ML18139B695
| ML18139B695 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 12/31/1981 |
| From: | WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP. |
| To: | |
| Shared Package | |
| ML18139B694 | List: |
| References | |
| TASK-2.F.2, TASK-TM NUDOCS 8201270510 | |
| Download: ML18139B695 (128) | |
Text
{{#Wiki_filter:I /., I I I i I I ~ i i I \\ r t ! r ~ f f j... WESTINGHOUSE CLASS 3
SUMMARY
REPORT WESTINGHOUSE REACTOR VESSEL LEVEL INSTRUMENTATION SYSTEM FOR MONITORING INADEQUATE CORE COOLING (MICROPROCESSOR SYSTEM) ( 8201270510 811106 PDR ADOCK 05000280 p PDR December, 1980
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 NRC Requirements 1.2 Definition of ICC 1.3 Condition or Events Which Describe the Approach to ICC 2.0 FUNCTIONAL REQUIREMENTS 2.1 Parameter Critical to ICC 2.2 Instrumentation Accuracies, Ranges, and Time Response 2.3 Qualification Requirements 2.4 Codes and Standards 3.0 ICC INSlRU>1ENTATION IDENTIFICATION 4.0 RVLIS - SYSTEM DESCRIPTION* 7683A 4.1 General Description 4.2 Detailed System Description 4.2.1 Hardware Description 4.2.1.1 Differential Pressure Measurements 4.2.1.2 System Layout
- 4.2.2 Microprocessor System
- 4. 2. 2.1 Inputs 4.2.2.2 Density Compensation System 4.2.2.3 Plant Operator Interface and Displays 4.2.2.3.1 Display Functions for Remote Control Board 4.2.3 Resistance Temperature Detectors 4.2.4 RVLIS Valves 4.2.5 Transmitters, Hydraulic Isolators, and Sensors 4.3 Test Programs 4.3.1 Forest Hills 4.3.2 Semiscale Tests 4.3.3 Plant Startup Calibration MP
TABLE OF CONTENTS (Continued) 4.4 Operating Performance 4.5 RVLIS Analysis 4.5.1 Transients Investigated 4.5.2 Observations of the Study 4.5.3 Conclusions 5.0 GUIDELINES FOR THE USE OF ICC INSTRUMENTATION 5.1 Reference Westinghouse Owners Group Procedure 5.2 Sample Transient
6.0 REFERENCES
7683A I MP
LIST OF TABLES Table 3.1 Infonnation Required on the Core Subcooling Monitor Table 4.1 Ccmpliance with-Regulatory Guide-1.97 Draft 2, Rev. 2 6/4/80 Table 4.2 Transients Investigated 7581A
LIST OF FIGURES Fi gu_re 4-1 Reactor Vessel Level Instrument System Figure 4-2 Process Connection Schematic, Train A Figure 4-3 Typical Plant Arrangement for RVLIS Figure 4-4 Reactor Vessel Level Instrument System Block Diagram (One Set of Two Redundant Resets Shown) Figure 4-5 RellXlte Display Module (Control Board) Figure 4-Sa Vessel Level Sulllnary Display Fig~re 4-Sb Vessel Level Trend Display Figure 4-6
- Typical Plant Arrangement for RVLIS Figure 4-7 Block Di a gram of Compensation Function Figure 4-7a Simplified Schematic of Density Compensation System Figure 4-8 Surface Type Clamp-On Resistance Temperature Detector Figure 4-9 HELB Simulation Profile Figure 4-10
- ITT Barton Hydraulic I sol a tor Figure 4-11 ITT Barton 11High Volume" Sensor Bellows Check Valve Figure 4-12 Case A 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip with Reactor Trip, RVLIS Reading and Vessel Mixture Level 7683A MP
Figure 4-13 Case A 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip with Reactor Trip, Void Fraction Figure 4 Case B 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip at 750 Seconds, Wide Range Reading Figure 4-15 Case B 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip at 750 Seconds, RVLIS Reading and Mixture Level Figure 4-16 Case B 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip at 750 Seconds, Void Fraction. Figure.4-17 Case B 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip at 750 Seconds,. Cold Leg Mass Flowrate (LB/Sec) Figure 4-18 *case C 2.5 Inch Pressurizer Break, No. SI, RVLIS Reading and Mixture Level. Figure 4-19 Case C 2.5 Inch Pressurizer Break, No. SI, Void fraction Figure 4-20 Case D 1 Inch Cold Leg Break, ICC Case, RVLIS Reading and Mixture -Level. Figure 4-21 Case D 1 Inch Cold Leg Break, ICC Case, Mixture Level,
- RVLIS Reading and Measured Inventory.
Figure 4-22 Case D l Inch Cold Leg *Break, ICC Case, RVLIS Reading and Mixture Level. Figure 4-23 Case D l Inch Cold Leg Break, ICC Case~ Void Fraction 7683A. MP
1.1 ~Re*REO~IREMENTS The NRC has established requirements (items I.C.l and II.F.2 of NUREG-0737, "Clarification of TMI Action Plan Requirements 11 ) to provide the reactor operator with instrumentation, procedures, and training neces-sary to readily recognize and implement actions to correct or avoid conditions of inadequate core-cooling (ICC). Under certain plant accident conditions, the potential exists for the formation of voids in the reactor coolant system (RCS). Under these conditions, it would be advantageous for the reactor operator to monitor the water level in the reactor vessel or the approximate void content during forced circulation conditions in order to assist him in subse-quent actions. Therefore, a reactor vessel level instrumentation system (RVLIS) has been incorporated to provide readings of vessel level which. can be used by the*operator. Vessel level *as measured by theRVLIS is the co 11 apsed 1i quid level in the vessel. The RVLIS provides a relatively simple and straight-forward means to monitor the vessel level. This instrumentation system neither replaces any existing system nor couples with -any safety system; however, it does_ act to provide additional information to the operator during accident conditions. The RVLIS utilizes.differential_pressure (d/p) measuring devic_es to indicate relative vessel level or relative void content of the circulating primary coolant system fluid. 1.2 DEFINITI6N*8F*Iee ICC as defined in References 1 and 2, is a high temperature condition in the core such that operator action is required to cool the core before damage occurs. 1-1 7581.A
1.3 CONDITIONS OR EVENTS WHICH*DESCRIBE THE APPROACH TO ICC The most obvious failure that would lead to ICC during a small-break _LOCA, although highly unrealistic since multiple failures are required, is the loss of all high pressure safety injection.
- The approach to ICC conditions and the analyses for this event sequence are provided in References 1 and 2.
1-2
2;8* *FUNeTIBNAt*REG~IREMENTS 2.1 - PARAMETERS*ERITieAt*T0*IEE The analysis provided in References 1 and 2 delineates those parameters critical for the detection of and the necessary mitigation actions for the recovery from an ICC condition. To briefly sunmarize those parameters, ICC is detected by either high core exit thermocouple temperatures or by a low reactor vessel level indication (core uncovery} in conjunction with core exit thermocouple indications. Mitigation actions consist of depressurizing the react~! coolant system-{RCS} to permit injection of accumulator water and/or to establish low head safety injection flow. The RCS is itself depressurized by depressurizing the steam generator S'eeondary side. Critical parameters at this point are steam generator pressures and wide range RCS loop temperatures. Once low head safety injection flow is established, transfer-out of the ICC procedure can be made when core exit thermocouple t~eratures are reduced and the.reactor vessel level gauge indicates a level above the top of the core. With the exception of reactor vessel level, all parameters are monitored by currently existing instrumentation. 2.2 INSTRHMENTATI8N*AEE~RAEIES;*RAN6ES;*ANB*TIME*RESP8NSE Acc12racy An accuracy of 6 percent is required on all three types of reactor vessel level instrt111ents. This should be a statistical combination of all uncertainties including those due to environmental effects { if any} on instrumentation. For the upper range instrument, this corresponds to an allowable deviation of about! 1 foot elevation head *. This will give the operator a good estimate of the steilll or gas volume in the upper head during a situation in which the head vent would be employed. For the narrow range instrument this corresponds to an allowable deviation 2.. 1. 7581A
of about! 2.5 feet elevation head. This is required to:
- 1) provide adeauate margin against inadvertant use of the ICC operating guideline (E2or-l, see Section 5.1), 2) assure that the vessel level reading can be reasonably used to aid in the detection of the onset of ICC condi-tions, 3) derive useful information regua~ding vessel level behavior during the vessel refill period of a LOCA transient.
The wide range instrument will cover the full range of expected differ-ential pressures with all reactor coolant pumps running. The maximum span of the wide range instrument will change with the number of pumps operating. The operator must be aware of the maximwn span for a given number of operating pumps. Both the narrow range and the upper range instrument indications should be set to indicate that the vessel is full with the pumps tripped. Time Response The d/p instrument response time shall not exceed 10 seconds. This time* delay is defined as the time required for the display instrument to reach the midpoint of a 50 percent step input d/p change. 2.3 QUAlIFICATION*REQUIREMENTS Environmental qualification of the RVLIS shall verify that the system equipment will meet, on a continuing basis, the performance requirements determined to be necessary for achieving the system requirements as presented above. Verification must include confirmation that those portions of RVLIS equipment which are within the containment will oper-ate during and subsequent to the conditions and events for which the system is required to* be operatio~al. Verification will include deter-mination that the system is sufficiently accurate during this time to meet its design basis. The system post-accident environment qualified life requirement for electrical equipment inside contai~ment is 120 days 2-2
following certain postulated events. The electrical equipment that is installed outside of containment need not meet a qualified life for an / extended period of time providing replacement or calibration checks can be made in short enough time commensurate with the reliability goals of the redundant system. For the resistance temperature detectors (RTDs) environmental requirements for service within the containment, refer to Section 4.2.3. Electrical equipment inside containment shall be instal-led such that it is renx,ved from areas where high energy pipe breaks or pipe whip could cause failure. The d/p transmitters and electronic processing equipment shall be located in a low amoient radiation area. The RVLIS sensing transmi_tters and associated electronic processing equipment shall be located in an area whose temperature range *is between 40 and 12o*F with Oto 95 percent ambient relative humidity. Normal operating environment for transmitter locations shall be between 60 and ao*F and Oto 50 percent relative humidity. The instrumentation shall be qualified to assure that it continues to operate and read within the. required accuracy fol lowing but not necessarily during a safe shutdown earthquake *. Qualification of the electronic equipment and reactor ves-sel level sensing transmitters _applies to and includes the channel iso-lation device or 'Hhere interface with a computer is involved, the input buffer. The location of the electronic isolation device or input buffer should be such that it is accessible for maintenance during accident conditions. 2.4 CODES ANO STANDARDS The RVLIS is in conformance with the fol lowing Codes and Standaras: Regulations GOC 1 Quality Standards and Records GOC 2 Design Bases for Protection Against Natural Phenomena GOC 4 Environmental and Missile Design Bases 2-3
GDC 13 GDC 16 GDC 18 GDC 19 GDC 24 GDC 30 GDC 31 GOC 32 GOC 50 GOC 55 GDC 56 Instrumentation and Control Containment Design Inspection and Testing of Electric Power Systems Control Room Separation of Protection and Control Systems Quality of Reactor Coolant Pressure Boundary Fracture Prevention of Reactor Coolant Pressure Boundary Inspection of Reactor Coolant Pre~sure Boundary Containment Design Basis Reactor Coolant Pressure Boundary Penetrating Containment Pfimary Containment Isolation 10CFR50, Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants" Indostry*Standards _ IEEE-308-1971, "IEEE Standard *Criteria for Class lE Electric Systems for Nuclear Power Generating Stations 11 IEEE-323-1971, "IEEE Trial-Use Standard: General Guide for Qualifying Cl ass 1 Electric Equipmen*t for Nuclear Power Generating Stations"'* IEEE-338-1971, "IEEE Standard Criteria for the-Periodic Testing of Nuclear Power.Generating Station Safety Systems" IEEE-344-1971, "Guide for Seismic Qualification of Class lE-Equipment for Nuclear Power Generating Stations"'*'* IEE-384-1977, "IEEE Standard Criteria for Independence of Class lE Ec~ipment and Circuits" AS>'E BPVC, Section III, Class 2 Nuclear Power Plant Components For certain specific plants, IEEE-323-1974 is applicable. For certain specific plants, IEEE-344-1975 is applicable. 2-4
ANSI 831.1.0, 1967 including addenda through and including 6/30/71, "Code f~r Pressure Piping", including nuclear code cases where a~plicable Regulatory Guides R.G. 1.11 Instrument Lines Penetrating Primary Reactor Containment R.G. 1.22
- Periodic Testing of Protection System Actuation Functions R.G. 1.75 Physical Independence of Electric Systems 2-5 7:81A
3.0 ICC INSTRUMENTATION IDENTIFICATION Adequate instrumentation is necessary to diagnose the approach to ICC ana ta determine the effectiveness of the mitigation actions taken. During the preparation of the ICC operating instructions, consiaeration was given ta the adequacy of current instrumentation and tne benefits derivable from the addition of new instrumentation. The following is a list of existing instrumentation considered (refer to the FSAR for details) and conclusions derived:
- 1.
Current Instrumentation
- a.
WIDE RANGE REACTOR COOLANT PRESSURE*- present instrumentation is available for determining general RCS pressure trenas during the ICC eve~~c.te&.:_accur_acy following ICC event.s is such that this -instrume~t can-~ot ___ be--~~- fo*r precise determina-tions of the pressure required to assure onset of low head safety injection flow to the RCS.
- b.
PRESSURIZER PRESSURE AND LEVEL - conditions in the pressurizer will generallylie-outside the ranges of these instruments during an ICC event in a Westinghouse PwR. Pressurizer pres-sure and level are not used for determining mitigation actions to be taken during ICC.
- c.
AUXILIARY FEEDWATER FLOW - present instrumentation is available for assuring the sufficiency of makeup water flow ta the steam generators during an ICC event.
- d.
WIDE RANGE RESISTANCE TEMPERATURE DETECTORS - present instru-mentation is available in determining trends of recovery actions but may not be available in deter~--the onset of ICC conditions for all break sizes.
- e.
CORE EXIT THERMOCOUPLES - present instrumentation is available in determining bot.h the existence of ICC and the trends of recovery actions. 3-1
- f.
CORE SUBCOOLING - does not provide useable infonnation during
- an ICC condition. Will indicate superheat conditions in core coolant. Will help indicate the approach to ICC by showing saturation conditions. Since the core subcooling monitors may not be described in the FSAR, refer to Table 3.1 for informa-tion.
- g.
STEAMLINE PRESSURE - present instrumentation is available for determining heat sink availability and heat removal capability during ICC mitigation actions.
- h.
STEAM GENERATOR LEVEL -: present instrumentation is available -- -,..~Qr.....de_t__1:1rmi-ni ng the availability of a heat sink for the RCS - ~ during an I CC' conai tion *-
- 2.
