/03L-0:on 810119,improperly Sealed Fire Barrier Penetration Discovered.Caused by Improper Matl Being Packed Into Penetration.Penetration Properly Sealed
ML18139B069
Person / Time
Site: Surry 
Issue date: 02/13/1981
From: Joshua Wilson
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML18139B067 List:
References
LER-81-013-03L, LER-81-13-3L, NUDOCS 8102190597
Download: ML18139B069 (2)


LER-1981-013, /03L-0:on 810119,improperly Sealed Fire Barrier Penetration Discovered.Caused by Improper Matl Being Packed Into Penetration.Penetration Properly Sealed
Event date:
Report date:
2811981013R03 - NRC Website

text

      • -----**-----------***-*------.. -

NRC FORM 366 [7-77)

LicENSEE. EVENT REPORT CONTROL BLOCK: 1 1

  • 1 1 0

. (Pt.EASE PRINT OR TYPE ALL REQUIRED INF.ORMATIONI 1

6 Cili:J Iv I A I s I PI s I 2 !G)I o I o I -I o I oj oJ o! oj -I o! o IG)l 4 11 J 1 1111101 I I© S

9 LICENSES CODE 14 15 LICENSE NUMBER 25 26 LICENSE TYPE JO 57 CAT 58 CON.,.

[ffiJ 8

@TI]

IIIIJ

((]IJ cmJ

(())]

[§JI]

[))]J

~~~~~~ W© I o I s Jo Io Io 12 ) 8 I 1 101 o 11 11 I 9 I 8 l 1 I© I o I 2 I 1 I 3 I B I 1 10 60 61 DOCKET NUMBER 6S 69 EVENT CATE 74 75 REPORT DATE

. 80 EVENT DESCRIPTION ANO PROBABLE CONSEQUENCES (,o)

I With Unit Two operating steady-stat? at.100% power, an improperly sealed fire barrier penetration was discoyered during a Q.C. department walkdown of the plant.


~;~ ~

This is contrary to T.S. 3~2i: *G.l and is reportable as per T.S. 6.6.2.b. (3).

All other fire protection systems remained. operable, therefore the health and safety of the public were not affected.

7 B 9 ITIIl a

SY~M

CAUSE

CAUSE COMP.

C.;DE CODE SUBCOOE COMPONENT CODE SUBCOOE U.L!.I@ l!.l L!J@ I z I* 1.1 zj z1 zf z1@ ~@)

9 10 11 12 13 18

-.1s SEQUENTIAL OCCURRENCE.

  • .:1'1EPORT VALVE SUBCODE

~@

20 r.:;,..

LER/!'10 LVENT VEAR REPORT NO.

CODE TYPE

\\!:.I REPORT I 8 11 I I I lo I 11 3 I l.,.....,

10 I 3 j W

1-1 NUMBEl'I 21 22 23 24

,26 27 28 29

  • 30 31

~ REVISION NO.

lE_J 32 COMPONENT BO ACTION FUTURE EFFECT SHUTDOWN

(.;:;\\

ATTACHMENT NPR°"'

"PRIME COMP.

TAKEN ACTION ON PL;ANT METHOD HOURS ~ SUBMITTED FORM i;ua.

SUPPLIER W@UU@) W@ 1.1J 1°1:01°1°1 L!J@). 1.!J ~@

MANUFACTURER

. 33 34 35 36 37 40 41 42 43 CAUSE DESCRIPTION ANO CORRECTIVE ACTIONS @

I z -I 9 I 9 I 9 I 44 47 [II§] J The fire barrier penetration had been packed with improper material.

A fire watch OJI] I was established until the penetration could be properly sealed.

OJ))

IDil 1

C!El a g FACILITY STATUS

"'POWER iIEJ L!.1 111 o I O 1@)1 7

B AbivlTY cti~TENT 12 11 RELEASED OF RELEASE AMOUNT.OF ACTIVITY@

r::m uJ@ W@)I N/A 7

a 9

10 11 PERSONNEL EXPOSURES Q

OTHER STATUS @*,.

N/A I

44 METMODOF

~

DISCOVERY

  • DISCOVERY DESCRIPTION ~

~(§).... !'_QC __

o_b_s_erv_a_t_*i_o_n __

45 46 80 I

44 U/A

_LOCATION OF REI.EASE BO BO NUMBER

(.;:;\\ TYPE DESCRIPTION ~

ETIJ l O I O I O 1'8~-~-----N

__ / A--------------------~.-..1 a s 11 12 1:i PERSONNEL INJURIES t,;":;'\\

NUMBER OESCRIPTION6 BO ITEl lo I al al@)

N/A a e 11

~,2:---------..,..;..~;._----.,........,.,.,..... ___.,...._.,.....,.,.,...,............... __________ s~o LOSS OF OR DAMAGE TO FACILITY '43' TYPE

DESCRIPTION

~

ITTIJ ~@

, B 9 ~10:-----------------------------------------s~o PUBLICITY t:::'i 1SSUED.c=\\DESCRIPTION~

NRC USE ONLY 0

[II§] L!Jei...... _________

N_IA ____________

--J I ! I ! I,. I I I l I I I!

7 8

9 10 68 69 80 ;

N/A (804) 357-3184

~-

    • ------~--------*

f. \\:

e SURRY POWER STATION, UNIT 2 DOCKET NO:

50-281 REPORT NO:

81-013/03L-0 EVENT DATE:

01-19-81 TITLE of EVENT:

FIRE BARRIER PENETRATION IMPROPERLY SEALED

1.

DESCRIPTION of EVENT

With Unit Two operating steady state at 100% power, an improperly sealed fire barrier penetration without a fire watch, was discovered during a normal QC tour of the facilitieso This is contrary to T.S

3. 21. G.1 and is reportable a.s per T. S. 6. 6. 2. b. (3).
2.

PROBABLE CONSEQUENCES and STATUS of REDUNDANT SYSTEMS:

All other fire protection systems remained operable, therefore the health and safety of the public were not affected.

3.

CAUSE

The fire barrier penetration had been packed -with improper material (rags).

The fire proof material had been removed when a :*temporary feeder to a Motor Control Center had beenremoved~from the penetration by construction personnel.

4.

Il1MEDIATE CORRECTIVE ACTION:

A fire watch was posted, the fire marshal! notified, and corrective action initiated to properly seal the penetration.

5.

SUBSEQUENT CORRECTIVE ACTION:

A temporary seal was installed as per EMP-C-FP-.Sl so,.as to remove c'

the requirement for a fire watch.

A permanent seal was installed the following,'id2Jy.

6.

ACTION TAKEN TO PREVENT RECURRENCE:

Re-instruct personnel as to importance of following procedures.

7.

GENERIC IMPLICATIONS:

None.