|
---|
Category:Inspection Report
MONTHYEARIR 05000424/20240032024-10-30030 October 2024 – Integrated Inspection Report 05000424/2024003 and 05000425/2024003 IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 IR 05000424/20240012024-04-23023 April 2024 –Integrated Inspection Report 05000424/2024001 and 05000425/2024001 IR 05000424/20230062024-02-28028 February 2024 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 - NRC Inspection Report 05000424-2023006 and 05000425-2023006 IR 05000424/20240102024-02-14014 February 2024 – Fire Protection Team Inspection Report 0500424/2024010 and 05000425/2024010 IR 05000202/20300042024-02-13013 February 2024 Integrated Inspection Report 052000250/2023004 and 05200026/2023004 IR 05000424/20230042024-02-0505 February 2024 Integrated Inspection Report 05000424-2023004 and 05000425-2023004 ML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 ML23312A3502023-11-14014 November 2023 – Integrated Inspection Report 05200026/2023003 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 IR 05000424/20234022023-11-0606 November 2023 – Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23254A2032023-09-13013 September 2023 – Initial Test Program and Operational Programs Inspection Report 05200025/2023013 IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 ML23223A0022023-08-14014 August 2023 Integrated Inspection Report 05200025/2023002 IR 05000424/20230112023-08-11011 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000424/2023011 and 05000425/2023011 ML23215A0822023-08-0404 August 2023 (Vego), Unit 3 – Initial Test Program and Operational Programs Integrated 05200025/2023011 Inspection Report ML23212B0612023-07-31031 July 2023 Security Baseline Inspection Report 05200025/2023401 IR 05000424/20234012023-07-31031 July 2023 Security Baseline Inspection Report 05000424/2023401 and 05000425/2023401 (Cover Letter) ML23216A0962023-07-26026 July 2023 Document Request for Vogtle 1 & 2 RP Inspection, Report No. 05000424/2023003 and 05000425/2023003 IR 05000424/20230022023-07-24024 July 2023 Integrated Inspection Report 05000424/2023002 and 05000425/2023002 ML23198A3802023-07-19019 July 2023 NRC Integrated Inspection Report 05200026/2023002 ML23199A0892023-07-18018 July 2023 Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2023007 IR 05000424/20233012023-06-30030 June 2023 – NRC Operator License Examination Report 05000424/2023301 and 05000425/2023301 ML23128A2932023-05-11011 May 2023 NRC Integrated Inspection Report 05200026/2023001 ML23129A0222023-05-10010 May 2023 Integrated Report 05200025/2023001 ML23128A3492023-05-0909 May 2023 – Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2023006 ML23121A3202023-05-0404 May 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2023010 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 IR 05000424/20230012023-04-26026 April 2023 Integrated Inspection Report 05000424/2023001 and 05000425/2023001 IR 05000424/20230902023-03-30030 March 2023 NRC Inspection Report 05000424/2023090 and 05000425/2023090, and Investigation Report 2-2022-006; and Apparent Violation ML23083B3702023-03-24024 March 2023 Security Baseline Inspection Report 05200026/2023401 IR 05000424/20220062023-03-0101 March 2023 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2, NRC Inspection Reports 05000424/2022006 and 05000425/2022006 ML23044A3902023-02-14014 February 2023 Integrated Inspection Report05200025 2022007 ML23040A0422023-02-0909 February 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2022008 ML23040A3612023-02-0909 February 2023 – NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2022008 ML23033A3972023-02-0707 February 2023 NRC Integrated Inspection Report 05200026/2022007 IR 05000424/20220042023-01-23023 January 2023 Integrated Inspection Report 05000424/2022004 and 05000425/2022004 2024-08-26
[Table view] Category:Letter
MONTHYEARNL-24-0385, Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator2024-10-31031 October 2024 Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator IR 05000424/20240032024-10-30030 October 2024 – Integrated Inspection Report 05000424/2024003 and 05000425/2024003 NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0386, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information2024-10-28028 October 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information NL-24-0366, Core Operating Limits Report, Cycle 26, Version 12024-10-25025 October 2024 Core Operating Limits Report, Cycle 26, Version 1 ML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML24269A2502024-09-26026 September 2024 Acknowledgement of the Withdrawal of the Requested Exemption and License Amendment Request to Remove Tier 1 and Tier 2* Requirements NL-24-0369, Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements2024-09-25025 September 2024 Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements NL-24-0350, Core Operating Limits Report, Cycle 24, Version 22024-09-25025 September 2024 Core Operating Limits Report, Cycle 24, Version 2 ML24243A0072024-09-10010 September 2024 – Correction of Amendment Nos. 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A2942024-09-0606 September 2024 Correction of Amendment Nos. 218 and 201 Regarding Revision to Technical Specifications to Use Online Monitoring Methodology 05200025/LER-2024-002, Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve2024-09-0505 September 2024 Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information 05000425/LER-2024-001, Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod2024-08-0909 August 2024 Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter 05200026/LER-2024-001, Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal2024-08-0606 August 2024 Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 ML24204A0722024-07-23023 July 2024 Issuance of Amendment No. 225, Regarding LAR to Revise TS 3.7.9 for a one-time Change to Support Nuclear Service Cooling Water Transfer Pump Repairs - Emergency Circumstances NL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24191A4562024-07-19019 July 2024 Request for Relief and Alternative Requirements for Squib (Explosively Actuated) Valves First Test Interval ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0243, Registration of Spent Fuel Cask Use2024-06-18018 June 2024 Registration of Spent Fuel Cask Use ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24155A1772024-06-0505 June 2024 Regulatory Audit in Support of Review of the LAR to Revise Emergency Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, Surveillance Requirements NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24094A1402024-05-16016 May 2024 Staff Response to Request for Revision to NRC Staff Assessment of Updated Seismic Hazard Information and Latest Understanding of Seismic Hazards at the Vogtle Plant Site Following the NRC Process for the Ongoing Assessment of Natural Hazard ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24120A1812024-05-13013 May 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage IR24 Steam Generator Tube Inspection Report – Enclosure 2 ML24101A2112024-05-11011 May 2024 Expedited Issuance of Amendment No. 198 Change to Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) ML24120A2832024-04-30030 April 2024 Project Manager Reassignment 2024-09-09
[Table view] |
See also: IR 05000324/2018301
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
April 26, 2018
William R. Gideon
Site Vice President
Brunswick Steam Electric Plant
8470 River Rd. SE (M/C BNP001)
Southport, NC 28461
SUBJECT: BRUNSWICK STEAM ELECTRIC PLANT - NOTIFICATION OF LICENSED
OPERATOR INITIAL EXAMINATION 05000325/2018 AND 05000324/2018301
Dear Mr. Gideon:
During a telephone conversation on April 12, 2018, between Mr. Bob Bolin, Lead Exam Author,
Mr. Dan Hulgin, Exam Writer, Mr. Ed Rau, Regulatory Exam Supervisor, and Mr. Bruno
Caballero, Senior Operations Engineer, arrangements were made for the administration of
licensing examinations at the Brunswick Steam Electric Plant. The on-site preparatory week is
scheduled for the week of October 22, 2018. The operating test is scheduled to be
administered during the weeks of November 26 and December 3, 2018. The written
examination is scheduled to be administered the week of December 10, 2018.
As agreed during the telephone conversation, your staff will prepare both the operating test and
written examination based on the guidelines in Revision 11 of NUREG-1021, "Operator
Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory
Commission (NRC) regional office will discuss with your staff any changes that might be
necessary before the examinations are administered. Your staff has also agreed to make
copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outline, and the supporting reference materials identified in Attachment 3 to ES-201, by
June 29, 2018. The operating test will be due by August 10, 2018. Mr. Bruno Caballero
provided the written examination outline to your staff in November 2017. The written exam will
be due by September 4, 2018. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal
Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall
approve the outline, examination, and test before they are submitted to the NRC for review and
approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
W. Gideon 2
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the NRC takes
licensing action on all the applications and any adjudicatory actions on any hearing demands
are complete.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator waiver and/or excusal requests (Office of Management and
Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date
(if possible). Contact Mr. Bruno Caballero to determine the method for submission of the waiver
or excusal requests. Preliminary reactor operator and senior reactor operator license
applications (OMB approval number 3150-0090) and medical certifications (OMB approval
number 3150-0024) should be submitted at least 30 days before the first examination date. If
the applications are not received at least 30 days before the examination date, a postponement
may be necessary. Final signed applications certifying that all training has been completed and
requesting any waivers or excusals, as applicable, should be submitted at least 14 days before
the first examination date.
Although the guidelines for receiving waiver or excusal requests call for at least 30 days before
the first examination date (preliminary) and 14 days before the first examination date (final), the
requests should be submitted as early as possible in the process (see the 60-day guideline
above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form
398, Personal Qualifications Statement-Licensee, or as directed by Mr. Bruno Caballero when
contacting him to determine the method for submission). The NRC will document its final
decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398
submitted for the applicant. The NRC will not provide its decision until the final application is
submitted to the agency.
Paperwork Reduction Act Statement
This letter contains information collection requirements that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved
by the Office of Management and Budget, approval number 3150-0018.
The burden to the public for these mandatory information collections is estimated to average
2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination, including the time for reviewing instructions, searching existing
data sources, gathering and maintaining the data needed, and completing and reviewing the
information collections. You may submit comments on any aspect of the information collections,
including suggestions for reducing the burden, to FOIA, Privacy and Information Collections
Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by
electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information
and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,
Washington, DC 20503.
W. Gideon 3
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection
of information, unless the document requesting or requiring the collection displays a currently
valid OMB control number.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding,
of the agencys Rules of Practice, a copy of this letter and its enclosures will be available
electronically for public inspection through the Agencywide Documents Access and
Management System (ADAMS). ADAMS is accessible from the NRC Website at
http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Bob Bolin has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRC's
examination procedures and guidelines, please contact Mr. Bruno Caballero at (404) 997-4608,
(bruno.caballero@nrc.gov), or me at (404) 997-4551, (Internet E-mail: gerald.mccoy@nrc.gov).
Sincerely,
/RA/
Gerald J. McCoy, Chief
Operations Branch 1
Division of Reactor Safety
Docket Nos.: 50-424, 50-425
License Nos.: NPF-68, NPF-81
cc: Distribution via ListServ
_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS II:DRS
SIGNATURE BLC2 GJM1
NAME CABALLERO McCOY
DATE 4/24/2018 4/26/2018
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
April 26, 2018
William R. Gideon
Site Vice President
Brunswick Steam Electric Plant
8470 River Rd. SE (M/C BNP001)
Southport, NC 28461
SUBJECT: BRUNSWICK STEAM ELECTRIC PLANT - NOTIFICATION OF LICENSED
OPERATOR INITIAL EXAMINATION 05000325/2018 AND 05000324/2018301
Dear Mr. Gideon:
During a telephone conversation on April 12, 2018, between Mr. Bob Bolin, Lead Exam Author,
Mr. Dan Hulgin, Exam Writer, Mr. Ed Rau, Regulatory Exam Supervisor, and Mr. Bruno
Caballero, Senior Operations Engineer, arrangements were made for the administration of
licensing examinations at the Brunswick Steam Electric Plant. The on-site preparatory week is
scheduled for the week of October 22, 2018. The operating test is scheduled to be
administered during the weeks of November 26 and December 3, 2018. The written
examination is scheduled to be administered the week of December 10, 2018.
As agreed during the telephone conversation, your staff will prepare both the operating test and
written examination based on the guidelines in Revision 11 of NUREG-1021, "Operator
Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory
Commission (NRC) regional office will discuss with your staff any changes that might be
necessary before the examinations are administered. Your staff has also agreed to make
copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outline, and the supporting reference materials identified in Attachment 3 to ES-201, by
June 29, 2018. The operating test will be due by August 10, 2018. Mr. Bruno Caballero
provided the written examination outline to your staff in November 2017. The written exam will
be due by September 4, 2018. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal
Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall
approve the outline, examination, and test before they are submitted to the NRC for review and
approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
W. Gideon 2
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the NRC takes
licensing action on all the applications and any adjudicatory actions on any hearing demands
are complete.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator waiver and/or excusal requests (Office of Management and
Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date
(if possible). Contact Mr. Bruno Caballero to determine the method for submission of the waiver
or excusal requests. Preliminary reactor operator and senior reactor operator license
applications (OMB approval number 3150-0090) and medical certifications (OMB approval
number 3150-0024) should be submitted at least 30 days before the first examination date. If
the applications are not received at least 30 days before the examination date, a postponement
may be necessary. Final signed applications certifying that all training has been completed and
requesting any waivers or excusals, as applicable, should be submitted at least 14 days before
the first examination date.
Although the guidelines for receiving waiver or excusal requests call for at least 30 days before
the first examination date (preliminary) and 14 days before the first examination date (final), the
requests should be submitted as early as possible in the process (see the 60-day guideline
above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form
398, Personal Qualifications Statement-Licensee, or as directed by Mr. Bruno Caballero when
contacting him to determine the method for submission). The NRC will document its final
decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398
submitted for the applicant. The NRC will not provide its decision until the final application is
submitted to the agency.
Paperwork Reduction Act Statement
This letter contains information collection requirements that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved
by the Office of Management and Budget, approval number 3150-0018.
The burden to the public for these mandatory information collections is estimated to average
2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination, including the time for reviewing instructions, searching existing
data sources, gathering and maintaining the data needed, and completing and reviewing the
information collections. You may submit comments on any aspect of the information collections,
including suggestions for reducing the burden, to FOIA, Privacy and Information Collections
Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by
electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information
and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,
Washington, DC 20503.
W. Gideon 3
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection
of information, unless the document requesting or requiring the collection displays a currently
valid OMB control number.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding,
of the agencys Rules of Practice, a copy of this letter and its enclosures will be available
electronically for public inspection through the Agencywide Documents Access and
Management System (ADAMS). ADAMS is accessible from the NRC Website at
http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Bob Bolin has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRC's
examination procedures and guidelines, please contact Mr. Bruno Caballero at (404) 997-4608,
(bruno.caballero@nrc.gov), or me at (404) 997-4551, (Internet E-mail: gerald.mccoy@nrc.gov).
Sincerely,
/RA/
Gerald J. McCoy, Chief
Operations Branch 1
Division of Reactor Safety
Docket Nos.: 50-424, 50-425
License Nos.: NPF-68, NPF-81
cc: Distribution via ListServ
_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS II:DRS
SIGNATURE BLC2 GJM1
NAME CABALLERO McCOY
DATE 4/24/2018 4/26/2018
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO