ML18142C218

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Requests ANO1-ISI-027, -028, -029, -030, and -031 (Epids: L-2018-LLR-063, -064, -065, -066, -067)
ML18142C218
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 05/22/2018
From: Thomas Wengert
Plant Licensing Branch IV
To: Pyle S
Entergy Nuclear Operations
References
L-2018-LLR-063, L-2018-LLR-064, L-2018-LLR-065, L-2018-LLR-066, L-2018-LLR-067
Download: ML18142C218 (3)


Text

NRR-DMPSPEm Resource From: Wengert, Thomas Sent: Tuesday, May 22, 2018 2:41 PM To: PYLE, STEPHENIE L Cc: CLARK, ROBERT W; BICE, DAVID B (ANO); Pascarelli, Robert

Subject:

ANO Acceptance Review of Relief Requests ANO1-ISI-027, -028, -029, -030, and

-031 (EPIDs: L-2018-LLR-063, -064, -065, -066, -067)

Ms. Pyle, By letter dated April 23, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18115A102), Entergy Operations, Inc. (the licensee) requested that, pursuant to Sections 50.55a(g)(6)(i) and 50.55a(g)(5)(iii) of Title 10 of the Code of Federal Regulations (10 CFR), the Nuclear Regulatory Commission (NRC) grant relief from certain inservice inspection (ISI) requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, pertaining to volumetric examinations for the fourth 10-Year ISI interval for Arkansas Nuclear One, Unit 1 (ANO-1).

Specifically, the licensee submitted the following five relief requests:

ANO1-ISI-027, Pressure Retaining Welds in Reactor Vessel - Inspection Program B ANO1-ISI-028, Pressure Retaining Welds in Vessels other than Reactor Vessels - Inspection Program B ANO1-ISI-029, Full Penetration Welded Nozzles in Vessels - Inspection Program B ANO1-ISI-030, Pressure Retaining Bolting, Greater than 2 inches In Diameter ANO1-ISI-031, Risk Informed Piping Welds The purpose of this e-mail is to provide the results of the NRC staffs acceptance reviews of these relief requests. The acceptance reviews were performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The regulation in 10 CFR 50.55a(g)(5)(iii) requires licensees to notify the NRC and submit supporting information, if it has determined that conformance with a code requirement is impractical for its facility.

Pursuant to 10 CFR 50.55a(g)(6)(i), the NRC will evaluate the licensees determination that the code requirements are impractical. The NRC may grant relief and may impose alternative requirements as it determines are authorized by law, will not endanger life or property or the common defense and security, and are otherwise in the public interest, giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief requests in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

1

Based on the information provided in your submittal, the NRC staff has estimated the jobhour expenditures to total approximately 550 hours22.917 days <br />3.274 weeks <br />0.753 months <br /> for the five requests. The NRC staff expects to complete this review in approximately 12 months, which is April 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Tom Wengert Project Manager - Arkansas Nuclear One NRC/NRR/DORL/LPL4 (301) 415-4037 2

Hearing Identifier: NRR_DMPS Email Number: 387 Mail Envelope Properties (Thomas.Wengert@nrc.gov20180522144000)

Subject:

ANO Acceptance Review of Relief Requests ANO1-ISI-027, -028, -029, -030, and -031 (EPIDs: L-2018-LLR-063, -064, -065, -066, -067)

Sent Date: 5/22/2018 2:40:49 PM Received Date: 5/22/2018 2:40:00 PM From: Wengert, Thomas Created By: Thomas.Wengert@nrc.gov Recipients:

"CLARK, ROBERT W" <RCLARK@entergy.com>

Tracking Status: None "BICE, DAVID B (ANO)" <DBICE@entergy.com>

Tracking Status: None "Pascarelli, Robert" <Robert.Pascarelli@nrc.gov>

Tracking Status: None "PYLE, STEPHENIE L" <SPYLE@entergy.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 4287 5/22/2018 2:40:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: