1. IAA NO. PAGE OF INTERAGENCY AGREEMENT 31310018S0016 1 2

2. ORDER NO. 3. REQUISITION NO. 4. SOLICITATION NO.

OCHCO-18-0088

5. EFFECTIVE DATE 6. AWARD DATE 7. PERIOD OF PERFORMANCE See Block 26c 04/20/2018 04/20/2018 TO 09/30/2018
8. SERVICING AGENCY 9. DELIVER TO NUCLEAR REGULATORY COMMISSION UNITED STATES NUCLEAR REGULATORY COMMISSION ALC: NUCLEAR REGULATORY COMMISSION DUNS: 040535809 +4: WASHINGTON DC 20555-0001 11555 ROCKVILLE PIKE USA ROCKVILLE MD 20852-2738 POC TELEPHONE NO.
10. REQUESTING AGENCY 11. INVOICE OFFICE HR US NUCLEAR REGULATORY COMMISSION ALC:

ONE WHITE FLINT NORTH DUNS: +4:

US NUCLEAR REGULATORY COMMISSION 11555 ROCKVILLE PIKE ONE WHITE FLINT NORTH MAILSTOP O3-E17A 11555 ROCKVILLE PIKE ROCKVILLE MD 20852-2738 ROCKVILLE MD 20852-2738 POC TELEPHONE NO.

12. ISSUING OFFICE 13. LEGISLATIVE AUTHORITY Economy Act US NRC - HQ ACQUISITION MANAGEMENT DIVISION MAIL STOP TWFN-07B20M WASHINGTON DC 20555-0001 14. PROJECT ID
15. PROJECT TITLE HUMAN CAPITAL OPERATIONS GAP ANALYSIS
16. ACCOUNTING DATA
17. 18. 19. 20. 21. 22.

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT Master IAA: N/A 00001 To obtain a Human Capital Operations Gap Analysis 24,745.00 from DOI/IBC NRC's COR: Romona Bowling,301-287-0699 DOI Client Advocate: Karen Roper, (O)703-964-3581,(Cell) 720-454-6563, karen_roper@ibc.doi.gov Attachment 1: NRC Statement of Work for IAA with DOI/IBC Attachment 2: NRC IAA Terms and Conditions Continued ...

23. PAYMENT PROVISIONS 24. TOTAL AMOUNT

$24,745.00 25a. SIGNATUR 26a. SIGNATURE OF GOVERNMENT REPRESENTATIVE (REQUESTING) 25b. NAME AND TITLE 25c. DATE 26b. CONTRACTING OFFICER 26c. DATE Karen Roper, IBC Client Advocate 4/20/2018 MARK S. LOHRMANN 4/20/2018

IAA NO ORDER NO PAGE OF 31310018S0016 2 2 Attachment 3: DOI IAA # IAA-18-HRD-PRJ-NRC-30 The total amount of award: $24,745.00. The obligation for this award is shown in box 24.

Attachement 1 Version Control Date: September 23, 2016 COVER PAGE ADDENDUM TO:

STATEMENT OF WORK (SOW)

(Interagency Agreements including DOE Laboratory)

NRC Agreement NRC Agreement NRC Task Order NRC Task Order Number Modification Number (If Modification Number Number Applicable) (If Applicable)

Project Title Human Capital Operations Gap Analysis Job Code Number B&R Number Servicing Agency DOI NRC Requisitioning Office Period of Performance OCHCO FY-18 NRC Form 187, Contract Security and Classification Requirements Involves Proprietary Information Applicable Involves Sensitive Unclassified Not Applicable Non Fee-Recoverable Fee-Recoverable (If checked, complete all applicable sections below)

Docket Number (If Fee- Inspection Report Number (If Fee Recoverable/Applicable) Recoverable/Applicable)

Technical Assignment Control Number (If Technical Assignment Control Number Fee-Recoverable/Applicable) Description (If Fee-Recoverable/Applicable)

Page 1 of 10

Version Control Date: September 23, 2016 CONTRACTING OFFICERS REPRESENTATIVE Contracting Officers Representative Name: Ramona Bouling Agency: U.S. Nuclear Regulatory Commission Office: Office of the Chief Human Capital Officer Mail Stop: 3WFN 03A12M Washington, DC 20555-0001 E-Mail: ramona.bouling@nrc.gov Phone: 301-287-0699 Alternate Contracting Officers Representative Name: Kimberly Meyer-Chambers Agency: U.S. Nuclear Regulatory Commission Office: Office of the Chief Human Capital Officer Mail Stop: 3WFN 03A12M Washington, DC 20555-0001 E-Mail: kimberly.meyer-chambers@nrc.gov Phone: 301-287-0739

--- End of Executive Summary ---

Page 2 of 10

Version Control Date: September 23, 2016 STATEMENT OF WORK (SOW)

(Interagency Agreements)

Contents 1.0 Background 2.0 Objective 3.0 Scope of Work/Tasks 4.0 List of Deliverables 5.0 Estimated Labor Categories, Key Personnel and Levels of Effort 5.1 Labor Categories, Requirements and Key Personnel 5.2 Level-of-Effort (in hours) 6.0 Certification and License Requirements 7.0 Meetings and Travel 8.0 Reporting Requirements 8.1 Monthly Letter Status Report (MLSR) 8.2 Final Report 9.0 Required Materials, Facilities, Hardware/Software 10.0 Applicable Publications (Current Editions) 11.0 Data Rights Page 3 of 10

Version Control Date: September 23, 2016 DESCRIPTION/SPECIFICATIONS/WORK STATEMENT (Interagency Agreement)

1.0 BACKGROUND

The Office of the Chief Human Resources (OHR), Human Resources Operations and Policy (HROP), is requesting the conduct of a gap analysis by the Department of the Interior (DOI),

Interior Business Center (IBC), in an effort to determine the cost and feasibility of having the Nuclear Regulatory Commissions (NRCs) human capital operational functions performed by DOI/IBC, a shared service provider.

