ML18139A717
| ML18139A717 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 07/03/1980 |
| From: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Ferguson J VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| Shared Package | |
| ML18139A716 | List: |
| References | |
| NUDOCS 8009050431 | |
| Download: ML18139A717 (2) | |
See also: IR 05000280/1980010
Text
In Reply Refer To:
RII:GAB
50-280/80-10
50-281/80-11
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTA ST., N.W., SUITE 3100
ATLANTA, GEORGIA 30303
JUL O 3 1980
Virginia Electric and Power Company
ATTN: J. H. Ferguson
Executive Vice President-Power
P. 0. Box 26666
Richmond, VA 23261
Gentlemen:
This refers to the inspection conducted by G. A. Belisle of this office on May 5
through 9, May 12-16, and May 20-23, 1980 of activities authorized by NRC Opera-
ting License Nos. DPR-32 and DPR-37 for. the Surry facility, and to the discussion
of our* findings held with J. L. Wilson at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspectors .
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items. The status of these items is discussed
in the enclosed report.
Two new unresolved items resulted from this inspection and are discussed in the
enclosed report. These items will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. These items and references
to pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
In addition to the need for corrective action regarding these specific items of
noncompliance, we are concerned about the implementation of your quality assurance
program that permitted their occurrence.
Consequently, in your reply, you
should describe in particular those actions taken or planned to improve the
effectiveness of your quality assurance program .
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
soo90 soL/31
. Virginia Electric and Power Company
-2-
JUL O 3 1980
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must
include a full statement of the reasons on the basis of which it is claimed that
- the information is proprietary, and should be prepared so that proprietary infor-
mation identified in the application is contained in a separate part of the
document. If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Enclosures:
Sincerely,
~~
James P. O'Reill1.::)
Director
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-280/80-10
and 50-281/80-11
cc w/encl:
J. L. Wilson, Manager