New Instrumentation
- a.
REACTOR VESSEL LEVEL~ provides an indication of the approach
to ICC and confirms the achievement of adequa.1:~_<:ore cooling when level in the reactor vessel is restored.
To summarize the above considerations, current _plant instrumentation is adequate to determine heat sink availability, to detect the onset of ICC, and to detect the effectiveness of mitigation acti.ons __ following the - onset of an I CC event.* The RV LIS is provided to permit a more continuous indfcation of the approach to ICC. 3-2 7581A
- f.
CORE SUBCOOLING - does not. provide useable information during an ICC condition. Will indicate sup.erheat conditions in core coolant. Will help indicate the approach to ICC by showing saturation conditions. Since the core subcooling monitors may not be described in the FSAR, refer to Table 3.1 for informa-tion.
- g.
STEAMLINE"PRESSURE - present instrumentation is available for determining heat sink availabilty and heat removal capability during ICC mitigation actions.
- h.
STEAM GENERATOR LEVEt - present instrumentation is available '.c..c__:~-=====~-~--=:::::=:;--~--- for determining the availability of a heat sink for the RCS -* during an ICC condition.
- 2.
New*Instrcmentation
- a.
REACTOR VESSEL LEVEL~ provides an indication of the approach to ICC and confirms-tt1e-*achievement of adequate core cooling when level in the reactor vessel is restored. To sunmarize the above considerations, current plant instrumentation is adequate to determine heat Sink availability, to detect the onset of ICC, and to detect the effectiveness of mitigation actions following the onset of an ICC event *. The RVLIS is provided to permit a more continuous indication of the approach to ICC. 7581A
~--,-,-.. TABLE 3.1 INFORMATION REQUIRED ON THE CORE SUBCOOLING MONITOR Disolay Infonnation Displayed (T-Tsat, Tsat, press, etc.) Display Type (analog, digital, CRT) Continuous or on Demand Single or Redundant Display Location of Display P-P sat subcoo led T-Tsat superheat Analog and digital Analog - continuous Digital - on demand Redundant User supplied Alarms Caution - 25PF subcooled for RTD) Alann - o°F subcooled (include setpoints) 15°F subcooled for T/C) for RTD and T/C Overall Uncertainty (OF, psi) Digital - 40F for T/C; 3°F for RTD Analog - s°F for T/C; S°F for RTD Range of Display Calibrated region - 1000 psi subcooled to 2000°F superheat Qua l ifi cati ans Calculator Overall - never offscale Type (process computer, dedicated digital or analog calc.) If process computer is used, specify availability (percent of time) Single or Redundant Calcu"lators Selection Logic (highest T., lowest press) Qua l ifi cati ens Calculational Technique (steam tables, functional fit, ranges) None at present* Dedicated digital N/A Redundant Highest T for RTD or T /C; Lowest P None at present Functional fit - ambient to critical point
- The display is currently undergoing seismic qualification testing by
~estinghouse which will confonn to IEEE-344-1971. This infonnation will only be provided at the specific request of the custaner and after appropriate installation checks have been made to verify the applicability of this qualifi-cation. 3-3
TABLE 3.1 (Continued) Input Temperature (RTDs or T/Cs) Temperature ( number of sensors and l ocati ens) Range of Temperature Sensors Uncertainty* of Temperature Sensors ( F at 1 a) Qua 1 if i cations Pressure (specify instrunent used) Pressure (number of sensors and locations) RTD, T/C and Tref RTD - 2 hot and 2 col d leg per channel TIC - 8 per channel RTO 700°F T /C 1650 °F (calibration unit range O - 2300 °F) User supplied User supplied User supplied 2 wide range - Loop l narrow range - Pressurizer Range of Pressure Sensors Wide range 3000 psi Narrow range - 1700 - 2500 psi Uncertainty** of Pressure Sensors. (psi at la)
- Qua 1 if icati ons Backup Capability Availability of Temp and Press Availability of Steam Tables etc.
ffrocedures User supplied User.supplied
- Uncertainties must address conditions of forced flow and natural circulation 3-4
- 4. 0 REACTOR VESSEL LEVEL INSTRUMENTATON SYSTEM - SYSTEM DESCRIPTION 4.1 GENERAL DESCRIPTION
, The ~eactor vessel level instrumentation system (RVLIS) uses differen-tial pressure (d/p) measuring devices to measure vessel level or rela-tive void content of the circulating primary coolant system fluid.
- The system is redundant and includes automatic canpensation. for* potential temperature variations of the impulse lines. Essential information is displayed in the main control room in a form directly useable by the.
operator. The functions performed by the RVLIS are:
- 1.
Assist in detecting the presence of a gas bubble or void in the reactor vessel
- 2.
Assist in detecting the approach to ICC
- 3.
Indicate the formation of a void in the RCS during forced flow' conditions. 4.2 DETAILED SYSTEM DESCRIPTION 4.2.l HARDWARE DESCRIPTION 4.2.1.l Differential Pressure Measurements The RVLIS (Figure 4-1) utilizes two sets of three d/p cells. These ce 11 s measure the pressure drop from the bottom of the reactor vesse 1 to the top of the vessel, and.fran the hot legs to the top of the vessel. This d/p measuring system utilizes cells of differing ranges to cover different flow behaviors with and without pump operation as discussed below: 4-1
- l.
Reactor Vessel - Upper Range (APa) The d/p cell APa shown in Figure 4-1 provides a measurement of reactor vessel level above the hot leg pipe when the reactor cool-.* ant pump (RCP) in the loop with the hot leg connection is not operating.
- 2.
Reactor Vessel - Narrow Range (APb) This measurement provides an indication of reactor vessel level from the bottom of the reactor vessel to the top of the reactor during natural circulation conditions.
- 3.
Reactor Vessel - Wide Range (APc) This instrument provides an indication of reactor core and inter-nals pressure drop for any combination of operating RCPs. Com-parison of the measured pressure drop with the*normal, singl~- phase pressure drop will provide an approximate indication of the relative void content or density of the circulating fluid. This instrument will roonitor coolant conditions on a continuing basis during forced flow conditions. To provide the required accuracy for level measurement, temperature measurements of the impulse lines are provided. These measurements, together with the existing reactor coolant temperat_ure measurements and. wide range RCS pressure, are employed to ccmpensate. the d/p transmitter outputs for differences in system density and reference leg density, particularly during the change in the environment inside the containment structure following an accident. The d/p cells are located outside of the containment to eliminate the large reduction (approximately 15 percent) of measurement accuracy asso-ciated with the change in the containment environment (temperature, pressure, radiation) during an accident. The cells are also located outside of containment so that system operation including calibration, cell replacement, reference leg checks, and filling is made easier. 4-2
4.2.1.2 System Layout A schematic of the system layout for the RVLIS is shown in Figure 4-2. r There are four RCS penetrations for the cell reference lines; one reac-tor head connection at a spare penetration near the center of the head or the reactor vessel head vent* pipe, one connection to an incore instrument conduit at the seal table, and connections into the side of two RCS hot leg pipes. The pressure sensing lines extending from the RCS penetrations will be a combination of 3/4 inch Schedule 160 piping and 3/8 inch tubing and will include a 3/4 inch manual isolation valve as described in Section 4.2.4. These lines connect to s,x sealed capillary impulse lines (two at the reactor head, two at the seal table and one at each hot leg) which transmit the pressure measurements to the d/p transmitters located outside the containment building.* The capillary impulse lines are .sealed at the*RCS end with a sensor bellows_ which serves as a hydraulic coupling for the pressure measurement. The impulse lines extend from the sensor bellows through the containment wall to hydraulic isolators, which al so provide hydraulic.coupling as well as a seal and isolation of the lines. The capillary tubing extends fran the hydraulic isolators to .the d/p transmitters, where instrument valves are provided for isolation and bypass. Figure 4-3 is an elevation plan of a typical plant showing the routing of the impulse lines. The impulse lines fran the vessel head connection must be routed upward out of the refueling canal to the operating deck, - then radially toward the seal table and then to the containment penetra-tion. The connection to the bottom of the reactor vessel is made through an incore detector conduit which is tapped with a T connection at the seal table.* The impulse line from this connection is routed axially and radially to join with the head connection line in routing to the penetrations. Similarly, the hot leg connection impulse lines are routed toward the seal table/penetration routing of the other two con-nections. 4-3 7581A
The impulse *lines located inside the containment building will be exposed to the containment temperature increase during a LOCA or HELB. Since the vertical runs of impulse lines form the reference leg for the d/p measurement, the change is density due to the accident temperature change must be taken into account in the vessel level determination.
- Therefore, a strap-on RTO is located on each vertical run of separately
- routed impulse 1 ines to determine the impulse 1 ine temperature and cor-rect the reference leg density contribution to the d/p measurement.
Temperature measurements are not required where all three impulse 1 ines of an instrument train are routed together. Based on the studies of a nurrber of representative plant arrangements, a maximum of 7 independent vertical* runs 1111st be measured to adequately compensate for density changes. 4.2.2 MICROPROCESSOR RVLIS The microprocessor RVLIS includes equivalent reactor vessel level indications on redund"ant flat panels with alphanumeric displays provided for control room installation in addition to having this information available for display at the microprocessor chassis~ RVLIS is
- .configured as two protection sets, in certain installations in separated sec'tions of a single instrument rack and* in other installations in two separated instrument racks.
The envelop_e of an instrument rack occupies a space at the base of [ J The a,c block diagram of the RVLIS using microprocessor equipment is shown in. figure 4-4. This diagram shows that in addition to the reactor vessel level (d/p) transmitter input, there are also* temperature compensating signals, reactor pump running status inputs, and RCS parameter inputs to each chassis of the two redundant sets. The output of each set will be to displays and to a recorder, *as well as an output for a serial data link. A general display arrangement is shown to Figure 4-5. Conformance with Regulatory Guide 1.97 for the processor dtsplay system is given in Table 4.1
- 4-4 7683/:1.
MP
4.2.2.1 RVLIS Inputs The,microprocessor system inputs are as follows. If ~xisting unquali-fied inputs are used, isolation as required will be provided by the owner. Differential Pressure Transmitters The three d/p transmitters per set are used to measure the d/ps between the three pressure tap points on the primary system, as discussed below:
- 1.
2
- 7683A The directiori of this transmitter's output is full scale (20 ma) with the vessel full and zero scale (4 ma) with the vE!ssel emptied to the h9t leg tap. These endpoints are nominal and are for low coolant temperatures. If no pumps are operating, 6Pa gives an indication of level in the region above the hot leg.
If the pump is running in the loop with the hot leg connection, this indication will be invalid and most likely off-scale. The !reading would be flagged as "invalid" under these conditions. The effect on the indication from the pump not running in this loop, but running in other loops, is less than 10 percent of the range. 4-5 MP a,c a,c
f.Pb gives an i*~:":ation of_ react:r :ess-:'. '.:vel,,,rien '10 pumps are running.
- ~ Jne ar more pumps!'": ru~ning, lPJ will ~e off-scale anj ::--: reading invaiiJ.
The sense 0f t1:.:,,P. output is s.. cn :::,a: a 20 ::ia signa1 is a D nominally ful~ 1-=ssel and a 4 ma.signal is for a nominally empty vessel.
- 3.
[ J
- The seose of tac o! c OJtput is tnat 20 -
ma represents al: pumps r~nning and 4 ma is empty vessel. With all pumps runni1g and no void fraction, :,e.:,,?c shoulj read 100 percent at zero ~ower. The reaaing at fJ11 ~ower is slightly higher. Reference Leg Tempera:Jre RTD The reference leg temperature RTDs are used t-::, :-;ieasJre the temperature of the coolant in the capillary tub@ reference legs. This is.used to compute the density of the reference leg fluia. A typical arrangement of the reference leg te~oeratJre ~TDs is snown in Figure 4-6. The conversion of RTS resistance to temperatJre s~all cover t~e tempera-ture range of 32 to JS0°F. The RTDs are 100 orirn ::ilatinum four wire RTDs as S'i*J'~"1 'n Fig*Jre 4-8. Hot Leg Temperature Either existing or "e*...- "'ide range hot leg_ t:-:-:,'"::~,.-= S':'1S:l'"S a'"-: used to measure the coo1ar;: temperature. -.,;s :="-::.. ::.;~= is *.;s-:: ::, calcu-late coolant density. 4-i 7683A MP
- ... ~ ::ie Range Reactor Cool ant Pressure
~*:her existing wide range pressure sensors or new pressure sensors will be used to ~easure reactor coolant pressure. The pressure is used to c3lculate reactor coolant density. Tne block diagram o.f the compensation functions is shown in Figure:4-7. Digital Inputs T~e reactor coolant pump status signals indicate whether or not pumps are running. Recognizing that hydraulic isolators are provided on each i~pulse line for containment isolation purposes, each-hydraulic isolator has *1imit switches to indicate they have reached the limit of travel. ~.2.2.2 Density Compensation System To provide the required accuracy for vessel level measurement, tem-perature measu~ements of the impulse lines are provided. These ~easurements, together with the existing reactor coolant temperature ~easurements and wide range RCS pressure, are employed to compensate the
- /p transducer outputs for differences in system density andreference
~eg density, pa~ticularly during the change in the environment inside the containment structure following an accident. A simplified schematic of the density compensation system is shown in Figure 4-7a. The d/p cells are located outside the containment. "'."~e reference leg fluid density calculation must cover a range of 32 to 430°F. The fluid is assumed to be compressed liquid water at 1200
- rs i a.
~3ch of the three d/p measurements will have density corrections from .::rta in temperature measurements. Some of these wi 11 have a pas iti ve cJrrection and some negative depending on the orientation of the impulse 'I fne where the temperature is being measured.
Vessel Liquid Density Calculation a,c Vessel Vapor Phase Density Calculation a,c Vessel Level Calculation .. [ Pump Flow d/p Calculation a,c 4-8 7683A MP
r The lower of the two calculated d/p corrections is divided into the measured d/p. The result is the percent of. expected d/p and should 100 percent with all pumps operating and no circulating voids. Scaling of Displayed Values read Each of the three d/p measurements after the preceding calculations shall be scaled to read in percent. With the vessel full of water and no pumps running, the outputs of 6Pa and 6Pb should read 100 percent. 4.2.2.3 Plant Operator Interface and Displays Information displayed to the operator for the RVLIS is intended to be unambiguous and reliable to minimize the potential for operator error or misinterpretation. The redundant control board displays provide the following information:
- 1.
- 2.