2.0 OBJECTIVE The objective of this gap analysis is for NRC to have a greater understanding of the scope of work and associated costs of DOI/IBC performing the NRCs human capital operational functions under a shared service arrangement.

3.0 SCOPE OF WORK/TASKS DOI/IBC must provide all resources necessary to accomplish the tasks and deliverables described in this Statement of Work (SOW). DOI/IBC must provide a comprehensive gap analysis that identifies the differences between NRCs current HR operations services and DOI/IBC's HR operations services. DOI/IBC's HR service delivery model provides Federal agencies high quality, cost-effective and streamlined HR services in an all-inclusive model while fully utilizing automated processes and HR systems in the following areas:

Ta le nt Acquis ition P os ition Cla s s ifica tion Employe e Re la tions La bor Re la tions Fe de ra l Be ne fits HR S ys te ms Adminis tra tion The Gap Analysis is typically a 2-day meeting conducted onsite at NRC between the DOI/IBC and NRC stakeholders involved with managing and delivering HR operations services. The purpose of the meeting is:

(for DOI/IBC) to gain an understanding of the NRCs mission and HR needs Page 4 of 10

Version Control Date: September 23, 2016 discuss and document differences between current HR operations services and DOI/IBC's HR operations services discuss roles and responsibilities discuss assumptions and constraints discuss NRCs agency policies ensure NRCs clear understanding of DOI/IBC's HR service delivery model DOI/IBC assumes NRCs HR servicing needs and requirements are based upon current systems and processes, i.e. "as-is" state. The Gap Analysis effort will not involve business process reengineering activities beyond the extent that it is determined DOI/IBC's systems or processes are different than NRCs current systems or processes and the NRC systems or processes would change as a result of migrating HR operations services from current provider to DOI/IBC. Requirements and analysis defined beyond the existing systems and processes are beyond the scope of the proposed work for the analysis.

Depending upon the outcome of the analysis, DOI/IBC or NRC may determine the differences (i.e., systems, rules, regulations, business processes, unique client needs) are too great for the DOI/IBC to address and that a migration is not feasible, regardless of costs. Completion of the Gap Analysis in no way guarantees DOI/IBC can migrate NRC to DOI/IBC's HR servicing support.

4.0 LIST OF DELIVERABLES The deliverables for the Gap Analysis will be:

Acomprehensive Gap Analysis document identifying the following:

  • Differences between current HR operations services and DOI/IBC's HR operations services
  • Business process changes that will be required and/or recommended if a migration was agreed upon
  • Potential challenges if a migration was agreed upon
  • Action items that would result for both NRC and DOI/IBC if a migration was agreed upon
  • Cost estimates for the following:
  • Migrating HR operations services to DOI/IBC
  • Initial year of DOI/IBC HR operations services (depending on date of implementation, this may be a pro-rated cost)
  • One full year of continued DOI/IBC HR operations services Page 5 of 10

Version Control Date: September 23, 2016 Subsequent to the Gap Analysis, DOI/IBC would hold a joint review session with NRC to review the Gap Analysis deliverables. The purpose of the review session will be to discuss and come to a mutual agreement regarding next steps.

Task Deliverable and Acceptance Criteria Deliverable Due Date Number Format 1 IBC & NRC attend Gap Analysis Meeting May 15-16, 2018 Session 2 IBC delivers identified comprehensive See below** NLT 14 business Gap Analysis document to NRC for days after review Gap Analysis session complete 3 IBC & NRC perform joint review session Teleconference NLT 7 business via telephone days after Gap Analysis document delivered to NRC 4 IBC & NRC approve identified Gap Meeting/ NLT 7 business Analysis documents Teleconference/ or days after joint E-mail Gap Analysis Review Session 5 IBC delivers Gap Analysis results to See below** NLT 7 business NRC to include estimated cost for days after approval migration, approved list of process of Gap Analysis changes, estimated schedule for documents implementation and any identified risks to the project

    • Deliverables will be formatted in Microsoft Word, Excel, PDF, or Project.

If a schedule slippage occurs due to the unavailability of NRC resources at agreed upon tasks, milestones, or decision points, the DOI/IBC project manager will document the event and adjust the period of performance in coordination with the NRC project manager.

All tasks will be documented to include a narrative on the process and information gained from discussions with NRC, through analysis and evaluation of current practices, policies and procedures. Conflicting items will be identified for resolution and approaches will be recommended for their resolution, to the extent to which the requirements or items can be Page 6 of 10

Version Control Date: September 23, 2016 resolved. In the cases where no resolution is identified, a recommended work-around may be provided.

