliance No. 9342 for the Model No. Versa-Pac - Request for Additional Information (W/Enclosure) ML18149A0472018-05-25025 May 2018 Letter to R. J. Freudenberger NRC Inspection Report 71-0249/2017-201(w/EnclosuNRC Inspection Report 71-0249/2017-201) ML18149A2582018-05-25025 May 2018 Letter to P. Sewell Receipt of Application for Amendment Request of Certificate of Compliance No. 9342 for the Model No. VERSA-PAC - Acknowledgement Letter 2023-04-12
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 25, 2018 Mr. Philip Sewell Senior Engineer 8161 Maple Lawn Boulevard Suite 450 Fulton, MD 20759
SUBJECT:
RECEIPT OF APPLICATION FOR AMENDMENT REQUEST OF CERTIFICATE OF COMPLIANCE NO. 9342 FOR THE MODEL NO. VERSA-PAC -
ACKNOWLEDGMENT LETTER
Dear Mr. Sewell:
By letter dated March 16, 2018, Daher-TLI submitted an application in accordance with Title 10 of the Code of Federal Regulations Part 71 to amend Certificate of Compliance No. 9342 for the Model No. Versa-Pac package per the details of the submitted revision of the safety analysis report, Revision 10. The cover letter to this request and a publicly available version of the report can be found in our agencys document database, the Agencywide Documents Access and Management System (ADAMS) in the package at Accession No. ML18087A451.
This letter acknowledges receipt of your application and informs you that the application appears to contain the necessary information to begin our technical review. We have established a schedule for the technical review of your amendment request. The schedule allows for the staff to issue a possible request for additional information (RAI) by mid-August 2018, and a certificate of revised compliance and safety evaluation report by mid-November, based on Daher-TLI responding to a RAI by the end of September 2018. The staff estimates that completing the safety review of this application will require approximately 1,500 staff review hours.
Please reference Docket No. 71-9342 in any future correspondence related to these actions. If you have any questions regarding this matter, please contact me at (301) 415-5196.
Sincerely,
/RA/
Nishka Devaser, Project Manager Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-9342 EPID No. L-2018-LLA-0100
ML18149A258 OFC DSFM DSFM DSFM NAME NDevaser SFigueroa JMcKirgan DATE 05/17/18 05/17/18 05/25/18