- 3.
a,c a,c a,c a,c
All signals are input to a microprocessor-b~sed data analysis system. The control room display format utilizes an alphanumeric display located remotely from the computational system. Redundant displays are provided for the two sets. Level information based on all three d/p measurements is presented. Correction for refer-ence leg densities is automatic. Any error conditions such as out-of-range sensors or hydraulic isolators are automatically displayed on the affected measurements. There are two display sheets for reactor vessel level: the first is a summary sheet, and the second is a trending of the three vessel level ind i cat i on-s. [ 4.2.2.3.1,Display Functions for Remote Control Board The prime display unit for the vessel level monitor is the 8 line, 32 character per line alphanumeric display which is located in the control board remote from the main processing unit.* Vessel Level Monitor Summary Display Figures 4-5, 4-Sa and 4-Sb give example displays. General arrangement is shown on Figure 4-5. The vessel level surrmary display is shown on Figure 4~5a. The following is a description of the display.
- 1.
The first line gives the title of the display as shown. The use of the underbar feature delineates this line from the rest of the display.
- 2.
7683A The second line gives column headings as shown. the underbar clarifies the display. 4-10 Again, the use of MP
- 3.
The third line gives the measured and normally expected values from the 6Pa measurement. The first field gives the title, the second gives the measured level, the third gives the normal value for the current status, and the last field gives the validity status and is blank under normal conditions.
- 4.
The fourth *1ine gives the 6Pb.measurement results using the same format as in line 3. S. The fifth line gives the 6Pc measurement results using the same format as in line 3. The use of underbar in line 5 delineates this line from the next.
- 6.
The sixth line gives the status of the pumps as seen by the unit. The runn,ng pumps are identified. 7-8. The seventh line and eighth line are normally left blank and are reserved for hydraulic isolator limit switch indicators, out of range sensors and operator disabled sensors. Trend Display ) The trend display for the vessel level monitor shall use the format shown in Figure 4-Sb. Displays on Main Processing Unit The one--line forty character alphanumeric display on the front panel of the main processing unit.is used to display individual sensor inputs. The sensor is selected with a two digit thumbwheel switch. The following information is to be given for each sensor:
- 1.
Sensor identification
- 2.
Input signal level
- 3.
Input signal converted to engineering units
- 4.
Status of sensor input 4-lOa MP
Disabled Inputs Any inputs can be disabled by the operator. this action is under the control of a keyswitch on the front panel of the main computational unit and causes the processor to disregard the analog input for that variable. 4.2.3 RESISTANCE TEMPERATURE DETECTORS (RTD) The resistance temperature detectors (RTD) associated with the RV~IS are utilized to Obtain a temperature signal for fluid filled instrument lines inside containment during normal and post-accident operation. The temperature measurement for all vertical instrument lines is used to correct the vessel level indication for density changes associated with the environmental temperature change. The RTD assembly i~ a totally enclosed and hermetically sealed strap-on device consisting of a thermal element, extension cable and termination
- cable,as indicated in Figure 4-8.
The sensitive portion of the device is mounted in a removable adapter assembly which is desig~ed to conform to the surface of the tubing or piping being monitored. The materials are all selected to be compatible with the normal and post-accident environment. Randomly selected samples from the controlled (material, manufacturing, etc.) production lot will be qualified by type testing. Qualification testing will consist of thermal aging, irradiation, seis-mic testing and testing under simulation high energy line break environ-mental conditions. For the qualified life requirement*s, see Section 2.3. The specific qualification requirements for the RTDs are as fol-lows: .7683A The thermal aging test will consist of operating the detectors in a high temperature environment: either 400°F for 528 hours or per other similar Arrhenius temperature/time relationship. 4-ll MP
- 2.
Radiation The detectors shall be irradiated to a total integrated dose (TIO) of 1.2 x 108 rads garrana radiation using a co60 source at a minimum rate of 2.0 x 106 rads/hour and a maximum rate of 2.5 x 106 rads/hour. Any externally exposed organic materials shall be evaluated or tested to 9 x 108 rads TIO beta radiation. The energy of the beta particle shall be 6 MEV for the first 10 MRad, 3 MEV for 340 MRad and 1 MEV for 150 MRad.
- 3.
Seismic 4. The detectors will be tested using a biaxial seismic simulation. The detectors shall be mounted to simulate a plant installation and will be energized throughout the test. High*Energy*line*Break*Sima1ation The detectors shall be tested in a saturated steam environment using the temperature/pressure curve shown in Figure 4~9, Caustic spray, consisting of 2500 ppm boric acid dissolved in water and adjusted to a pH 10.7 at 2s*c by sodium hydroxide, shall be applied during the first 24 hours. The test.units will be energized throughout the test. The RTD device is designed to operate over a temperature range of -58 to 5oo*F (the *normal temperature range is 50 to 130°F). 4.2.4 REACTOR VESSEL LEVEL INSTRUMENTATION SYSTEM VALVES Two types of valves are supplied for the RVLIS. The root valve (3/4 T78) is an ASME Class 2, stainless steel, globe valve. The basic func-tion of the valve is to isolate the instrumentation fran the RCS.The other valve (1/4 x 28 ID), is an instrumentation-type valve. It is a manually actuated ball valve used to provide isolation in the fully 4-12 7581A
closed position. The valve is hermetically sealed and utilizes a pack-
- ess design to eliminate the possibility of fluid leakage past the stem
- o the atmosphere.
4.2.5 TRANSMITtERS, HYDRAULIC ISOLATORS, AND SENSORS Differentia~*Pressare*Transmitters The d/p transmitters are a seismically qualified design as used in numerous other plant applications. In the RVLIS application, accuracy considerations dictate a protected environment, consequently trans-mitters are rated for 40 to 1300F and 104 rad TIO. Several special requirements ~or these transmitters are as follows:
- 1.
Must withstand long. term overloads of up to 300 percent with minimal effect on calibration *
- 2.
High range and bi-directional units required for pump head measure-ments.
- 3.
Must displace minimal volumes of fluid in normal and overrange oper-ating modes. The first two requirements are related to the vernier characteristic of the pumps off level measurements and the wide range measurements, respectively. The third is related to the limited driving displacement _of the hydraulic isolator when preserving margins for pressure and ther-mal expansion effects in the coupling fluids. The d/p transmitters are rated 3000 psig working pressure and all units are tested to 4500 psig. Internal valving also provides overrange ratings to full working pressure. 4-13 7581A I . I
~--- -- Hydraulic-Isolator _ a,c High Volome*Sensor a,c 4-14 7581A
I 4.3. TEST PROGRAMS A variety of test programs are in progress or will be carried out to study the static and dynamic performance of the RVLIS at two test facil-ities, and to calibrate the system over a range of normal operating conditions at each reactor plant where the system is installed.* These programs,-which supplement the vendors' tests of hydraulic and electrical components, will provide the appropriate verification of the system response to accident conditions,as well as the appropriate procedur~s for proper operation, maintenance and calibration of the equipment. A description of these programs is presented in the following section: 4.3.l Forest Hills A breadboard installation consisting of one train of a RVLIS was instal- . led and tested at the Westinghouse Forest Hills Test Facility. The system consisted of a full single train of RVLIS hydraulic components (sensor assemblies, hydraulic isolators, isolation and bypass valves and d/p transmitters) connected to a simulated reactor vessel. Process connections were made to simulate the reactor head, hot leg and seal table connections. Capillary tubing which in one sensing line simulated the maximum expected length (400 feet) was used to connect the sensor asseni>lies to the hydraulic isolators and all joints were welded. Con-nections between the hydraulic isolators, valves and transmitters util-ized compression fittings in most cases. Resistance telll)erature detec-tors, special large volume sensor bellows and volume displacers inside 4-15 a,c
the hydraulic isolator assemblies which are normally part of a RVLIS inst a 1 lation were not included in the installation since elevated tem-peratJre testing was not included in the program. The ~ydraulic isolator assemblies and transmitters were mounted at an elevation -slightly below the simulated seal table elevation. The objectives of the test were as follows:
- 1.
Obtain installation, filling and maintenance experience
- 2.
Prove and establish filling procedures for initial fi 11 ing and system maintenance.
- 3.
Establish calibration and fluid inventory maintenance procedures for shutdown and normal operation conditions. -4. Prove long term integrity or hydraulic components s~ Verify and quanti.fy fluid transfer and makeup. requirements asso-ci ated with instrument valve operation.
- 6. *- Verify leak test procedures for field use Reactor*Yesse1*Sima1ator The reactor*vessel simulator consisted of a 40 foot long 2 inch diameter stainless steel pipe with taps at the top, side_ and bottom to simulate the reactor head, hot leg and incore detector thimble conduit penetra- -
tion at the bottom of the vessel. Tubing (0.375 inch diameter) was used to connect this lower tap to the sensor at the simulated seal table elevation and the hot leg sensor to the head connection was simulated by 1 inch tubing which connected the sensor to the vessel. The reactor vessel simulator was designed for a pressure rating of 1400 psig to comply with local stored energy and safety code considerations
- 4-16 7581~
Instai1ation The system was installed in the high bay test area of the Westinghouse Forest Hills Test Facility by Westinghouse personnel under the supervi-sion of Forest Hills Test Engineering. All local safety codes were considered in the construction. Fi11ing*0peration 4-17 7581A a,c
4.3.2 SEMISCALE TESTS In* order to study the transient response of the RVLIS during a small-break LOCA and other accident conditions, the h~draulic components of the RVLIS have been install~d at the Semiscale Test Facility in Idaho. Vessel level measurements wil_l be obtained during the current semiscale test program series whi.ch runs from Decetnber 1980 to March 1982. The test scheduled to be completed by July.1981 are expected to provide the desired transient response verification; additional data will be obtained from the tests scheduled for _completion by Noveni>er 1981. The Semiscale Test Facility is a model of a 4-Loop pressurized water reactor coolant system with elevation dimensions essentially equal to the dimensions of a full-size system. The reactor vessel contains an electrically heated fuel assembly consisting of 25.fuel rods with a heated length of 12 feet. Two reactor coolant loops are provided, each having a pump and a stec111 generator with a full neight tube bundle. One loop models the loop containing the pipe break, which can be located at any* point in the loop. The other loop models the three in~act loops. A blowdown tank collects and cools the fluid discharged from the pipe break during the simulated accident. Over 300 pressure, temperature, flow, level and fluid density instruments are installed in the reactor vessel and loops to record the fluid conditions throughout a test run. Test results are compared with predictions for verification of computer code models of the transient performance. 4-18 7581A a,c I
The Westinghouse level measurements obtained during a test run will be compared with data obtained from existing instrumentation installed on the semiscale reactor vessel. The semiscale facility has two methods of measuring the level or fluid density: d/p measurements are obtained over 11 vertical spans on the reactor vessel to determine level within each span, and ganrna densitometers are installed at 12 elevations on the reactor vessel to determine the fluid density at each elevation. This data establishes a fluid density profile within the vessel under any operating condition, ana this information will be compared with the data obtained from the Westinghouse level instrumentation. Other semiscale facility instruments (loop flows and fluid densities when pumps are operating, and pressure and temperatures for all cases) will provide supplemental information for interpretation of the test facility fluid conditions and the level measurement. Specific tests included in the semiscale test program during which Westinghouse RVLIS measurements will be obtained are as follows:
- 1.
Mi see 11 aneous steady state and transient tests with pumps on and off, to calibrate test facility heat losses.
- 2.
Small-break LOCA test with equivalent of a 4 inch pipe break.
- 3. Repeat of small-break LOCA test with test facility modified to simu-late a plant with upper head injection (UHI).
- 4.
Several natural convection tests covering subcooled and saturated coolant conditions and various void contents.
- 5. Tests to simulate a station blackout with discharge through relief valves.
6
- Simulation of the St. Lucie cooldown incident.
4-19 7581A
4.3.3 PLANT STARTUP CALIBRATION / During the plant startup, subsequent to installing the RVLIS, a test program will be carried out to confirm the system calibration. The program will cover normal operating conditions and will provide a reference for comparison with a potential a~cident condition~ The ele-ments of the program are described below:
- 1. During refilling and venting of the reactor vessel, measurements of all 6 d/p transmitters would be compared to confirm identical level indications.
2 *. During plant heatup with all reactor coolant pumps running, measure-ments would be obtained from the wide range d/p transmitters to confirm or* correct the temperature compensation provided in the system-electronics. The temperature compensation, based on a best est,mate of the flow and -pressure drop variation during ~tartup, corrects the transmittet' output so that the control board indication
- is maintained at 100 percent over the entire operating temperature range.
- 3.
At hot standby, measure~nts would be obtained from all transmitters with-different combinations-of reactor coolant pumps operating, to provide the reference data for comparison with accident conditions. For any pump operating condition, the reference data, represents the. normal condition, i.e., with a water-solid system. A reduced d/p during an accident would be an indication of voids in the reactor vesse 1.
- 4.
At hot standby, measurements would be obtained from the reference leg RTDs, to confirm or correct reference leg temperature compensa-tion provided in the system electronics
- 4-20 7~81A
\\ 4.4 0PERATING*~ERF0RMANEE Each train of the RVLIS is capable of monitoring coolant mass. in the vessel from norma 1 operation to a condition of comp 1 ete uncovery of t_he reactor core. This capability is provided by the three d/p transmit-ters, each transmitter covering a specific range of operating condi-tions. The three instrument ranges provide overlap so that the measurement can be obtained fran more than one meter under most accident conditions. Capabilities of each of the measurements are described below: 1.* Reactor Vessel - Upper Range The transmitter span covers the distance from the hot leg piping connection to the top of the reactor vessel. With the reactor cool-ant *pump shut down in the loop with the hot leg connection, the _transmitter output.is an indication of the level in the upper plenum , or upper.head of the.reactor vesse 1. The* measurement wi 11 provide an accurate indication for guidance *when operating the reactor ves- . sel head vent. The measurement will also provide a confirmation that the level is above* the hot leg nozz*les. When the pump in the loop with the hot leg connection is operating, the d/p would be greater than the transmitter span, and the trans-mitter output would be disregarded.
- 2.
Reactor Vessel - Narrow Range The transmitter span-covers the total height of the reactor vessel * .. With pumps shut down, the transmitter output is an indication of the collapsed water level, i.e., as if the steam bubbles had been separ-ated from the water volume. The actual water level is slightly higher than the indicated water level since there will be some quan-tity of steam bubbles in the water volume. Therefore, the RVLIS provides a conservative indication of the level effective for ade-quate core cooling
- 4-21 7581A
When reactor coolant pumps are operating, the d/p would be.greater than the transmitter span, and the transmitter output would be dis-regarded.
- 3. Reactor Vessel - Wide Range The.transmitter span covers the entire range of interest, from all pumps operating with a water-solid system to a completely empty reactor vessel and therefore, covers the measurement spans of the other two instruments. Any reduction in d/p compared to the normal operating condition is an indication of. voids in the vessel. The reactor coolant. pumps will circulate the water and s.team as an
- essentially homogeneous mixture, so there would be no distinct water level in the vessel.