NRC will have twenty (20) business days to complete its review of the final Gap Analysis document deliverable. Acceptance of the final deliverable will be determined by either written acceptance (email is satisfactory) from the NRC Project Manager or the expiration of 20 business days from the receipt of the deliverable. In the event of a rejection of any deliverable, DOI/IBC will be notified in writing (email is acceptable), giving the specific reason(s) for rejection. DOI/IBC will have ten (10) business days to correct the rejected deliverable and redeliver to the NRC for review and acceptance. Expected durations are to be considered business days (excludes weekends and Federal holidays).

4.1 NRC Responsibilities NRC is the key stakeholder in this process; accurate information sharing will contribute to a thorough Gap Analysis and assessment of migration risks. NRC will provide the following resources to support the Gap Analysis:

Age ncy S pons or a nd/or P roje ct Ma na ge r S ubje ct m a tte r e xpe rt(s ) in the full range of NRCs HR processes S ubje ct m a tte r e xpe rt(s ) in NRC s ma na ge rs ' a nd s upe rvis ors ' role s a nd responsibilities related to HR processes S ubje ct m a tte r e xpe rt(s ) in NRC s a ge ncy policie s Budge t point of conta ct with e xpe rtis e in NRC s budge t procedures (necessary to explore financial system impacts resulting from change in Servicing Personnel Office)

NRC stakeholders will attend two (2) days of Gap Analysis sessions and potential follow up teleconference discussions, depending upon requirements and gaps discovered during the session.

IBC understands there may be a need to work with contractors acting on behalf of the NRC.

However, being a government entity, the NRC will be the formal decision making body on all decisions.

The roles and responsibilities for NRC and IBC's staff will be clearly stated for each activity involved with the analysis.

NRC will provide notification of any changes in points of contact information or changes in job responsibilities.

Page 7 of 10

Version Control Date: September 23, 2016 5.0 ESTIMATED LABOR CATEGORIES, KEY PERSONNEL AND LEVELS OF EFFORT DOI/IBC shall provide personnel with skill in interpreting and applying appropriate Federal laws, regulations, policies, procedures, and guidelines in the human resources functional areas of recruitment and placement, classification, employee relations, performance management, workforce planning, and employee benefits.

5.1 Labor Categories, Requirements and Key Personnel. Personnel working under this agreement/order shall meet the minimum requirements for experience and education, as follows [Insert the qualifications for all personnel, i.e., years working in nuclear field/industry; at least masters degree engineering discipline; professional certification or license; knowledge of risk assessments, power plant operations and systems, and severe accidents; etc. or by labor category - see example table below.]

Labor Category Position Minimum Requirements Key Personnel*

(yes or no) 5.2 Level-of-Effort (in hours). Estimate the number of hours required for each labor category, including base and option periods. This estimate is advisory only and not to be considered as the sole basis for development of a staffing plan. [Insert labor categories and LOE requirements based on labor categories in IGCE as applicable to this effort]

Indicate the types of positions (e.g., geologist, nuclear engineer, etc.) and levels of expertise (i.e., senior, mid-level, junior, etc.) and corresponding labor hours needed. Identify which labor categories are considered key personnel You may provide suggested labor categories and corresponding LOE estimates for informational purposes, but the DOE Laboratory should retain the ability to propose what it considers to be adequate personnel, personnel mix, and labor to accomplish the requirement.

If the DOE Laboratory has performed the tasks previously, it may be prudent not to provide the CORs estimate in the SOW in order to see the DOE Laboratorys unbiased independent estimate based on its knowledge of the project.

Page 8 of 10

Version Control Date: September 23, 2016 Fiscal Fiscal Fiscal Fiscal Fiscal Total Year Year 20 Year 20 XX Year 20 Year 20 20XX XX XX XX Task Labor Estimated Estimated Estimated Estimated Estimated Category Hours Hours Hours Hours Hours 6.0 CERTIFICATION AND LICENSE REQUIREMENTS N/A 7.0 MEETINGS AND TRAVEL Travel is anticipated for this effort. Travel costs are included and assume all travel is between Denver, Colorado and NRC only.

8.0 REPORTING REQUIREMENTS DOI/IBC is responsible for structuring the deliverables to current agency standards. DOI/IBC must submit deliverables free of spelling and grammatical errors and shall conform to requirements stated in this section.

DOI/IBC shall submit draft and final Gap Analysis documents consistent with Section 4.0 of this document.

9.0 REQUIRED MATERIALS, FACILITIES, HARDWARE/SOFTWARE N/A 10.0 APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

N/A Page 9 of 10

Version Control Date: September 23, 2016 11.0 DATA RIGHTS The NRC shall have unlimited rights to and ownership of all deliverables provided under this agreement/order, including reports, recommendations, briefings, work plans and all other deliverables. All documents and materials, to include the source codes of any software, produced under this agreement/order are the property of the NRC with all rights and privileges of ownership/copyright belonging exclusively to the NRC. These documents and materials may not be used or sold by the servicing agency without prior written authorization from the CO. All materials supplied to the NRC shall be the sole property of the NRC and may not be used for any other purpose. This right does not abrogate any other Government rights.

Page 10 of 10

ATTACHMENT 2 NRC GENERAL TERMS AND CONDITIONS (GT&C) FOR INTERAGENCY AGREEMENTS (IAA)

General Guidance Note: If the Order(s) issued pursuant to the GT&Cs will be fully funded you may delete Clause 5, Limitation of Funds. However, by including it in multiple Order IAAs, NRC has the option to incrementally fund future orders.

1. Technical Direction The NRC Contracting Officers Representative (COR), as named in the NRC SOW, is responsible for ensuring that the services required under this project are delivered in accordance with the terms of the SOW. All technical direction instructions to the Servicing agency must be issued through the COR.

Technical direction includes interpreting technical specifications, providing needed details, and suggesting possible lines of inquiry. Technical direction must not constitute new work or affect overall project cost or period of performance. Technical direction must be confirmed in writing to the servicing agency with a copy provided to the cognizant NRC Contracting Officer (CO).

2. Key Personnel The individual(s) identified as key personnel is (are) considered essential to the successful performance of the work. The servicing agency agrees that these personnel shall not be removed from the project or replaced without complying with the following:

- If one or more of the key personnel, for whatever reason, becomes or is expected to become unavailable for work under this IAA for a continuous period exceeding 30 workdays, or is expected to devote substantially less effort to the work than indicated in the proposal or initially anticipated, the servicing agency shall immediately notify the NRC CO of its intent to make key personnel replacements.

- All requests for approval of substitutions on a project shall be in writing and shall provide detailed explanation of the circumstances necessitating the proposed substitutions. The request shall contain a complete résumé for the proposed substitute and other information requested by the NRC CO to approve or disapprove the proposed substitution. The NRC will evaluate such requests and promptly notify the servicing agency of its approval or disapproval thereof in writing.

- The project may be terminated if the NRC determines that:

o Suitable and timely replacements of key personnel who have been reassigned, terminated, or have otherwise become unavailable for the project are not reasonably forthcoming.

o The resultant reduction of effort or expertise would be so substantial as to impair the successful completion of the work order.

ATTACHMENT 2

3. Billing Requirements Servicing agency shall bill NRC monthly for costs paid in support of NRC projects by the agreement number. The servicing agency shall bill and collect from NRC by an electronic transfer of funds through the U.S. Treasury Intergovernmental Payment and Collection System (IPAC).

The servicing agency voucher shall identify the NRC agreement number, and the NRC and servicing agency budget and reporting (B&R) numbers.

The servicing agency voucher, at a minimum, shall indicate the month that costs were incurred and the dollar amount of these costs. In some instances because of accrual accounting and other adjustments, the amounts may differ slightly from the original accrual amount.

When the Status Report costs differ from the amount billed, servicing agency shall provide an explanation of the difference on the voucher.

The servicing agency voucher shall be sent to support the IPAC funds transfer. The instructions must identify the billable activities as specified by 10 CFR Part 170. The servicing agency voucher and other required documentation shall be submitted to NRC Payments U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mailstop O3-E17A Rockville, MD 20852-2738 Electronic Commercial Vendor and IPAC Payments:

Effective immediately, commercial vendors and Federal entities should use the new electronic mailing addresses shown below:

Invoice and training billing Email address - NRCPayments@NRC.gov IPAC billing Email address - NRCIPAC.Resource@NRC.gov

4. Status Reports The servicing agency shall submit a Status Report in accordance with the SOW and the Status Report Requirements, if attached to the SOW, to the NRC CO and NRC COR with a copy to the Office of Administration/Acquisition Management Division to ContractsPOT.Resource@nrc.gov.
5. Organizational Conflict of Interest By submitting a proposal to the NRC, the servicing agency acknowledges the disclosure requirements of: 1) the NRC Clause, the NRC Conflict of Interest, Management Directive 11.8; and 2) that Section 170A of the Atomic Energy Act of 1954, as amended, requires that NRC be provided with disclosures on potential conflicts when NRC obtains technical, consulting, research and other supporting services. The servicing agency further recognizes that the assignment of NRC work to the servicing agency must satisfy NRCs organizational conflict of interest (OCOI) standards.

ATTACHMENT 2 Therefore, the servicing agency, in its proposal to NRC (which will be incorporated into an interagency agreement between NRC and the servicing agency), is required to make an assertion per #1 or #2 of Part A below. If the servicing agency selects #1, then, it must also fill out the accompanying Part B - whereby the servicing agency must, again, make an assertion by answering each of the five (5) NRC OCOI provisions per the NRC Acquisition Regulation (NRCAR).

PART A:

"In accordance with Office of Personnel Management (OPM) role in, and responsibility for, disclosing its relationships with organizations which conduct business in the same and/or similar technical area as described by the present and/or ongoing NRC project's scope of work, and in accordance with the NRC clause as stated herein, OPM hereby asserts that it has examined its relationships with all such organizations, and has also examined its current and future/planned work, and where appropriate, its past work (generally for the previous five years), for other organizations and OPM states the following:

1) OPM hereby discloses the following relationships _______ [state the name of persons, organizations, and business relationships, etc. **] ________ that may give rise to a potential OCOI. (Servicing agency must answer the questions in Part B below);

Or

2) OPM to the best of its knowledge and belief, asserts that it has no current work, planned work, and where appropriate, past work for the servicing agency and others (to mean -

organizations in the same and/or similar technical area as the present and/or ongoing NRC project scope of work); and OPM hereby asserts that it is not aware of any same/similar technical work that would give rise to any potential OCOI as defined in the Atomic Energy Act of 1954, as amended.

Signed: _________________________________________________________________

PART B:

In accordance with OPM role/responsibility regarding OCOI disclosure, as stated in Part A, above OPM further discloses, to the best of its knowledge and belief, that:

1) OPM and/or any of its organizational affiliates* as defined in Part A above [does/does not]

provide advice and recommendations to the NRC in the same technical area (e.g., fire protection, PRA, seismic, vulnerability analysis, fracture mechanics) where it is also providing consulting assistance to any organization regulated by NRC. If OPM "does" - the OPM hereby discloses such organization(s) in Part A above;

2) OPM and/or any of its organizational affiliates as defined in Part A above [does/does not]

provide advice and recommendations to the NRC on the same or similar matter (e.g., particular licensing amendment, particular EIS, particular high level waste repository site) on which it is also providing assistance to any organization regulated by NRC. If OPM "does" - the OPM hereby discloses such organization(s) in Part A above;

3) OPM and/or any of its organizational affiliates as defined in Part A above [will/will not] be required to evaluate its own products or services, or has been substantially involved in the ATTACHMENT 2 development or marketing of the products or services of another entity. If OPM "does" - the OPM hereby discloses such organization(s) in Part A above;
4) OPM and/or any of its organizational affiliates as defined in Part A above [does/does not]

have a conflicting role, given the award of the present and/or ongoing NRC project, in which its judgment or the judgment of any of its organizations may be biased in relation to its work for NRC. If OPM "does" - the OPM hereby discloses such conflicting role(s) with organization(s) in Part A above;

5) OPM and/or any of its organizational affiliates as defined in Part A above [are/are not]

soliciting or performing concurrent work at an applicant or licensee site, while performing work in the same/similar technical area for NRC at the same site. If OPM "does" - then the OPM hereby discloses such organization(s) in Part A above."

Signed: __________________________________________________________________

  • Organization affiliate - Business concerns which are affiliates (related) to each other when either directly or indirectly, one concern or individual controls or has the power to control another, or when a third party (i.e. parent firm) has the power to control both.
    • The Atomic Energy Act of 1952 uses the term person to mean any entity - e.g., sole proprietorship, partnership, joint venture, corporation; university; limited partnership, subchapter S corporation; limited liability company, etc.
6. Incompatibility Between Regular Duties and Private Interests (a) Employees of the servicing agencys contractor shall not be permitted to make or influence any decision on behalf of the contractor which directly or indirectly affect the interest of the Government, if the employees personal concern in the matter may be incompatible with the interest of the Government. For example: An employee of a contractor will not negotiate, or influence the award of, a subcontract with a company in which the individual has employment relationship or significant financial interest; and an employee of a contractor will not be assigned the preparation of an evaluation for the servicing agency for any technical aspect of the work of another organization with which the individual has an employment relationship, or significant financial interest, or which is a competitor of an organization (other than the contractor who is the individuals regular employer) in which the individual has an employment relationship or significant financial interest.

(b) The contractor shall be responsible for informing employees that they are expected to disclose any incompatibilities between duties performed for the contractor and their private interests and to refer undecided questions to the contractor.

7. Intellectual Property Rights The statutory, regulatory, and procedural intellectual property policies of servicing agency will be applicable to the work falling under this work order

- Provided that information concerning disclosures of inventions identified as having been conceived or first actually reduced to practice under Commission-funded work will be reported to the Commission, and the Commission will be kept advised as to their status.

ATTACHMENT 2

- Except that the Commission reserves the right to control title to inventions as to any rights that vest in the Commission under statute. If servicing agency and servicing agency's contractor, where the contractor has such rights, should determine not to protect these inventions either domestically or abroad, the Commission will have the right to protect these inventions.

- Provided that if the technology covered by an invention disclosure upon which the servicing agency intends to file a patent application on behalf of the U.S. Government is deemed by the Commission to fall within the Commissions mission, that is, when the technology relates to nuclear facilities and materials safety, safeguards, and environmental protection in support of the Commissions licensing and regulatory functions, the Commission may so notify servicing agency and a determination will be made by the parties as to which party will file the patent application or applications.

- Provided that neither party shall grant an exclusive patent license on an agency owned invention without the approval of the other party.

8. Acquired Material, Equipment, or Software (Property)

In accordance with the SOW, the servicing agency proposal must include a description of the property required for project performance that has an estimated acquisition cost of $500 or more. The proposal must also identify the potential development of NRC-funded software during the project. NRC-funded software is software specifically developed for NRC by the servicing agency and is generally the deliverable for the project.

After the NRC reviews the list of property and NRC-funded software included in the servicing agency proposal, any questions regarding the acquisition of property or the development of NRC-funded software will be addressed with the servicing agency during negotiations. After negotiating project terms and conditions, NRC shall issue the IAA for the servicing agencys acceptance authorizing the work and approving acquisition of property or development of NRC-funded software.

The servicing agency shall submit a written request to the NRC CO for approval to develop additional NRC-funded software or purchase additional property with an estimated acquisition cost of $500 or more after work initiation. The NRC CO shall approve or disapprove the acquisition or development of any additional items in writing.

