Forwards IE Insp Repts 50-280/79-50 & 50-281/79-70 on 790827-29 & Notice of Violation
ML18136A217
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/27/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Proffitt W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18136A215 List:
References
NUDOCS 7911260175
Download: ML18136A217 (2)


See also: IR 05000280/1979050

Text

. ,,,

.t

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

Virginia Electric and Power Company

Attn: W. L. Proffitt

Senior Vice President, Power

Post Office Box 26666

Richmond, Virginia 23261

Gentlemen:

SEP 2 71919

This refers to the inspection conducted by B. R. Crowley of this office on

August 27-29, 1979 of activities authorized by NRC License Nos .. DPR-32 and

DPR-37 for the Surry Nuclear Plant facility, and to the discussion of o~r findings

held with W. L. Stewart at the conclusion of the inspection.*

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2. 201 of the NRC' s "Rules of Practice", Part 2, Title 10, Code of Federal Regula-

tions.

Section 2.201 requires you to submit to this office, within 20 days of

yo,ur receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you, and the results achieved; (2)

corrective steps which will be taken to avoid further noncomplia~ce; and (3) the

date when full compliance will.be achieved.

In accordance with Section 2. 790 of the NRC' s "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed. in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure)

Any such

  • application must include a full statement of the reasons on the basis of which

.......

7911260 175'

. ,,.

.....

Virginia Electric and Power Company

-2-

- SEP c, 71979

it is claimed that the information identified in the application is contained in a

separate of the document. If we do not hear from you in this respect within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

,t.

Murphy,

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-280/79-50

and 50-281/79-70

cc w/enclosures:

W. L. Stewart, Manager

Post Office Box 315

Surry, Virginia 23883

.. _ ....