When pumps are not operating, the transmitter output is an additional indicatio.n of the level in the vessel, sup-plementing the indications fran the other instruments. The output of each transmitter is compensated for the density*di!ference between the fluid in the reactor vessel and the fluid in the reference. leg at the initial *ambient temperature. The compensation is b*ased on a wide range. hot. leg. temperature measurement or a wide range. system pres-sure measurement, whichever results in the-highest value of water den-sity, and, therefore, the lowest value of.indicated level. Compensation based on temperature is applied when the system is subcooled, and com-pensation based on pressure (saturated conditions} is applied if super-. he_at exi_sts at the hot leg temperature measurement point. The output of each transmitter is also compensated for the density dif-ference between the fluid in the reference leg during an accident with elevated temperature-in the containment and the fluid in the reference leg at the initial ambient temperature. The compensation is based on t~erature measurements on the vertical sections of the reference leg. The corrected transmitter.outpuis are displayed on meters installed on the control board, one meter for eac~ measurement in each train. A - three-pen recorder is also provided on~the control board to record the 4-22 7581A
level or relative d/p and to display trends in the measurements. An indicator light installed under the upper range level meter would pro-vide an indication if the pump in the loop with the hot leg connection is operating, and therefore an indication that the off-scale reading on the Tieter should be disregarded. During normal plant heatup or hot standy operation with all reactor coolant pumps operating, the wide range d/p meter would. indicate 100 percent on the meter, an indication that the system is water-solid. If less than all pumps are operating, the meter would indicate a lower d/p (determined during the plant startup test program) that would also be an indication of a water-solid system. With pumps operating, the narrow range and upper range meters would indicate off-scale. If all pumps are shut down, at any temperature, the narrow range and upper range meters would indicate 100 percent, an indication that the vessel is full. The wide range d/p meter would indicate about 33 per-cent of the span of the meter, which would be the value (determined during the test program) corresponding to a full vessel with pumps shut down. In the event of a LOCA where coolant pressure has decreased to a prede-termined setpoin1;, existing emergency procedures would require shutdown of a11 reactor coolant pumps. In these cases, a level will eventually be established in.the reactor vessel and indicated on all of the meters. The plant operator would monitor the meters and the recorder to determine the trend in fluid mass or level in the vessel, and con.firm that the ECCS is adequately compensating for the accident conditions to prevent ICC. Future procedures may require operation of one or more pumps for recov-ery fran certain types of accidents. When pumps are operating while voids are developing in the system, the pumps will circulate the water and steam as an essentially homogeneous mixture. In these cases, there will be no discernible level in the reactor vessel. A decrease in the 4-23 7581A
measured d/p compared to the nonnal operating value will be an indica-tion of voids in the system, and a continuously decreasing d/p will indicate that the void content is increasing, that mass is being lost fran the system. An increasing d/p will indicate that the mass content is increasing; that the ECCS is effectively*restoring the system mass content. 4.5 RVLIS ANALYSIS In order to* evaluate the usefulness of the RVLIS during the approach to ICC, it was decided to detennin~ the response of the RVLIS under a variety of fluid conditions. The.RVLIS response was analytically deter-mined fer a number of small break transients. The response was deter-mined by ca 1 cu 1 ati ng the pres sure difference between the upper head and
- lower plenum and converting* this to an equivalent vessel _head in feet.
(Note that RVLIS indications will actually be represented by percent of span) Saturation density at the fluid temperature in the upper plenum .was used for this conversion. _This approximates the calibra~ion that will be used for the RVLIS. _ This indication corresponds to the RVLIS configuration used for non-UHI _pl ants. The conclusions of the study are expected to be the same far the UHI configuration. The indication of the upper span (hot leg ta upperhead) is not included in this analysis. The upper span indication will be used for head venting operations and will not be used to indi-cate the approach to ICC. When the reactor coolant pumps are not operating, the RVLIS reading will be indicated on the narrow range scale ranging from zero ta the height of the vessel.
- A full scale reading (100 percent of span) is indicated when the vessel is full of water. This reading represents the equiva-lent collapsed liquid level in the vessel which is a conservative indi-cation af the approach to ICC.
The RVLIS indication can alert the operator that a condition of ICC is being approached and the existance of ICC can be verified by checking the core exit thennocouples. When the reactor coolant pumps are operating the narrow range RVLIS meter will be pegged at full scale. 4-24
When the reactor coolant pumps are operating, tne RVLIS reading will be indicated on the wide.range scale which reads from Oto 100 percent. The 100 percent reading corresponds to a full vessel with all of tne pumps in operation. With the pumps running the RVLIS reading is an indication of the void fraction of the vessel mixture. As the void content of the vessel mix-ture increases, the density decreases and the RVLIS reading will decrease due to the reduction in static head and frictional pressure drop. The latter effect*will be enhanced by degradation in reactor coolant pump performance. When this reading drops to approximately 33 percent, there wil 1 also be an indication on the narrow range scale. This fraction approximately corresponds to a vessel mass at which would just cover the core if the pumps were tripped. Four smaH-break transients under a variety of conditions are discussed in the next section. Three of these cases were obtained from WFLASH an*alyses and* the other was obtained fran the ICC analysis using NOTRUMP. A description of these codes can ce found in References 1 through 6 in Section 6.0. The transients included in this report are listed Table 4.2 whicn gives a brief description of the transient, the plant type, and the model used for the analysis. A discussion of each transient is provided in tne next section. Figures 4-12 through 4-23 provide plots of vessel two-phase mixture level, RVLIS narrow range reading, mixture and vessel void fraction, and for Case B with pumps running, RVLIS wide range reading and.cold leg mass flowrate ** The two-phase mixture-level plotted is that which was predicted oy tne codes for the mixture height below the upper support plate. Water in the upper head is not reflected in this plot. The RVLIS reading that would be seen is plotted on the same figure for ease of comparison. The void fraction plots are for the core and upper plenu~ fluid volumes. The mixture void fraction includes the volume oelow tne two phase mixture level while the total void fraction also includes tne steam space above the mixture level. 4-25
4.5.1 Transients Investigated Case A The initiating event for this transient is a 3 inch break in the cold leg. After the break opens, the system depressurizes rapidly *to the steam generator secondary safety valve setpoint. Consistent with the FSAR assumptions, the reactor coolant pumps are assumed to trip early in the transient when the reactor trips. The system pressure hangs up ~t the secondary setpoint, until the loop seal unplugs at approximately 550 seconds, allowing steam to flow out the break and the depressurization continues. The core uncovers while the-loop seal is draining then recovers when the loop seal unplugs. The core then begins to uncovel" again as more mass is-being 1 ost through the break than is being replaced by safety injection. The core begins to recover at about 1500 seconds when the acc1111u lat ors begin to inject. \\ This transient does not represent a condition that would lead to ICC but it does represent a break size in the range that would be most probab 1 e if a small-break did occur. The response of the RVLIS for typical con-ditions for*which it would be used can be investigated with this tran-sient. After the reactor coo 1 ant pumps trip the RV LIS reading drops rapidly to the narrow,range scale. It f.alls until the pressure drop due to flow becomes insignificant compared to the static head of the fluid in the vessel. The first dip in the RVLIS reading is due to the behavior of the upper head. When the upper head starts *to drain it behaves like a pressurizer. The pressure in the upper head remains high until the mixture level drops to below the top of the guide tube where steam is allowed to flow fran*the
I upper head to*the upper plenum. When this occurs the upper head pres-sure decreases - thereby increasing the vessel d/p - and the RVLIS reading again more accurately reflects the vessel inventory. This phenomenon is more prevalent for large-break sizes and the effect will be of brief duration for breaks in this range. Furthennore, the ICC guidelines require verification of the RVLIS reading through the use of the core exit thennocouples. During this phenomenon, the core exit thennocouples would read saturation temperature. Therefore, this early phenomena in the,upper head will not cause a false indication of ICC. When the vessel begins to drain during the loop seal uncovery the RVLIS reading trends in the same direction as the vessel level. The RVLIS reading remains below the vessel mixture level and is therefofe a con-servative indication. When the vessel mixture level increases after the loop seal unplugs the RVLIS reading follows it. Then, RVLIS re~dings continue to follow the vessel mixture level throughout the transient while underpredicting the actual two-phase level. The wider difference. between the Rvus* level and the two-phase level later in the transient ;s due to the system being at a lower pressure which allows more bubbles to exist in the mixture. Case B This case is the same as case A except it was assumed that the reactor coolant pumps continued to operate until 750 seconds. If the reactor coolant pump trip criteria is followed the pumps would be tripped much earlier in the transient. This case is, however, instr_uctive in deter-mining the RVLIS response when the pumps are running.
- After the break opens, the system depressuri zes rapidly to the sec_ondary safety valve setpoint, and then begins a period of very slow depressuri-zation. During this time the upper portions of the system drain.
Due to the reactor*coolant pump operation, the two-phase mixture in the vessel remains at the hot leg elevation, although the void fraction of the mixture continues to increase. 4-27 7581A -~--
At 750 seconds the system has drained to the point that steam can be vented through the break and the system begins to depressurize more rapidly. The pumps are also tripped at this time resulting in a col-lapse of the mixture in the vessel and the core uncovers. The vess*e1 continues to drain until the accumulators inject at about 1000 seconds to recover the core. There is~ subsequent uncovery which will be ended when the pressure is low enough for the.safety injection to make up for mass lost through the break. During the early portion of the transient the wide range RVLIS reading drops fairly smoothly from 100 percent to about 20 percent, which is due to the decreasing mass in the ves*sel
- and the decreasing pressure drop. as the pump performance is degraded.
The plot of cold leg mass flowrate is indicative of,the pump degradation. The oscillations in this plot are due to alternate steam and two-phase flow predicated by WFLASH.
- When the fl ow through the pump becanes mostly steam, the increasing void fraction of the vessel mixture becomes the predominant factor in the decreasing RVLIS reading.
RCP operation keeps the steam and water mixed enough that the mixture level does not fall below the hot legs, although the mixture void frac-tion is increasing during this time. This loss -of inventory*is indi-cated by the continued drop in the RVLIS reading..When the pumps trip, the steam and water in the mixture separate and there is a rapid decrease.in the core mixture level and mixture void fraction *although the vessel void fraction continues to rise. The fact that mass is being -...redistributed rather than lost is seen in.the RVLIS-reading - there is little change in the reading (compared to the change in level) from 750 seconds to the time that the accumulators come on. The prolonged reactor coolant pump operation has caused the downcomer to drain so that when the accumulators cane on the cold acc1.111ulator water condenses steam in the downcomer causing a local depressurization. The downcaner pressure is then temporari 1 y 1 ower than the upper head pres-sure due to inertia and the RVLIS reading becomes temporarily negative. 4-?8 7581A
This period-of erratic indication is brief (one or two minutes). The pressure wi 11 equilibrate and the RVLIS wi11 resume fol lowing the vessel mixture level. This phenomenon has only been observed when the accumu-lators inject when the aowncomer is highly voided. There is no apparent discrepancy during accumulator injection when there is a significant amount of water in the downcomer. It is believed that this effect is exaggerated by the modeling techniques used in WFLASH (which uti 1 ize a homogenous equilibrium assumptions at the accunulator injection loca-tion). For the remainder of the transient the RVLIS reading follows the vessel level closely. Case C The initiating event for this transient is the opening of the pressur-izer power operated relief valves (PORVs). The reactor coolant p1.111ps and the reactor trip early in the transient on a low pressurizer pres-sure signal consis.tent with FSAR assumptions~ Auxiliary feedwater is available in this case but, no pumped*safety injection is assumed. The pressurizer mixture level rises to* the top of the pressurizer early in the transient and stays at this level throughout most of the tran-sient. The fl<M through the PORVs ~l ternates between steam and twophase mixture while the pr~ssure in the system drops rapidly to the steam generator secondary safety valve setpoint. The pressure hangs up at this value until the upper portion of the system has drained and then continues to decrease. When the upper portions of the primary system (excluding the pressurizer) have drained the vessel* mixture level begins to decrease and continues until the core completely. uncovers. The RVLIS reading drops rapidly to the narr.ow range span after the reac-tor coolant pumps are tripped. When the vessel level reaches the hot leg elevation the calculated RVLIS readings begin to oscilate due to the mode 11 ing used in WFLASH. In ltlFLASH, the hot legs are connected to tne vessel by point contact connections. This rrcdel 1 ing technique causes the hot leg flCM to alternate between steam and two pnase flow. The oscillitory behavior of the calculated RVLIS reading continues wnile tne 4-29
level remains at the hot legs. The average calculated value during this period of time shows that the.RVLIS reading is a conservative indication of the mixture level. When the vessel mixture begins to decrease, the RVLIS reading decreases as well. The RVLIS continues to underpredict the two-phase mixture level and to follow the trend. Case 0 This case is one of the transients investigated for the ICC study using NOTRUMP. A more detailed discussion of this transient can be found in Reference 1. The RVLIS reading i-s below the vessel mixture level throughout most of the transient and is therefore a conservative indication. The RVLIS reading follows the same trend as the vessel mixture level except for early in the transient when the mixture void fraction is fluctuating. Included in the plots for this case is a compar~son of the mass inven-tory in the core and upper plenum regions to the RVLIS reading. This comparison shows that the RVLIS reading also corresponds very well with the relative vessel mass inventory. Also included is a comparison for
- the UHi and non-UHi RVLIS configurations. For the UHi RVLIS configura-tion, the pressure difference is measured from the hot leg to*the lower plenum rather than the upper head to lower plenum.
This plo.t shows a very good co~arison between the two systems, indi~ating that either will give a useful indication. 4.5.2 Observations Of The Study The RVLIS will provide useful information for breaks in the system ranging from small leaks to breaks in the limiting small-break range. For breaks in tMs range, the system conditions will change at a slow enough rate that the operator will be able to use the RVLIS information as a basis for some action. 4-30 7581A
For larger breaks, the response of the RVLIS will be more erratic, due to rapid pressure changes in the vessel, in the early portion of the blowdown. The RVLIS reading will be useful for monitoring accident recovery, when other corroborative indications of ICC could al so be observed. Very few instances have been identified where the RVLIS may give an amibiguous indication. These include a break in the upper head, accumu-lator injection into a highly voided downcomer, periods of time when the upper head behaves like a pressurizer, upper plenum injection, and peri-ods of void redistribution. A break in the upper head may cause a much lower pressure to exist in the upper head compared to the rest of the RCS. Because of this the pressure difference between the lower plenum and the upper head is much larger than is seen for an equivalent vessel level when the b~eak -is----~:::::::~:=~-==.:: located elsewhere in the system. The reading, in fact, may never reach the narrow range scale. If the narrow range reading remains at full scale and the wide range reading is greater than that reading which would indicate a full vessel with the reactor coolant pumps tripped, a break in the upper head is indicated *. This situation should not cause a problem in detecting ICC because of the parallel logic for the gkick-out11 to the ICC procedures. If the RVLIS indication is erroneous due to a break in the reactor vessel upper head, the operator will begin fol-lowing the ICC procedure if the selected core exit thermocouples read 12oo*F. This situation* only exists, however, when the break discharge is large enough to cause a large d/p through the flow paths connecting the upper head to the rest of the system. These flow paths become the limiting factor in the depressurization rate. This analysis is applicable to all Westinghouse PWR plants, including those plants with upper plenum injection (UPI). The normal condition for continuous UPI occurs only with the operation of the low head safety injection pumps, which does not occur until a pressure of under 200 psi 4-31 7581A
Flow blockage is not expected to decrease the usefulness of the RVLIS indication. The increased d/p due to the flow blockage will be small during natural circulation. The RVLIS will continue to follow the trend in vessel level. When the reactor coolant pumps are operating, flow blockage is not expected to occur unless the pumps had previously been tripped and are being restarted after an ICC situation already exists * . If flow blockage were present when the pllllps were running the RVLIS indication would still be useful and, although the indication would be somewhat higher, would continue to follow the trend in vessel inventory. 4.5.3 eonclasions
- 1.