The servicing agency shall report property, including software, with an acquisition cost of $500 or more in the status report in the month the property or software was acquired. The servicing agency shall provide the information required by the Status Report Requirements for each item reported as appropriate, in the status report:

9. Dissemination of Project Information/Publication Requirements (a) Prior to any dissemination, display, publication, presentation, or release of papers, articles, reports, summaries, or abstracts developed under the NRC/servicing agency agreement, the servicing agency shall submit them to the NRC for review and comment. NRC shall have a review and comment period of at least [60] days, after which both an NRC and servicing agency representative at the lowest management level, shall attempt to resolve any differing viewpoints ATTACHMENT 2 or statements which are the subject of NRC objection. If the matter cannot be resolved at that level, the issue shall be brought up to the next management level in both organizations until an agreement can be reached or it reaches the Office Director level. In the event resolution cannot be achieved , the NRC may direct the servicing agency to not publish the work as a NUREG/CR, but publish as a servicing agency report without the NRC office name or Contracting Officers Representative (COR)s name listed on the report, and with a Disclaimer conspicuously noted on the report, article, summary, abstract or related document that the servicing agency intends to release, display, disseminate or publish to other persons, the public or any other entities:

The views expressed in this [paper, journal article, report, summary, or abstract] do not represent those of the U.S. Nuclear Regulatory Commission.

(b) The NRC and servicing agency agree to handle all classified information provided or developed during the course of this project in accordance with all applicable laws and regulations governing the handling of such information. In the event NRC determines during its review and comment period that a draft servicing agency paper, article, report, summary, or abstract contains classified information regarding the work performed for NRC, NRC, in addition to commenting on the subject matter, shall also direct the servicing agency to direct an authorized classification authority to appropriately review, classify and mark the product, pursuant to nationally acceptable standards/guidelines. Under these circumstances, the Laboratory will either publish the work solely as a classified product pursuant to NRC direction, or not publish the work in any format. In cases where classification of the product is in dispute, NRC may consult with servicing agencys Office of Classification; however NRC retains the ultimate authority over the classification of the product.

(c) In addition, travel costs to present papers or reports developed under the NRC/servicing agency agreement may not be authorized if the NRC determines that presentation of the paper does not support the NRC program or project. Such determination will not affect payment of the contract work costs.

(d) The servicing agency contractor, to the extent it is permitted to and asserts copyright therein, grants a royalty-free, nonexclusive, irrevocable worldwide license to the Government to use, reproduce, modify, distribute, prepare derivative works, release, display or disclose the articles, reports, summaries, abstracts, and related documents developed under the Agreement, for any governmental purposes and to have or authorize others to do so.

10. Review and Approval of Reports The servicing agency shall comply with the terms and conditions of the agreement regarding the contents of the draft and final reports, summaries, data and related documents, to include correcting, deleting, editing, revising, modifying, formatting and supplementing and of the information contained therein. Corrective actions shall not be undertaken unless sufficient funding from NRC is available to cover the costs of the corrective actions. Performance under the agreement shall not be deemed accepted or completed until it complies with NRCs directions.

Identification/Marking of Sensitive Unclassified and Safeguards Information. The servicing agency shall comply with the requirements stated MDs 12.7 NRC Safeguards Information Security Program as follows:

ATTACHMENT 2 a) Classification Clause To the extent that the performance of work under this work order involves classified information, the following clause is applicable:

- In the performance of work under this work order, servicing agency shall ensure that a servicing agency authorized classifier shall assign classification levels to all documents, material, and equipment originated or generated by the performing organization in accordance with classification guidance furnished by the Commission. Each subcontract and purchase order issued hereunder involving the generation of classified documents, material, or equipment shall include a provision to the effect that in the performance of such subcontract or purchase order, a servicing agency authorized classifier shall assign classification levels to all such documents, material, and equipment in accordance with classification guidance furnished by the NRC.

- When appropriate, the attached NRC Form 187, Contract Security and/or Classification Requirements," is a part of this work order. It is the responsibility of the NRC office originating the work order to review the classification assigned and to refer any problems to the NRC Division of Security Operations (DSO), NSIR, for resolution.

b) Safeguards Information, Unclassified Controlled Nuclear Information, or Unescorted Access to Protected and Vital Areas of Nuclear Power Plants To the extent that the performance of work under this work order involves Safeguards Information (SGI), the following clause is applicable:

In the performance of the work under this project, servicing agency shall assure that the Servicing agency shall mark and protect all documents, material, and equipment originated, generated, or received by the performing organization in accordance with the provisions of Section 147 of the Atomic Energy Act of 1954, as amended, its implementing regulations (10 CFR 73.21), Protection of Safeguards Information: Performance Requirements.

Further guidance on the protection of Safeguards Information and examples of proper marking of cover; title page, and back cover are contained in NRC Management Directive (MD) 12.7,* "NRC Safeguards Information Security Program and the NRC Guide to Marking Safeguards Information.

To the extent that performance of work under this work order involves unclassified controlled nuclear information (UNCI), the following clause is applicable:

In the performance of the work under this project, servicing agency shall assure that the Servicing agency shall mark and protect all documents, material, and equipment originated, generated, or received by the performing organization in accordance with the provisions of Section 148 of the Atomic Energy Act of 1954, as amended, its implementing servicing agency regulations, and servicing agency orders and guidance.

It is the responsibility of the NRC office originating the work to indicate whether the work will involve SGI or unescorted access to protected and vital areas of nuclear power plants. An NRC Form 187, Contract Security and/or Classification Requirements, shall be completed to indicate such access.

c) Proprietary Information ATTACHMENT 2 In connection with the performance of work under this work order, NRC may furnish for the servicing agency review, evaluation, or other use certain trade secrets or confidential or privileged commercial or financial information determined by the office to be exempt from public inspection or disclosure. A synopsis of such information must be submitted in writing to the servicing agency before reaching agreement with the office on the acceptance and use of the information. Up-to-date guidance on the protection of proprietary information used in reports prepared by the Servicing agency on proper marking of cover, title page, and back cover may be obtained from the NRC COR.

