Advises That Turbine Insp Originally Scheduled for May,Is Now Underway Due to Vibrations Experienced Prior to Shutdown.Completion Expected by 800310.Requests That Preparation of EIS Not Interfere W/Generator Replacement
ML18139A172
Person / Time
Site: Surry Dominion icon.png
Issue date: 02/26/1980
From: Ferguson J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Ahearne J
NRC COMMISSION (OCM)
Shared Package
ML18139A171 List:
References
150, NUDOCS 8004250041
Download: ML18139A172 (3)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIROINIA 23261 February 26, 1980 Honorable John F. Ahearne, Chairman U. Se Nuclear Regulatory Commission Washington, D.CQ 20555

Dear Dr. Ahearne:

Serial No. 150 LQA/EAB: rab Docket No. 50-280 License No. DPR-32 On February 19, 1980, Surry Unit 1 was removed from service in order to perform modifications on supports of two piping systems within the containmente Since some vibration had been experienced on the turbine just prior to the shutdown, it was decided to advance the turbine inspection that was originally scheduled for May of this yeare That inspection is now underway, and we anticipate completing it by March 10.

Should the results require extended outage for turbine repair, we may wish to begin the steam generator replacement program at that time, rather than in May as originally plannedo Amendment No. 47, dated January 19, 1978, to the Surry Unit 1 license authorizes us to perform the replacement in accordance with the program descriptions previously submitted.

It is our understanding that the Commission is considering ordering the Staff to prepare an Environment Impact Statement on ihe Surry 1 replacement program.

We believe that such an effort is un-necessary, particularly in 1 ight of the recent successful completion of the replacement of the steam generators at Surry Unit 2;. however, should the Commission order the preparation of a statement, we respectfully request that the preparation be carried out in a way that will not inter-fere with the initiation and timely completion of the Surry Unit 1 steam generator replacement.

We will advise your staff on the results of our turbine inspections and our plans for the steam generator replacement as soon as they are completede Yours very truly,

~~

J. H., Ferguson Executive Vice President-Power cc:

Secretary, Ue Se Nuclear Regulatory Commission Washington, D~C.

20555 Attn:

Chief, Docketing and Service Section

BY HAND Honorable John F. Ahearne, Chai,nnan Ue S. Nuclear :Regulatory Comnission Washington, n. c.

20555

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIRGl:N.IA. 23261

~..