- With. the:..RCPs tripped, the Westingho.us.a...RYill:-wi.U _ result in an underpredicted indication of vessel level while provfcffni~:=1inambi.....
guous indication of the mass in the vessel. The Westinghouse RVLIS will also measure the vessel level trend reasonably well.
- 2.
With the RCPs tripped, it is feasible to determine a setpoint for the RVLIS to warn the operator that the system_ is approaching an uncovered core. 3 *. The RVLIS. should be used along with the core exit thermocouples to detect I~C.
- 4.
Wi'th the RCPs running, the RVLIS is an indication of the mass in the vessel.
- 5.
When the RCPs are running, and the RVLIS reading drops to the narrow range scale, there is significant voiding in the vessel and the core would just be covered if the pumps were tripped.
- 6.
A break of sufficient size in the upper head could cause the RVLIS to give an ambiguous indication of vessel mass. The core exit thermocouples, however, will provide an indication of ICC if appro-priate. 4-33 7581A
- 7.
Accumulator injection when the downcomer is highly voided could result in a temporarily erratic indication.
- 8.
The RVLIS may significantly underpredict the vessel mass while the fluid in the upper head is flashing. However, use of the core exit thermocouples will preclude a premature entry to the ICC procedures.
- 9.
Rapid void redistributions will not be detected by the RVLIS. 4-3'4 7581A
TABLE 4.1 CONFORM.A.NCE WITH REGULATORY GUIDE 1.97, DRAFT 2, REV. 2 (6/4/80) . FOR THE MICROPROCESSOR DISPLAY SYSTEM Seismic*qualification Single failure criteria Environ~ental quailification
- [ I EEE-323-1971 applicability]
Power Source Quality Assurance 10CFRSO Appendix B applicability Display type and method Unique identification Periodic Testing
- In some cases IEEE-323-1974 is applicable *
- 683A Yes Yes Yes Class lE Yes Vertical scale voltage processed in addition to a recorder Yes
'fes MP
CASE A 8 C D PLANT 3 loop 2775 MWt 3 loop 2775 MWt 4 loop UHI type 3411 MWt 4 loop Non-UHI 3411 MWt TABLE 4.2 TRANSIENTS INVESTIGATED DESCRIPTION 3 inch cold leg break - FSAR assumptions*; WFLASH 3 inch cold leg break - RCPs trip at 750 seconds - otherwise, FSAR assumptions; WFLASH 2.5 inch break in top of pressurizer - no UHI - no pump_ed safety injection-- pumps not running; WFLASH 1 inch cold leg break - no high head safety injection; NOTRUMP
- RCPs tripped at reactor trip, mininrum pumped safety injection is available, minimtm1 auxiliary feedwater is available
- 4-36 7581A
MOVEABLE REACTOR CORE DETECTOR CONDUIT --..J TRAINA TRAIN I Figure 4-1 Reactor Vessel Level Instrument System 17917*1 NARROW RANGE
17917-2 -HEAD PENETRATION _ _ll'"-~~11""1'- CONTAINMENT WALL Figure 4-2 Process Connection Schematic, Train A
I,. Figu.-e 4-3 Typical Plant Arrangement for RVLIS I I I L - +-PROTECTED ENVIRONMENT Hi6fT -t40FT ..J I.II e a: a. 0~ ~ w a: t OFT -16FT
17917-5 Figure 4-4 Reactor Vessel Level Instrument System Block Diagram (One Set of Two Redundant Resets Shown) . a,c
. r--,- - - -l __ -_-_@
v_ess_E_L_L_E_v_E_L_MO_N_n_o_R ___ -_-_-_-_-~ - - - - -, I ALARM I ICAUTIONI INORMALI L--------------------------------------~ I RESETIG PROCESSOR figure 4-5 Remote Oisplay Module (Control Board)
REACTOR VESSEL LEVEL
SUMMARY
VALUE NORMAL STATUS PLENUM LEVEL 73% 100% ALARM VESSEL LEVEL 4 7%
- 0%
INVALID. FLOW HEAD >110%*# 100% 0 FF SC A PUMPS RUNNING: 41. 42. 43. 44 ISOLATOR ALARMS: LI3
- DISABLED: TJ TH1
,-1gure 4-5a "Vessel Level '.:.u111mary Oispldy
REACTOR VESSEL LEVEL TREND TIME I PLENUM VESSEL MIN LEVEL LEVEL 00 73% 47" I ....:.15 78% 49% I -30 79" 62" I -45 82% 56% I -60 97% 99" I Figure 4-5b Vessel Level Trend Display F'tow HEAD >110% 98% 9 7 % 9 8 % 99% OS ~ -:J
a.b.c Ftgure 4-6 Jyplc1I Plant Arrangement For RVLIS
Figure 4-7 Block Diagram of Compensation Function 17917-7 a.b.c
17917-8 a,c Figure 4-7a Simplified Schematic of Density Compensation System
a,b,c figure 4-8 Surface Type Cl111P-lln Resistance Yeniperalure Detector
420 340 ii: 306 ~ w a:. ~ a: lU
- o. 206
- t LU f-120
, *..__ 72 PSIA -- 0 10 3 6 0 10 CAUSTIC SPRAY 72 PSIA ~ I ..,~ SATURATED~ STEAM ~...-I I I I I I I
1 3
6 20 24 16 SEC MIN MIN SEC MIN MIN MIN HOUR DAV TIME
- TIME BETWEEN TEMPERATURE TRANSIENTS MUST BE AT LEAST ONE HOUR OR UNTIL TEST UNITS RETURN TO A STEADY ST A TE OUTPUT. TIME ABOVE 340°F MUST BE FIVE MINUTES OR LESS.
f1~ure 4-9 HELB Simulation Profile
figure 4-10 ITT Barton Hydraulic lsohtor lnterna1 Scheme a.b.c co... ~ (X)
17917-17 a,b,c Figure 4-11 ITT Barton 11High Volume" Sensor Bellows Check Valve
40 35 30 26 ti 20 w IL 16 10 0..... ---L----Ji-----------J---.... --~---L-_.;...--1, __ 0 260 500 760 1000.;, 12i0 11GG 1760 2000 2260 2600 TIME (SECOND1il figure 4-12 Case Al-Loop Plant, 3 Inch Cold Let Breik, Pump Trip with Reac(or Tr~p. RVllS Reauing in~ Vessel Mixture level a.b.c
1.0 0.8 z 0 0.8 ~ c( a:
- u.
9 0.4 0 > 0.2 0.0 0 r VESSEL r CORE MIXTURE 260 600 760 1000 1260 1600 1760. 2000 TIME asECONDSI figure 4-13 Case A 3-Loop Plant, 3 Inch Cold Leg Break, Pump Trip with Reactor Trip, Void Fraction I I 2260 2600
~ 80 w _. ct fA w " z 60 ~ a: lU a ~ Cl z 40 ~ w a: ~ 20 a: 0 260 760 1000 1260 1600 1760 TIME (SECONDSI figure 4-14 Case 9 3-Loop Plant, 3 Inch Cold leg Break, Pump Trip at /aO Secmul1s, Wide Range ~eading a.b.c 2000
40 36 30 16 10 5 0 17917-25 0 250 500 750 1000 1250 1500 1750 2000 TIME (SECONDS) Figure 4-15 Case B 3-Laop ?lant, 3 Inch Cold Leg Break, ?ump Trip at 750 Seconds, RVLIS Reading and Mixture Level
z 0 t ct a: IL Q - 0 > 1.0..-------------------------------- 0.8 0.8 0.4 0.2 0 VESSEL CORE MIXTURE 260 600 760 1000 1260 1600 1760 TIME CSECONDS) Figure 4-16 Case B 3-Loop Plant, 3 Inch Cold leg Break. Pump Trip at jju Secon~se Void fraction. 2000 U) i-l m
16000 12600 6 w l'! 10000 .~ w ~ 7600 IC ~ ..I IL 6000 I 0 2600 UJ .J 9 8* 0 -2600 0 260. 600 760 1000 1260 1600 TIME (SECONDSt figure 4-17 Case 8 3-Loop Plant,~ Bnch Cold leg Break, Pump Trip at 750 :;econds, Cold Leg Mass flowrate (LB/Sec) 1760 2000
17917-28 a.b.c - 40 35 30 25 15* 10 5 o.._ ____________.._ _______._ _______ _ 0 400 800 1200 1600 2000 .2400 TIME (SECONDS) Figure 4-18 Case C 2.5 Inch Pressurizer Break,"No SI, RVLIS Reading and Mixture Leve 1
- 2800 I -
a.b.c
- 100 80
/ ~ z 60 0 fi <( a:
- u.
40 a - 0 > 20 0 0 260 600 760 1000 1260 1600 1760 2000 2260 2600 2760 TIME (SECONDS) figure 4-19 Case C 2.5 Unch Pressurizer Break, No SI, Void Fraction
40 36
- 30.
25 ti 20 w IL 11i 10 Ii 0 a.b.c 2600 6000 1600 10000 12600 16000 TIME (SECONDSI figure 4-20 Case O 1 Inch Cold leg Break, ICC Case, RVL!S Reading and Mixture Level.
a.b.c 95
- i:
Bx 104 m ..I 30 IC t ~ z ~ w 26 w z
- c 6 X 104
~ a .Z ~ ~
- i:
UJ 20
- i:
IC z ~ W* 4 x 104 ..I A. 2: 16 a: w w a: 0 u 0 10 z ~ 2 X 10-0 w a: 0 u 6 0 2600 6000. 7600 10000 126000 16000 TIME (SECONDS) Figure 4-21 Case O 1 Inch Cold Leg Break. ICC Case, Mixture Level
- a< VLIS Reading and Measured inventory.
35 30 26 t; 20 w IL 16 10 6 o-------"------'----....1.-.:.----L-----'-----_J_ 0 2600 6000 7600 TIME tSECONDSt 10000 12600 f tgure 4-22 Case O ! Inch Cold Leg Break 0 ICC Case, RVLIS Reading and Mixture level. 16000 a,b,c
1.0.----------~---------------_:._ _______,......:,. 0.9
- E
- , z 0.11 w
.J A. llC w 0.1 CL A. ~ 0.8 c( w a: 0 0.6 Q z Q ~ 0.4 a: IL 9 0.3 0 > ..J w 0.2 ta w >
0.1 LEGEND
-- TOTAL vom FRACTION MIXTURE VOID FRACTION I I I 1 I " I I . M I 1 11 I I I 11 I I I 11 I I I II I I I 11 I I I 11 I I I : 1 I I I I I I ~ I I I 111 I I ,'l' I I I I ~ I I I -,--~---~----J I '1 ¥ ,,,1 I If 1,-1 1----vil1 O...__.'-----J-------------a..-----------L-----.JILLI 0 2600 6000 7500 TIME ISECONDS8 10000 12600 Fiw1re 4-23 Case O 1 Unch Cold Leg Break, NCC Case, Void Fraction 16000 u,... .... w w
5;8**GUIDEtINES*F0R*THE*USE*0F*ree*INSTRUMENTATI8N 5.1 REFERENeE*0WNERS*GR0~P*PR0eEB~RES Based on the analyses defined in Sections 1.3 and 4.5 of this report, Westinghouse and the Westinghouse Owners Group have developed a Refer-ence Emergency Operating Instruction to address recovery from ICC condi-tions caused by a small-break LOCA without high head safety injection. This instruction has been transmitters to the NRC via Westinghouse Owners Group Letter, OG-44, dated November 10, 1980. It should be noted that this instruction was developed on a generic basis as a technical reference for implementing plant specific procedures, and must be tailored to meet plant specific needs. 5.2 SAMPtE*TRANSIENT The response of the vesser level indications, other ICC instrumentation and system response during the_se ICC events and recovery actions are described in References 1 and 2. 5-1 7581A
6.0 REFERENCES
- 1.
Thompson, C. M., et al., "Inadequate Core Cooling Studies of Scenarios with Feedwater Available, Using the NOTRUMP Computer
- Code, 11 WCAP-9753 (Proprietary) and WCAP-9754 (Non-Proprietary), July 1980.
- 2.
Mark, R.H., et al., 11 InadequateCore Cooling Studies of Scenarios with Feedwater Available for UHI Plants, Using the NOTRUf,f> Computer Code,* \\iitAP-9762 (Proprietary) and WCAP-9763 (Non-Proprietary), June 1980.
- 3. *Report on Small Break Accidents for Westinghouse Nuclear Steam Supply System, 11 WCAP-9600 (Proprietary) and WCAP-9601 (Non-Pro-prietary}, June 1979.
4 *. Esposito, V. J., Kesavan, K., and Maul, 8. A., 11WFLASH - A FORTRAN-IV Canputer Program for Simulation of Transients in a Multi-Loop PWR,* \\ICAP-8200; Revision 2 (Proprietary) and WCAP-8261, Revision l (Non-Proprietary}, July 1974.
- 5.
Skwarek, R., Johnson, W., and Meyer, P., *westinghouse Emergency Core Cooling System Small Break October 1975 Model,* WCAP-8970 (Pro-prietary} and WCAP-8971 (Non-Proprietary), April 1977.
- 6. "Analysis of Delayed Reactor Coolant Pump Trip During Small Loss of Coolant Accident for Westinghouse NSSS," ltCAP-9584 (Proprietary} and WCAP-9585 (Non-Proprietary}, August 1979
- 6-1
RESPONSES TO NRC REQUEST FOR ADDITIONAL INFORMATION ON THE WESTINGHOUSE R.V.L.I.S. SUM~RY REPORT ( i.i Processor)
r Item 1 Justify that the single upper head penetration meets the single failure requirement of NUREG-0737 and show that it does not negate the redun-dancy of the two 1 nstrument trains.
Response
- 1.