Proprietary or other privileged information may be provided by the office on an individual basis to servicing agency employees working as NRC consultants with the understanding that it shall be protected from disclosure and shall be returned to the office upon completion of the work.

Any such claimed proprietary data will be appropriately identified and marked as such. The use of proprietary information in reports prepared by consultants requires protection. Further information may be obtained from the NRC COR.

d) Other Sensitive Unclassified Non-Safeguards Information (SUNSI)

Information other than safeguards, unclassified controlled nuclear, proprietary information, and pre-decisional information may at times be determined to be sensitive. The use of such information in reports requires the specific NRC designation and protection as prescribed by the NRC SUNSI policy. Further information may be obtained from the NRC COR.

11. Sensitive Information Work Efforts To the extent that the performance under this work order involves classified information, the following clauses are applicable:

- Responsibilities. The servicing agency and the servicing agency contractor, if any, shall be responsible for safeguarding Restricted Data, Formerly Restricted Data, and other National Security Information and for protecting it against sabotage, espionage, loss, and theft in accordance with applicable NRC and servicing agency security regulations and requirements.

- Transmission of Classified Matter. Except as otherwise expressly provided, servicing agency or the servicing agency contractor shall, upon completion or termination of the work order, transmit to the NRC program office all classified matter in its possession or in the possession of any person under its control in connection with performance of this work order. If retention of any classified matter is required by servicing agency or the servicing agency contractor, servicing agency must obtain the approval of the NRC program office and complete a certificate of possession specifying the classified matter to be retained.

- Regulations. The servicing agency and the servicing agency contractors shall be responsible for compliance with all applicable NRC and servicing agency security regulations and requirements.

- Definition of Restricted Data. The term Restricted Data, as used in this clause, means all data concerning (1) the design, manufacture, or utilization of atomic weapons; (2) the production of special nuclear material; or (3) the use of special nuclear material in the ATTACHMENT 2 production of energy, but does not include data declassified or removed from the Restricted Data category pursuant to Section 142 of the Atomic Energy Act of 1954, as amended.

- Definition of Formerly Restricted Data. The term Formerly Restricted Data, as used in this clause, means classified information related primarily to the military utilization of atomic weapons that can be adequately safeguarded as National Security Information, subject to the restrictions on transmission to other countries and regional defense organizations that apply to Restricted Data.

- Definition of National Security Information. National Security Information is information that has been determined pursuant to Executive Order 13526 or any predecessor order to require protection against unauthorized disclosure and is so designated.

- Security Clearance of Personnel. servicing agency and servicing agency laboratories shall not permit any individual to have access to Restricted Data, Formerly Restricted Data, or National Security Information, except in accordance with the Atomic Energy Act of 1954, as amended, Executive Orders 12968 and 10865, and servicing agency regulations or requirements applicable to the particular type or category of classified information to which access is required.

- Safeguards Information Access. The servicing agency and servicing agency laboratories shall not permit any individual to have access to Safeguards Information, except in accordance with 10 Code of Federal Regulations Part 73.22 and NRC Management Directive 12.7.

- Liability. It is understood that the unauthorized disclosure or the failure to properly safeguard Restricted Data, Formerly Restricted Data, or National Security Information that may come to the servicing agency or to any person under an NRC/servicing agency order in connection with work under the order may subject the performing organization, and its agents, employees, or subcontractors, to administrative sanctions and criminal liability under the laws of the United States. (See the Atomic Energy Act of 1954, as amended [42 U.S.C.

2011et seq.], 18 U.S.C. 793 and 794; and Executive Orders 13526 and 12968.)

- Subcontracts and Purchase Orders. Except as otherwise authorized in writing by the Commission, servicing agency shall insert provisions similar to the foregoing in all subcontracts and purchase orders under this work order.

12. Software Development Systems development efforts shall comply with applicable Government-wide Federal Information Processing Standards developed by the National Institute of Standards and Technology, applicable public laws, Office of Management and Budget circulars, and NRC policies and procedures. Particular attention is necessary to incorporate security features in the design of systems that process sensitive data. The format of software deliverables is specified in NRC Bulletin 0904-4. If any deliverable is provided on diskette, the diskette shall be scanned for viruses by the contractor and verified to be free of viruses before delivery to NRC. All software development, modification, or maintenance tasks shall follow general guidance provided in NUREG/BR-0167, Software Quality Assurance Program and Guidelines. NRC shall advise the servicing agency Patent Counsel with respect to any rights in the software that NRC desires under any particular project, which rights include NRC imposing restrictions on use, and distribution of the software by servicing agency.

ATTACHMENT 2

13. Copyright in Computer Software and Codes In the event that the servicing agency desires to assert a copyright of any computer software or computer code funded in whole or in part by NRC, the servicing agency shall request, in writing, the written approval of the cognizant NRC CO before advising servicing agency's patent counsel of its desire to seek the copyright.

If NRC determines that public health and safety or other programmatic considerations dictate that the Servicing agency contractor should not be given permission to copyright the computer software or code, the NRC CO, after consultation with the NRC program office division director or designee and the NRC Office of the General Counsel (OGC) shall so advise the servicing agency in writing.

