Summary of 851104 Meeting W/Util in Bethesda,Md Re Integrated Implementation Schedule & Reg Guide 1.97 Schedule on Core Exit Thermocouple Upgrade.Followup Meeting Held on 860205.Attendees List Encl
ML18149A167
Person / Time
Site: Surry  Dominion icon.png
Issue date: 05/27/1986
From: Chan T
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
RTR-REGGD-01.097, RTR-REGGD-1.097 NUDOCS 8605300490
Download: ML18149A167 (3)


Text

e May 27, 1986 e OELD Docket Nos. 50-280/281 DISTRIBUTION Docket File NRC PDR Local PDR PAD#2 Rdg E. Jordan B. Grimes ACRS (10)

C. Grimes A. Wang APPLICANT:

FACILITY:

SUBJECT:

Virginia Electric and Power Company Surry Power Station, Units 1 and 2

J. Partlow L. Rubenstein T. Chan C. Patel MEETING

SUMMARY

REGARDING THE NOVEMBER 4, 1985 INTEGRATED SCHEDULE AND REGULATORY GUIDE 1.97 SCHEDULE REGARDING CORE EXIT THERMOCOUPLES A meeting was held in Bethesda, Maryland with Virginia Electric and Power Company and NRR representatives on November 4, 1985 to discuss the submission of an Integrated Implementation Schedule (IIS) and the schedule regarding Core Exit Thermocouple upgrade at Surry. Enclosed is a list of meeting attendees.

The schedule for the core exit thermocouples (CETs) upgrade was discussed briefly.

VEPCO stated that the possibility existed for the CETs not to be operational by the end of the next refueling outage for Unit 1 due to the availability of certain electronic hardware.

However, all the thermocouples will be available and installed. Completion of the electrical installation would be expected to be compl~ted around August 1986.

Discussions of the meeting centered around the IIS, a projected timetable of IIS activities including the estimated initial submittal date of the amendment required, following discussions with the staff, and the estimated date for the issuance of the amendment.

VEPCO subsequently submitted the IIS amendment request on December 13, 1985 and a follow-up meeting with the staff was held on February 5, 1986.

Enclosures:

As stated cc:

See next page Crf)f)

PM:PAD#3 TChan:bl 5/.23/86 Terence L. Chan, Project Manager PWR Project Directorate #3 Division of PWR Licensing-A Office of Nuclear Reactor Regulation 8605300490 860527 PDR ADOCK 05000280 p

PDR

-~"'\\

Mr. W. L. Stewart Virginia Electric and Power Company cc:

Mr. Michael W. Maupin Hunton and Williams Post Office Box 1535 Richmond, Virginia 23213 Mr. Robert F. Saunders, Manager Surry Power Station Post Office Box 315 Surry, Virginia 23883 Resident Inspector Surry Power Station U.S. Nuclear Regulatory Commission Post Office Rox 166, Route 1 Surry, Virginia 23883 Mr. Sherlock Holmes, Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 W. T. Lough Virginia Corporation Co1'1!11ission Division of Energy Regulation

. Post Office eox 1197 Richmond, Virginia 23209 Mr. J. T. Rhodes Senior Vice President - Power Virginia Electric and Power Company Post Office Box 26666 Richmond, Virginia 23261 Regional Administrator, Region II U.S. Nuclear Regulatory ColTD'Tlission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30323 James B. Kenley, M.D., Co!TD'Tlissioner Department of Health 109 Governor Street Richmond, Virginia. 23219 e

Surry Power Station Attorney General Supreme Court Building 101 North 8th Street Richmond, Virginia 23219

e e

ATTENDANCE LIST INTEGRATED IMPLEMENTATION SCHEDULE SURRY POWER STATION NOVEMBER 4, 1985 NRC-NRR T. Chan C. Grimes A. Wang VEPCO D. Fortin R. Cross E. Schaub ENCLOSURE