Redundancy is not compromised by having a shared tap since it is not conceivable that the tap will fail either from plugging or break-ing. Freedom from plugging is enhanced by, 1) use of stainless steel connections which preclude corrosion products and, 2) absence of mechanisms, such as, flow for concentrating boric acid. It is also inconceivable that the tap will break because it *is in a pro-tected area. It should also be pointed out that in other cases where sharing of a tap occurs*in the RCS, we know of no prior experience reporting deleterious malfunctions of the shared tap. Also, even if the shared tap does fail, it should be recognized that RVLIS is oot a Protection Syste.m initiating automatic action, but a monitoring system with adequate backup monitoring such as by core exit thermocouples for operator correlation.
T Item 2 Describe the location of the level system displays in the control room with r~spect to other plant instrument displays related to ICC monitoring, in particular, the saturation meter display and the core exit thermocouple display. <~
Response
,,J
- 2.
- The RVLIS displays in the Surry Unit 1 Control Room are located on Vertical Board Section 1-1 in the upper left corner. This would correspond to Section 2-1 for Surry Unit 2.
This location was chosen based upon the need for RVLIS displays to be located near the Post Accident Monitoring Control Panel and the minimal amount of existing panel space available at Surry. The RVLIS displays are operated in conjunction with the Reactor Vessel Head Vent System which is *controlled at the PAMC Panel. The Inadequate Core Cooling Saturation Meters for Surry Unit 1 are loc~ted on Vertical Board Section 1-2 directly below the ~tatus Trip, Bypass and Permissive lights. This would correspond to Section 2-2 for Surry Unit 2. This location was chosen based upon the proximity of Reactor Coolant System data available on this section of Vertical Board and the available panel space. The Incore Exit Thermocouple Meter is.!located on the Incore Instrument Pane 1 s which are located in the rear of the Contra l Room along the wall which separates the Control Room from the Turbine Building walkway. The location of the panels was chosen during the original design of the pl ant. The location of each device with respect to each other can best be. described as a triangle (see attached figure). The Inadequate Core Cooling Saturation Meters and the RVLIS displays are located on adjacent panels with the Saturation Meters to the.right if facing the panels. The Incore Exit Thermocouple Meter is located on the
Incore Instrument Panel, which is to the rear of the Control Room and directly opposite Vertical Board Section 1-2 for Surry Unit 1 and Section 2-2 for Surry Unit 2, where the Saturation Meter is located. The operator is in the middle of this triangle and has an unobstructed view of each device.
Plf\\ \\'-I 4*.,~.. 'TUl(~-- $UPV tMfl\\ r,[~ !>*Z i j .,,e l __ _ ,Cl AVT. CH(M. (11J** ff.:,o:) I +
- I ~RCP VIB. DFr. r,,na Ff-3Ct
- 1 I,
Orf1C£
- Lr==-F
- Yo* '
~ ',ol I I~~
~* Item 3 Describe the provisions and procedures for on-lirie verification, cali-bration and maintenance.
Response
3 *. In general, t_he system electronics are verified, maintained and calibrated on-line by placing one of the redundant trains into a test and calibrate mode while leaving the other train in operation to monitor inadequate core cooling. A _general verification is performed before shipment, but plant specific data is not used. The capability exists for the *operator to verify the operation of the system. This would involve discon-necting the sensors at the RVL1S electronics, providing an arti-ficial-input, and observing the response of the system on the front panel and remote display. On-line calibration of the system is made possible by the controls available on the main processing unit. The calibration consists of entering constants into the non-volatile RAM_along with adjusting the potentiometers on the analog to digital conversion cards. The initial calibration is done when the system is installed, but subse- - quent calibrations can be performed as described in the Technical Manua 1 to maintain* system accuracy. The RVLI S system_ requires the nonna 1 maintenance given to other control and protection systems within the plant. On-line mainte-nance is accomplished by placing only one of the two redundant trains into* maintenance at a time this will allow continued moni-toring of inadequate core cooling. In addition, software programs are provided so that the front panel controls and display can be used to perform a function.al test, serial data link tests, calibration tests and deadman timer tests. These tests are considered part of the operator maintenance proce-dures and should be performed monthly. For additional details of procedures see "Attachment A".
AITACHMENT A SYSTEMS OPERATING PROCEDURES 2-1. PURPOSE The objectives of these instructions are to establish the requirements for the use of the Reactor Vessel Level Instrumentation System (RVLIS) for various plant conditions and to specify the maintainability require-ments of the system equipment. 2-2. PREREQUISITES o The capillary lines have been vacuum filled, per the instruc-tions of section 4. o Ensure that the hydraulic isolators are zeroed (within plus or minus 0.1 in.3). o Calibrate the d/p cells per *instructions of ITT Barton Manual . for Model 752~ Level B, transmitters. o The process equipment must be.scaled using the appropriate scaling document. o Determine the height of the upper top piping above the inside top of the vessel. 2-3. INITIALIZATION With the plant less than 2QQOF and less than 430 psig, obtain the following data for trafns A and B:
(1) With an automatic data logger, record the following: . o T hot o RCS pressure o d/p transmitter output o Signal to the remote di'splay (2) Manually record: o Level indication readings o* Hydraulic isolator dJa:l readings o Reference leg RTD output (3) Record the above data for the following reactor coolant pump operations: NOTE The various configurations should be obtained through the normal startup if possible. NOTE Upper plenum will read offscale if pump is running in the instrumented loop; narrow range will read offscale with one or more pumps running. o No pumps running NOTE An indication of 100 percent reading repre-sents a level.to the inside top *of the vessel. The height of the upper top piping above the inside top of. the vessel will result in a reading greater than* 100 per-cent. This added height is plant specific and must be determined prior to adjusting the process equipment (upper plenum and narrow range) for full scale indication
- l
o One noninstrumented loop pump running o Two noninstrumented loop pumps running o Two noninstrumented loop pumps.and one instrumented loop pu!Jl) running o All pumps running -- Adjust process equipment so that wide_ range indication reads 100 percent. (4) With all pumps running, increase RCS pressure. - temperature to Tavg no-load and record data refer to step (1) every. 500F increment. Data of step (2) should be recorded at 3500F and at Tavg no-load. Adjust process electronics for density co!Jl)ens~tion at Tavg no-load. Verify that wide range indication reads 100 percent. (5) Trip all pumps and record data per steps (1) and (2). Verify that upper plenum and narrow *range indication is in agreement. with the reading of step (3) 11 No pumps running". (6) Restart pumps in sequence and record wide range readings for both trains for each pump combination * (7) Enter into the equipment programning the expected percent level for the various pu!Jl) contlinations per the micro-processor instruction manual. 2-4. NORMAL PLANT OPERATION With the plant at power, the level readings should be as follows: Wide range .rllO percent (wide range reading will increase from 100 percent to approximately 110 percent with all pumps running, as reactor power is increased from zero to 100 percent)
Narrow range Upper plenum Off Scale - High Off Scale - Low (RCP status light on main control board is off) Any reduction in wide range expected readings (with all pumps running) can only be caused by the presence of voids in the circulating water. Voids will not exist without reduced pressure which could trip the reactor, so all accident conditions will proceed from a condition of zero power ( 100 percent reading on the wide range). Check that the pressure has decreased or that subcooling meter confirms saturation conditions exist; then readings below 100 percent are an indication of voids in the coolant. If the actual readings differ from the expected readings by 3 percent for a single train, refer to troubleshooting (paragraph 2-10). If the indication for both trains differs from the expected readings, refer to the emergency operating instructions for inmediate and subse-quent action. 2-5. REFUELING After depressurization and prior to lifting the reactor vessel head, perform the following steps to prepare the RVLIS: (1) Close reactor vessel level head connection isolation valve. (2) Disconnect piping between the isolation valve and the sensors. NOTE Contaminated water residue may be in the pipe.
\\. (3) Provide temporary plugs for the pipe ends of the removable section and stationary sections. Restore the RVLIS after reactor vessel head installation as follows: (1) R,ernove pipe end plugs and reconnect piping section. (2) With the* isolation valve open, backfill the piping from sensors by attaching a water source to the sensor vent. {3) Disconnect waterfill apparatus. (4) At startup (450 psig, <2QQOF), visually inspect piping/ coupling of the reinstalled piping for leakage. {5) At full system pressure, repeat inspection. 2-6 *
- PERIODIC TE STING 2-7.
Plant at Power Perform monthly ca]ibration checks of the process electronics in accor-dance with the process.equipment instruction manual * . 2-8. . Refueling Outages (i) For the d/p transmitters, perform zero check of each d/p tr-lns:nitter by closing.the respective isolation valves and opening the bypass valve.* If zero reading differs from the 1a'st recorded reading by percent, then recalibrate d/p trar1S1i1it1::r using instructfons of Barton Instruction Manual (Model 752) and the* instructions contained in the RVLIS system manual and the appropriate equipment instruction I manuals.
~~----~~- (2) Record the appropriate hydraulic isolator dial readings and' compare results with previous cold shutdown readings. Readings should be within plus or minus 0.1 in.3. (3) Perform the calibration check of the process electronics in acc~rdance with the equipment technical manual. (4) Verify the operability of the RVLIS System during the startup/heatup of plant following a refueling or major plant outage by tracking the displays of the two trains. Readings should be within percent of the previous recorded readings. 2-9. Every Other Refueling Outage In addition to t.he steps of paragraph 2-8, perform the following every other refueling outage: (1) At the process equipment,cabinets, read the impulse line - RTD resistances
- NOTE Take the ambient temperature reading near the RTD and adjust the measured resistance.
accordingly. Compare the adjusted res is-tance to the original results or the previous recorded data. (2) Employing a pneumatics calibration, per instructions of section 4 at the sensor vent ports, check the calibration of the transmitters and perform a time response check of the system. The calibration res~lts should be within plus or minus percent of instrument span of the previous recor-ded data. The time response of the system should be within 10 seconds. This is the time required-for the display instrument to reach the midpoint of a 50 percent step input variable change
- 2-10.
TROUBLESHOOTING, PLANT AT POWER If single indication varies from the expected value, check the following: (1) Call for the sensor status display for any abnormalities * (2) Compare hydraulic isolator di al reading with reading taken from diverse train. and those taken at Tavg no~load condi-tions. Dial readings deviating by more than plus or minus .0.1 in.3 may be indicative of potential capillary line leakage; however, it may not be the reason for the devia-tion in the display reading until the isolator reached the valve-off point. (3) Perform a calibration check of the process equipment, per the appropriate instruction manual. (4) Perform a zero check of the appropiate d/p transmitter. If more than one indicator/display deviates from the diverse train or from Tavg no-load readings, check the following: o ColTITion isolator dial readings versus previous reading o d/p transmitter valve lineup o Process equipment power supplies If repairs are required to the capillary lines, the system must be vacuum-filled and calibrated per the instructions contained in section 4 and the appropriate equipment iristructi on manuals.
Item 4 Describe the diagnostic techniques and criteria to be used to identify malfunctioning components.
Response
The microprocessor based RVLIS performs internal diagnostic* checks of the non-volatile RAM, non-volatile PROM and other microprocessor compo-nents. No operator interface is required for these internal checks which are performed in each cycle. A "deadman" circuit is provided to detect microprocessor failure. This circuit will indicate a processor problem on the front panel of the unit and automatically reset the CPU to restart the microprocessor~ The remote display unit of the RVLIS indicates the status of the input sensors. If any sensor is out of range or disabled a symbol will f_ollow the affected level reading on the sunmary display page. In addition, software programs are p*rovided so that the front panel controls and display can be used to perform a func-tional test, serial data link tests, calibration tests and deadman timer test. These tests are considered part of the operator maintenance pro-cedures and should be perfonned monthly.
Item 5 Estimate the in-service life under conditions of normal plant operations and describe the methods used to make the estimate, and the data and sources used.
Response
The in-service life of the RVLIS Microprocessor based electronics is dependent upon proper maintenance, including the replacement of individual component parts when necessary. The provisions for this maintenance are included in the technical manual. - Based on the assumpti.on of normal* conditions and proper maintenance of the components, the only limitation to the in-service life will be the availability of replacement parts. It is estimated that in 20 years, some of the components wi 11 be technically obsolete and no 1 anger produced. Consequently, the cards may have to be modified in the future to acconmodate the current technology. Thus,any individual component failures are regarded as maintenance considerations and 'their replacement is necessary to prolong in-service,life. In-Service life which is different than Design Life and Qualified Life is dependent upon implementing a scheduled preventative maintenance program including periodic overhaul of the equipment. -In this manner, -the equipment-is restored to a level that continual operatibility is ensured. In developing the maintenance program, repair costs may necessitate replacement of the-equipment. If the maintenance program is followed there is no apparent reason that-operation of the equipment cannot be extended. Some of the equipment is-similar to equipment installed in present Westinghouse plants that have been operating for 10-15 years *
~=-.:.:.r. _; ~. - r I Vessel Level *Instrumentation System for Surry Units 1 and 2; W Design -Code W Valve ID Qty Manufacturer Specification Applicability 3/4 T 78 4 Rockwell G-952855; Rev 0 ASME B&?V Class 1/4 X 28I 10 Autoclave Engineers G-955230; Rev 2 N & S
- i
~ 1/4 N 28I* 6 Autoclave Engineers G-955230; Rev 2* N & S
- Shut off valve which is part o~ the transmitter access assembly.
The 3/4 T78 valve is a stainless steel, manually *operated globe valve whose basic function is to isolate the flow of fluid. The valve is designed for a cycle life of 4000 cycles over the 40 year design life, which satisfies the nonnal plant operating requirements established in above referenced specification. The vav_e i~ a. hermetically sealed valve, designed to be maintenance free with no cons.umable materials making a pressure boundary seal. The instrumentation valves (1i Valve !D's 1/4 x 28I and 1/4 N28I) stainless steel, manually operated.valves, designed to meet the requirements of the above referenced specification, which calls for zero leakage (environmentally and across the seats), minimal fluid displacement during stoke and a 1000 cycle life. For normal plant operating conditions, the metallic parts are -designed for a 40 year service life. The consumable items*, where app 1 icable, are identified in the appropriate drawings and instruction manuals, with recomnended maintenance schedules
- II
Item 6 Explain how the value of the system accuracy (given as+/- 6% was derived. How were the uncertainties from the individual components of the system combi~ed? What were the random and,systematic errors_assumed for each component? What were the sources of these estimates?
Response
- 6. The system accuracy of:. 6% water level was a target value established during the conceptual design and was related to the, dimensions of the reactor vessel (12% from nozzles to top. of core) and core ( 30%), and the usefu 1 ness of the measurement during an accident. Subsequent analyses have established a system accuracy based on the uncertainties introduced by each component in the instrument system. The individual uncertainties, resulting from random effects, were combined**statistically to obtain the overall instrument system accuracy.
Some of the individual uncertainties vary with conditions such as system pressure. The following tab1e
- identifies the individual uncertainties for the narrow range
~ measurement while at a system pressure of 1200 psia. Component and Uncertainty Definition
- a. Differential pressure transmitter calibration and drift allowance,
(+ 1.5% of ~pan) multiplied by the ratio of ambient to operating water density. b~. Differential pressure transmitter
- allowance for change in calibration due to ambient temperature change
(:!:. 0.5% ~f span for!. SOOF) multiplied by the density ratio
- Uncertainty
% Level + 2.1 + 0.7
- c. Differential pressure transmitter allowance for change in calibration due to change in system pressure
(!. 0.2% of span per 1000 psi change) multiplied by t~e density ratio.
- d.
Differential pressure transmitter allowance for change in calibration due to exposure to long-term overrange (::, 0.5% of span) multiplied by the density ratio.
- e. Reference leg temperature instrument (RTD) uncertainty of::, soF and or allowance of+ SOF for the difference between the measurement and the true average temperature of the reference leg, applied to each vertical section of the reference leg where a measurement is made~
Stated uncertainty is based on a maximum containment temperature of 42QOF, and a typical reference leg i nsta 11 ati on.
- f. Reactor coolant density based on auc-tioneering for highest water density obtained from hot leg temperature
(+ 60F) or system pressure (+ 60 psi). Magnitude of uncertainty varies with system pressure and water level, with largest uncertainty occurring when the reactor vessel is full * + 0.34 + 0.7 + 0.64 + 2.3
- g. Sensor and hydraulic isolator bellows displacements due to system pressure changes or reference leg temperature changes will introduce minor errors in the level measurement due to the small volumes and small bellows spring constants. The changes, such as pressure or temperature, tend to cancel, i.e., the bellows associated with each measurement move in the same direction. Maximum expected error due to differences in capillary line volume and local tempera-tures is equivalent to a level change of about 5 inches, multiplied by the density rati a.
- h. Density function generator output mis-match with ASME Steam Table? limited to a maximum of:
/
- i. Electronics system ca 1 i brat ion, over a 11 uncertainty 1 imi tee! to 1 ess than:
- j. Control board indicator resolution; microprocessor digital readout to nearest percent of level span.
+ 1.46 + a.so + 1.0 + 0.5 The statistical combination of (square root of the sum of the squares) of the individual uncertainties described above results in an overall system instrumentation uncertainty of!. 3.9% of the level span. For the narrow range indication of approximately 40 feet, or !. 1.5 feet, at a system pressure of 1200 psia. Examples of the uncertainty at other system pressures are: Uncertainty=!. 3.6% at 400 psia Uncertainty=!. 4.2% at 2000 psi a
I ~
- I
/ Assume a range of sizes for "small break" LOCA's. What are the relative times available for each size break for the operator to initiate action to recover the pl ant from the ace i dent and prevent daw:ge to the _core_'? What is the dividing line between a "small break" and a 0 12.rge break"?
Response
- 7.
Inadequate core coolant {ICC) was defined in WCA?-9754, "Indequate Core Cooling Studies _of Scenario With Feedwater Available Using the NOTRUMP Computer Code", as a high temperature cond1tion in the core such that the operator is required to take action to cool the core before significant damage occurs. During the design basis small loss of coolant accident, the operator is not requ1r:d to take any action to recover the plant other than to verify th~ operable status of the safeguards equipment, trip the reactor cool ant pump {RCPs) when the primary side pressure ****nas decreased to a s~:eifi c point, and initiate cold and hot leg recirculation procedures as required
- In the design basis sma11 LOCA, a period of cladding heat~ may occur prior to automatic core recovery by.the safe;uards equipment.
The heat up period is dependent.upon the break size ~~d ECCS perfor- ~ mance. An ICC condition may arise if there is a failure of the safeguards. equipment beyond the design basis. In that case> acsquate instru-- mentati on exists in the Surry p1 ant to* di a;nose the onset of
- ICC,and to determine the effectiveness of the mitigation actions taken. The instrumentation which may be used to determine the ade*
quacy of core cooling consists of a subcooling meter, Core Exit Thermocouples (T/Cs), and the Reactor Vessel Level-Instrumentation .System {RVLIS). For a LOCA of an equivalent size equal to approximately six inches or less, an ICC condition can only occur if twQ or ~ore failures occur. in the ECCS. As indicated in WCAP-9754, an rec condition can be calculated by hypothesizing the failure of all high head safety
injection (HPSI) for LOCAs of approximately one inch in size. For a 4 *inch equivalent size LOCA one can hypothesize an ICC condition by assuming the failure of all HPSI as well as the failur~ of the passive accumulator system (a truly incredible sequence of events). For LOCAs of sizes of six inches or less, the approach to ICC is unambiguous to the reactor operators. The first indication of a possible ICC situation is the indication that some of the ECCS pumps have failed to start or are* not delivering flow. The second indica-tion of a possible ICC situation is the occurrence of a saturation condition in the primary coolant system as Jndicated on the subcool-ing monitor. Shortly after the second indication, the RVLIS would start to indicate*the presence of steam voids in the vessel. At some point in time the RVLIS will indicate a collapsed liquid level below the top of the core. The core exit thermocouples will begin to indicate* superheated steam conditions. If appropriate the RVLIS and core exit T/C behavior will provide unambiguous indications to operator to follow the ICC.mitigation procedure. WCAP-9754 indicates that the selected core exit T/Cs will read. 12QOOF at* approximately 11000 seconds after the initiation of a 1-inch LOCA with the* loss of all HPSI. The Generic Westinghouse EDP Guideline instruct operator to pursue ICC mitigation procedures when these cond i ti ans are reached. The 4-i nch LOCA wi 11 indicate 1200°F at about. 1350 seconds. By.following the Westinghouse recomnended Emergency Operating Procedures (EOPs), the operators will have earlier indication of a possible ICC situation. Recovery procedures to depressurize the primary below the core pressure safety injection shutoff he~d may be followed. These procedures include correction of the HPSI failure, opening steam dump, or open-ing pressurizer PORVs. The RCPs may be restarted to provide addi-tional steam cooling flow. Large break LOCAs consist of LOCAs in which the fluid behavior is inertially dominated. Small break LOCAs, on the other hand, have
I which are significantly larger than an equivalent 6-inch break, the ECCS has the maximum potential for flow delivery since the primary coolant system is at low pressure. No early manual action is useful in recovering from ICC. Analyses for LOCAs in this-range indicate ambiguous behavior of the core exit T/Cs and RVLIS early in the accident due to dynamic blowdown effects. This behavior is temporary and the core exit T /Cs and the RVLIS will indicate the progress being made by the ECCS in recover-ing thJ'-;*core. When the core exit T/Cs and RVLIS may be temporarily providing ambiguous indications, no manual act1on is needed or use-ful. Later in the accident when manual action may be useful, the core exit T/Cs and RVLIS will provide an unambiguous indication of ICC if it exists *. This unambiguous indication may be present as early as. 30 seconds after the* initiation of the LOCA for a double ended guillotine rupture or a main coolant pipe. The limiting small break size is -normally found to be between j and 4 inches. Westinghouse typically envelopes this situati'on with caiculations
- up to 6 inches.
Breaks betw.een 6 inches and 18 inches *are. typically not limiting. Large breaks become a concern around 18 inches.
. Item 8 Describe how the system response time was estimated. Explain how the response ti~es of the various components (differentitl pressure trans-ducers, connecting lines and isolators) affect the response time.
Response
- 8. The microproce~sor reads all the inputs every five seconds and updates the digital display and analog outputs within four seconds after the inputs are read.* Thus, a worst case time from analog input change to display and analog output change is 9 seconds.
Any analog delays cue to the front-end electronics, sensor electronics, sensor mechanics, impulse lines, hydraulic isolators, etc., have five seconds to settle out. Thus, analog delays only add to the, 9 se!=ond worst case response time if they are 1 anger than 5 seconds. The front end electronics of the microprocessor system has a time constant less than.0.5 seconds, and the total analog delays due to the sensor electronics, mechanics, impulse lines and hydraulic iso-1 ators are les.s than 3 seconds. Therefore, the worst case response time is 9 seconds for the system.
Item 9 T>-iere are indications that the TMI-~ core may be up to 95%,blocked. Estimate the effect*of partial blockage in the core on the differential oressure measurements for a range of values from O to 95% blockage. Resoonse Q. 8lockage in the core will increase the frictional*pressure drop and increase the total differential pressure across the vessel. This . will be reflected as a higher RVLIS indication. The increase -in the RVLIS will be most significant under forced flow cond-itions when the reactor cool ant pumps are operating. In order for blockage to be pres~nt, the core would have to have been uncovered for a prolonged period of time. A low RVLIS indication along with a high core exit thermocouple indication would have been indicated during this time. If the RCP's had been operating throughout the transient, there would have been sufficient cooling to prevent significant core damage. Therefore, for significant blockage tci exist during pump operation, the operator would have restarted the pumps after an ICC condition had existed for a period of time. Based on the history of the transient, the operator \\r<<luld know that the RVLIS' would read higher than expected. Although the RVLIS would read high, it would still fo*llow the* trend in vessel inventory. The operator. would be able to monitor the recovery with the.RVLI$. Under natural* circulation conditions, the impact of core blockage is not expected to be large. Although the RVLIS indication w.ill read slightly higher than normal, the RVLIS will. still trend wi~h the vessel inventory and provide useful information for monftoring the recovery from ICC. ICC will have been indicated at an earlier time; before a significant amount of core blockage has occurred. The operator will know that the RVLIS could read slightly high, based on the history of the transient.
!tern ~-0 Describe the effects of reverse flows within the reactor vessel on the indicated level. Resoonse
- 10. Reverse flows in the vessel will tend to decrease the DP across the
-vessel which would cause the RVLIS to indicate a lower collapsed levei than actually exists. The low indication would not c_ause the operator to take unnecessary actions, since the RVLIS would be used along with the core exit thermocouples to indicate the approach to I CC. It is important to note that large reverse f1 ows are not expected to occur for breaks smaller -than 6" in diameter during the time that the core is uncovered. Large reverse flow rates may occur ear1.v in the bl owdown transient for large diameter breaks but, as is discussed in the response to Item 7, it is not necessary to use the RVLIS as a basis for operator action for breaks in this range
- Item 11 What is the experience, if any, of maintaining 0/p cells at 300% over-range for long periods of time?
Response
- 11. Experience in overranging of. 0/p Instruments has been obtained in previous applications of 0/p capsules similar to those used in RVLIS.
In Dual Range Flow (0/p) Applications the "Low Flow" trans-mitter {and/or gages) are overranged to 300% or greater by normal flow rates yet provide reliable metering when required for* startup. , Als'?, test data exists on the basic transmitter design showing about 0.5% effect on calibration with 24 hours exposure to 3000 psig over-range. All units are similar.ly exposed to this overrange for 5 min-* utes in both directions as a part of factory testing. There have *been instances involving accidental overrange of these instruments {including RVLIS) as the result of. leakage or* operator errors where full line pressure overranges have occurred for up to several weeks with minimal effect on instrument.accuracy.
- Based upon this experience and test* data we expect to prove statis-tically that reliable measurements can be made by the selected over-ranged instrument designs used for RVLIS.
On line calibration capa-bility is provided if needed to support gathering of statistical data
- Five conditions were identified which could cause the DP 1e'le1 system to give ambiquous indications. Discuss the nature of the ambiguities for 1.' accumulator in.iection into a highly voided downcomer, 2. 'when the uoper head behaves like a pressurizer, 3. upper plenum injection, and
- 4. periods of void redistribution.
Resoonse l2. l. When the downcomer is highly voided and the accumlators inject, the cold accumulator water condenses some of the steam in the downcomer which causes a loca 1 depressurization. The local depressurization will lower the pressure at the bottom of the vessel which will lower the.DP across the vessel, causing an apparent decrease in level indication. The lower pressure in the downcomer also causes the mixture in the core to flow to the lower plenum, causing an actual* decrease in level. The period of time when the RVLIS indication is lower thpn tne actual collapsed liquid level will be brief. An exarrple of when this phenomenon may occur is when the reactor coolant pumps are running for a long period of time in a _small break transient. After. the RCS loops have drained and the pumps are circulating mostly steam, the level in the downcomer will be depressed. A 1 arge volume of.steam wi 11 be present in the - downcomer, above the low.mixture level, which allows a large amount of ~ondensation to occur. For most small break transients, the reactor coolant pumps will be tripped early in the transient and the downcomer mixture level win **remain h.igh,
- even in cases where ICC occurs.
When the downcomer level is high the effect of accumulator injection on the RVLIS indication will be minor *
- 2.
When the uoper head begins to drain,*the pressure in the upper head decreases at a slower rate than the oressure in the rest of the qr.s. This is due to the upper head region behaving much li~e the pressurizer. The higher resistance across the upper suoport olate relative to the rest of the RCS prevents the upper head from draining quic~ly. This situation only exists until the mixture level in the upper head falls below the top of the guide tubes. At this time, steam is allowed to flow from the upper plenum to the upper head and the pressure equilibrates. While the upper head is behaving like a pressurizer, the vessel differential pressure is reduced and the RVLIS indicates a lower than actual collapsed liquid level. This phenomenon is discussed in the sunmary report on. the RVLIS* relative to the three inch ~old *leg break. Since.that time, the upper head modeling has been investigated in more detail. It was found that the modeling used at that time assumed a flow resistance that was too high for the guide tub.es. Subsequent analyses have shown that the pressurizer effect has less impact on the vessel dp than was originally shown. There is very
- little impact on the results after the level drains below the top of the guide tubes.
The pressurizer effect is still believed to exist and it becomes more significant as break size increases. The interval* of time when the upper head behaves* like a pressurizer* is brief and the RVLIS will resume trending
- with the vessel level after the top of the guide tubes uncover.
The reduced RVLIS indication w*ill not cause the operator to take an.v.unnecess.ary.action~.eve*n 1f a level *be.low the top of* "the core.is indicated since the core exit thermocouples are used as a corroborative indication of the approach to ICC. Westinghouse Electric Corporation, "Westinghouse Reactor Vessel Level Instrumentation System for Monitoring Inadequate Core r.oo 1 i ng," Oecemb er 1980 *
- 3.
The normal condition for continuous upper olenum inje:tion (UPI) occurs on1y with t.,e ooe!"ation of the low head safety injection oumos, which does not occur until a oressure of under 200 psi is realized. The RVLIS may not accurately trend ~ith vessel level during the initial start of UPI. During this short period of time, the cold water being injected will mix with the steam in the upper plenum causing condensation. c,.This condensation will occur faster than the system response: The system wi11 equilibrate after a short period of time *. Upon equilibrating, the system will continue to accurately trend with the vessel .leve 1. In the range of break sizes where RVLIS is most useful in detecting the approach to ICC, the system pressure will equilibrate at a level above. the pressure where UPI will nonnally occur. -It is important to note that the flow from the low head pumps is sufficient to recover the core and no operator action ba.$.ed on the RVLlS indication will be necessary. For the vast majority of-small breaks, the condition of upper plenum injection does not cause a significant impact.* For th~ remainder, the impact is very small and within tolerable limits.
- 4.
- During the time when the distribution of voids in.the vessel is changing rapidl_y, there can be a large change in the two-phase mixture level with very little change in collapsed mixture level. The use of the RVLIS, in conjunction with the core exit thennocouples,.. is still valid for this situatiof!, however.* *Toe only event that has been identified which could cause a* large void redistribuition is when the reactor coolant pumps are tripped when the* vessel mixture is highly void.ed.
After. the pump perfonnance has degraded enouqh that the flow pressure drop
co~tribution to the vessel differential pressure is small, the chanoe in RVLIS indication will be small when the oumos are tripped. As niscussed in the surranary report, the approach to ICC would be indicated when the wide range indication read 33 percent. If the pumps were tripped at this time, the core would sti 11 be covered. The operator would know that the core may uncover if the pumps were tripped with a wide range indication lower than 33 percent. Prior to pump trip, the core will.remain adequately cooled due to forced circulation-of the mixture. When the pumps trip-the two phase le.vel mayequillibrate at a level below'the top of the core. The narrow range indication wi11 provide an indication of core coolability at this time.
Item 13 No reconmendations are made as to the uncertainties of the pressure or temperature transducers to be used, but the choice appears to be left to the o,mer or AE. What is the upper limit of uncertainties that should be allowed? Describe the effect of these uncertainties on the measure-ment of level. What would be the effect on the level measurement should these uncertainties be exceeded?
Response
13 *. The reactor coolant pressure and temperature signals originate from the existing wide range pressure and hot leg RTD 1s already installed in the plant, and the uncertainties for these instruments are unders to.ad. As indicated in the response to question 6, the pressure uncertainty is_:. 60 psi and the temperature uncertainty is .:. GOF, resulting in a maximum level uncertainty contribution of + 2.3% when the vessel is full. This uncertainty is smaller when the level is at the elevation of the reactor core. This contribution to the total uncertainty would increase roughly in proportion to an increase in the pressure or temperature measurement uncertainty.
I t'=m 1 *1 Only single RTD sensors on ~ach vertical run are indicated to determine the temperatures of the impulse lines. Where are ~hey to be located? What are the expected temperature gradients along each line under normal operating conditions and under a de?ign basis accident? What is the worst case error that could result from only determining th~ temperature at a single point on each line? *
Response
- 14. RTD sensors are installed on every independently run vertical sec-ti on of impulse line, to provide a measurement for density compensa-tion of the reference leg. If the vertical section of impulse line runs through two compartments separated by a solid floor, an RTD sensor is installed in each compartment.
The RTD is installed at the midpoint of each vertical section, based on the assumption that the temperature in the compartment is uniform or that the temperature distribution is linear in the vicinity of .the impulse line. As stated in the response to question 6, an allowance for the.true average impulse line temperature to differ - from the RTD measurement by soF is included in the measurement uncertainty analysis. This allowance permits a significant devia- . tio~.from a linear gradient, e.g., 20% of. the 'impulse line could be up to 250F different from a linear gradient without exceeding the allowance *. During.no.rnial operation, forced circulation from cooling fans is.expected to maintain compartment temperatures reasonably uniform. During the LOCA, turbulence within a compartment due to release of steam....ould also produce a reasonably uniform tempera-ture. Note that the impulse lines subject to .direct jet impingement are protected by met'a"'t* instrument tubing channels
- Item 15 What is the source of the tables or relationships used to calculate density corrections for the level system?
Response
.The.relationships used in the microprocessor based RVLIS system to cal.. culate density corrections are used on the ASME.Steam Tables dated 1967. These relationships are implemented in the system using two fourth order polynomials, end to end, fit to approximate the tables above
- The microprocessor system is stated to display the status of the sensor input. Describe how is this indicated and what this actually means with respect to the status of the sensor itself and the reliability o~ the indication.
Response
The remote gisplay unit* of RVLIS indicates the status of the input
- f, sensors.
If'- any sensors are out of range, regardless of the reason!> a symbol shows the affected level reading on the sullB'llary display page_. The particular sensor that is out of range is identified at the bottom of the summary display page. Due to the redundant sensors and trains it is possible for the operator to disable some of the sensors without ___ affecting the"'system reliability.* The display indicates which level readings are affected. The disabled sensors are also displayed at the bottom of the sullB'llary page. A separate sensor status page can be dis-played showing all sensors which are disabled or out of range and their affected level. readings.
Item 17 Describe the ptovisions for preventing the draining of either the upper head or hot leg impulse lines during an accident *. What would be the resultant errors in the level indications should such draining occur?
Response
- 17. The layout of the impulse lines from the upper head and hot leg are arranged to prevent or minimize the impact of drainage during an accident.
In general, however, the water in the impulse lines will be cooler than the water in the reactor or hot leg, and there will be sufficient subcooling overpressure in the lines so that very little, if any, of the water would*flash to steam during a depres-surization or containment heatup. Heat conduction along the small diameter piping and tubing wotild be insufficient to result in flash-ing in~ significant length of piping. The 6onnecti on to the upper head from a spare contra 1 rod, drive mechanism pert or vessel vent line drops or. slopes down from the highest point of the vesse 1 conne~tion to the s_ensor bellows mounted on the refueling canal wall, so water would be retained in this piping.
- Draining of the vertical section. irrmediately above the reactor vessel has no effect on the level measurement, since this section is included in the operating range of the instrument.
Draining of the horizontal portion of vessel vent piping above the vessel also has no effect oii the measurement since no elevation head is involved. The connection from the hot leg to the sensor bellows is a horizon-tal run of tubing, so draining of this tu~ing has no effect on the measurement since no elevation head is involved. The majority of the impulse line length is in capillary tubing sealed at botry ends with a bellows (sensor bellows at the reactor end, hydraulic isolator at the containment penetration end), so /
water would be retained in this system at all times. The water will be pressurized by reactor pressure, and since the reactor tempera-ture will be higher than containment temperature during an accident, the water in the sealed capillary lines cannot flash.
Item 18 Discuss the effect on the level measurement of the release of dissolved, noncondensible gases in the impulse lines in the event of a depressuri-zation.
Response
- 18. The majority of the impulse lines are sealed capillary tubes vacuum rilled with demineralized, deaerated water. The lines contain no noncondensible gases and are not in a radiation environment.suffi-cient for the disassociation of water.
The short runs of impulse line connected directly to the primary system will behave as described in the response to question 17. -There \\!tOUld be* ro error duet~ gases in the hot leg line since the line is_ horizontal. Since there is no mechanism for concentration of gases at the top of the reactor vessel during normal operation, the connection to the top of the vessel would contain, at most, the normal quantity of dissolved gases in the coolant, and the subcool-* ing pressure during an accident would maintain this quantity of gas in solution
- Item 19 In some tests at Semi-scale, voiding was observed in the core while the upper head was still filled with water. Discuss the possibility of cooling the core-exit thermocouples by water draining down out of the upper head during or after cor~ voiding with a solid upper head.
Response
- 19. One of the indicators of an approach to an Inadequate Core Cooling (ICC) situation is the response of the core exit thermocouples (T/Cs) to the presence of super-heated steam.
The core exit thermo-couples will not provide an indication of the amount of core void-ing. Response of the core exit T/Cs provides a direct indication of the existence of ICC, the effectiveness of ICC recovery actions, and restoration of adequate core cooling. The core is adequately cooled whenever the vessel mixture level is above the top of the core and the core may have a significant void fraction and still be ade-quately coo 1 ed. Realistically, an indication of an ICC condition would not occur until the primary coolant system has drained sufficiently for the ~ reactor vessel mixture level to fall below the top of the core. Westinghouse has performed analyses which indicate that the upper head will drain below the top of the guide tubes before ICC condi-tions exist. The guide tubes are the only flow path from the upper head to the upper plenum. In WCAP-9754, 11 Inadequate Core Cooling Studies of Scenarios With Feedwater Available, Using the NOTRUMP Computer Code", it was found that inadequate core cooling situations woul not result for LOCAs of an equivalent size or equal to approxi-mately 6 inches or less without two or more failures in the ECCS. In both specific scenarios examined in WCAP-9759, a 1-inch and 4-inch small LCX:A, the upper head and upper plenum had completely drained before the onset of an ICC condition
- from the bottan of the support columns (see attached Figure).
In this location, they measure the temperature of the fluid leaving the core region through the flow~passages in the upper core plate. Flow from the upper head must enter the upper plenum via the guide tube* before being able to enter the upper core plate flc,,.; passages. In addition, the LOCA blowdown depressurization behavior must.be* such that there is a flow reversal for the core exit T/Cs to detect the upper.head fluid temperature. The upper head fluid is expected to mix wit~the upper plenum ~luid as it drains fr~>> the upper_head. The potential for core exit T/C cooling from colder-upper head fluid~ while ~he core has an appreciable void fraction is not viewed as a potential problem for the detection of an inadequate core cool-ing situation. Although some Semi-scale,tests* indicated core void-ing while the upper head was liquid solid that does not imply that the.core exit T/Cs would give_ an ambigious indication of.ICC. Calculations for a Westinghouse *pwR and consideration of the core exit T/C design would not result in ambigious ICC indications. / 1
. i. f
- .1 2 S T 1 :l G Hu lJ S ~ E L EC T ~ I C CO ~ ? 0 ~.~-;- l C H
- UPPER 1-f EA D U'FF!R*. *" *
. I j SttPPl>flT F1xrs" '. ' ::s "' ~
- . -'~.* $. ti?PoRa*
C.a1..\\AMJI.. UPPE.R.. *- PLE.NLlM.* Ft.at,.l° FRo1"', *~ F1..otJ FRo:..\\ _
- UPPE. R H EA ti
~ // /
- C.oRE To -~--
U ?PE.R P&9lu.hh---.** - r, *1** : _ ~ I *JY. :. *? : ~. I./'~-~~/*.. i .,,/--u* I.. F",;o..ir-' "'. j ~.. r~- = J.* --... Upp~. CoRE Ex1T 1 ~-- -* *.,. .. HaA:o To ~ _/ ~ -~t'.*-~~ FLOW ~QM (C>~~ ~r.J.(<<£6 _ 'Z/?e7/SJ
Item 20 Describe the behavior cf t~e leve1 measurement syste~ when the upper head is full, but the lower vessel is not. Resoonse
- 20. During the course of a LOCA transient, th~ upper plenum will experience voiding before the. upper head.
The voids in the upper plenum will be indicated by a lower RVLIS reading. The RVLIS will not indicate where the voiding is occurring, but at this point in the transient, it is not necessary to know where the region of voiding is. In the early part of the transient when the mixture level is above the top of the guide tube in the upper head, it is sufficient for the operator to know*that the vessel inventory is decreasing,. irrespective of the region where voiding is occurring. As discussed in.the response to Item 21, the fluid in the upper head .does not affect the RVLIS indication after the upper head has drained to below the top.of the guide tubes. As discussed in the* response to *Item 19, the uipper head will drain befor.e the onset of ICC and there will not be an ambiguous indication during the period of time when RVLIS will-be used.
Item 21 One discussion of the mi croprocesor system states that water in the
- upper head is not reflected in the plot. Does this mean that there is no water in the upper head or that the system is indifferent to water in the upper head under these conditions?
. Response
- 21. The discussion in the system description is contained in* the section describing the analysis of the system performance. The :statement in question is referring to the WFLASH code calculation of mixture level, rather than how the RVLIS.will respond to water in the.upper
- head. The computer code includes calculation of water mass and pressure in the upper head, but this water mass is not included in the ca lcu 1 at ion of mixture level; hence, the mixture l eve 1 is ind i -
cated only below the elevation of the upper support plate. The RVLIS measurement from top to bottom of the vessel will measure the level-in the following regions: top of vessel to top of guide* tube; inside guide tube from top to upper support plate; upper plenum; reactor core; lower plenum. During a LOCA, the RVLIS* will measure the water level in the upper head only un.til the level drops to the top of the guide tubes; RVLIS would then measure level reduc-tion in the guide tubes and upper plenum. The water remaining in the upper head below the.top of the guide tubes would not be mea-sured by RVLIS. This water would eventually drain through small holes into the guide tubes and downcomer, and this draining would be accomplished within a few minutes, depending on the accident. In any case, the water temporarily retained in the upper head wou 1 d have no effect on the RVLIS indication.
Item 22 Describe the details of the pump flow/Op calculation. Discuss the pos-sible errors.
Response
- 22. Calculations are performed to obtain an estimate of the differential pressure that the wide range instrument will measure with a 11 pumps operating, from ambient temperature to operating temperature.
The calculations employ the same methods* u*sed to estimate reactor cool-ant flow for plant design and* safety analysis. *These calculations are used.primarily to define the instrument span and to provide an estimate for the function that compensates the differential pressure signal over the full temperature range, i.e., that results in the wide range display indicating.100% over the full temperature range with all-pumps operating, pumping subcooled coolant. During the initial p1a!'1t startup following installation of the instrumentation, wide range differential pressure data would be obtained and used to. confirm or revise the compensation function so that a 100% output is obtained at all temperatures. **Since the *calculated.compensation function is verified by plant operating data, any uncertainties in the fl ow and d iff erenti al pressure ~st.imates are eliminated. /
Item 23 Have tests been run with voids in the vessel? Describe the results of these tests.
Response
- 23. At present a Westinghouse RVLIS is installed at the Semis*cale Test Facility in Idaho. Small break loss-of-coolant experiments are being conducted at this facility by EG&G for the NRC.
The results of these tests are used to compare the RVLIS measurements with Semi-sea le differential pressure measurements, gamma densi tonieter data and core c.ladding surface thermocouple indications. To date, after correcting for differences between PWR reactor vessel interna 1 s and Semiscale modeling, good *correlation between Semiscale level indica-tions and RVLIS measurements has been observed. In cooperation with the NRC, EG&G and ORNL, Westinghouse is preparing a report summariz-ing the RVLIS performance during selected Semiscale tests.
Item 24 Estimate the expected accuracy of the system after an I CC event.
Response
- 24. The accuracy of the system as described in the response to question 6 would be the same for any LOCA-type incident, including an ICC event, causing a temperature increase within the reactor contain-ment.
Uncertainties due to reference leg temperature measurements and sensor and hydraulic isolator displacements are included in the accuracy analysis
- Item 25 Describe how the conversion of RTD resistance to temperature made in the analog level system.
Response
The RTD is connected such that an analog voltage which is proportional to RTD temperature, is input to the microprocessor system. This analog voltage is converted to temperature by using a curve stored in memory which relates voltage to RTD temperature *}}