Alternatively, if permission to copyright computer software or a computer code is granted, the cognizant NRC CO, after consultation with NRC program office division director or designee and OGC, shall provide the servicing agency with written notice of that decision. In those cases in which the NRC CO determines that the rights retained by the Government pursuant to the copyright provisions of the servicing agencys contract should be modified to protect NRC's interests, NRC will advise servicing agency's patent counsel of NRC's desire to modify servicing agency's standard policy with respect to permission for a contractor to assert copyright in that code. The servicing agency and NRC will then jointly determine the appropriate provisions for the code. The servicing agency patent counsel shall provide the Laboratory with written notice, with a copy to the NRC CO, of that joint determination. The Laboratory may then proceed to assert copyright.

In no case shall the servicing agency take action relating to assertion of copyright until the NRC CO provides written approval of the request to assert copyright. Further, the servicing agency shall not permit a contractor to assert copyright of NRC-funded computer code or computer software without the written approval of the NRC CO. Where NRC has not granted permission to copyright, NRC recognizes that once the servicing agency has delivered to NRC a developed version of a particular code, the servicing agency may exercise the existing right the servicing agency and other parties have to further develop, without NRC funds, software codes that are in the public domain and to copyright the new, non-NRC-funded versions of these codes without NRC approval.

14. Appropriate Use of Government Furnished Information Technology (IT) Equipment and/or its Services/Access When the NRC work at a servicing agency site requires electronic processing of information, servicing agency will follow NIST Special Publication (SP) 800-37 Rev. 1 or later, and SP 800-53 Rev. 3 or later (which are based on FIPS-199 and FIPS-200). For those specific projects with electronic processing of Safeguards Information (SGI), Restricted Data (RD) and/or Unclassified Nuclear Information (UCNI), the NRC shall provide servicing agency with the appropriate requirements that must be met on a project by project basis. In addition, for those specific projects that require classified electronic information processing, servicing agency will follow the CNSS policy, directives, instructions, and guidance.

ATTACHMENT 2

15. NRC Information Technology Security Training The servicing agency and its contractors shall ensure that their employees, consultants, and subcontractors with access to the NRCs information technology (IT) equipment and/or IT services complete NRCs online initial and refresher IT security training requirements to ensure that their knowledge of IT threats, vulnerabilities, and associated countermeasures remains current. Both the initial and refresher IT security training courses generally last an hour or less and can be taken during the employees regularly scheduled work day. Agency/Contractor shall ensure that their employees, consultants, and subcontractors, with access to the NRCs IT equipment, complete the Information Security (INFOSec) Awareness Training annually; no later than December 31.

The servicing agency and its contractor employees, consultants, and subcontractors shall complete the NRCs online, Computer Security Awareness course on the same day that they receive access to the NRCs IT equipment and/or services, as their first action using the equipment/service. For those contractor employees, consultants, and subcontractors who are already working under an existing agreement/contract, the online training must be completed in accordance with agency Network Announcements issued throughout the year.

The servicing agency and its contractor employees, consultants, and subcontractors who have been granted access to NRC information technology equipment and/or IT services must continue to take IT security refresher training offered online by the NRC throughout the term of the agreement/contract.

The servicing agency and its contractor employees will receive notice of NRCs online IT security refresher training requirements through agency-wide notices.

The NRC reserves the right to deny or withdraw the servicing agency and its contractor use or access to NRC IT equipment and/or services should the Agency/Contractor violate the Agency/Contractors responsibility under this clause.

16. Contract Security Requirements for Unescorted Access to Nuclear Power Plants If performance under this work order involves unescorted access to protected and vital areas of nuclear power plants or access to nuclear power reactor SGI, individual contractors requiring access to protected and vital areas of nuclear power plants or access to nuclear power reactor SGI shall be approved for unescorted access in accordance with the following procedures:

16.1 Temporary Approval The contractor (servicing agency employees and contractors) does not need a temporary approval if he or she has a valid Government clearance, for example, a servicing agency Q or L clearance. If the contractor employee does not have such a clearance, the contractor shall submit the information discussed below within 30 calendar days following contract award, modification, or proposal of new personnel for contract tasks. This information shall be provided for each person proposed to perform tasks requiring unescorted access to nuclear power plants or access to nuclear power reactor SGI. If access to SGI is needed, and unescorted access is not required, the provisions of 10 CFR 73.22 must be followed as a condition for access to SGI.

The information shall be provided to the NRC Division of Facilities and Security (DFS) through the NRC COR and consists of the following:

ATTACHMENT 2

- A completed Personnel Security Forms Packet, including an SF 86, "Questionnaire for National Security Positions, and copies of the individuals 5-year employment and education history checks, including verification of the highest degree obtained

- A reference from at least one additional person not provided by the individual

- Results of a psychological evaluation (This is not a requirement of the background check that is required for access to SGI.

- Form FD-258, ORIMDNRC000Z (Fingerprint Card)

- A certification that the contractor has found all checks acceptable The results of a psychological examination that uses a reliable written personality test or any other professionally accepted clinical evaluation procedure shall be used to evaluate a subjects trustworthiness, reliability, and stability. The servicing agency and contractor shall review all required information for accuracy, completeness, and legibility, except Part 2 of the SF 86, which must be completed in private and submitted, along with the Form FD-258 by the individual to the contractor in a sealed envelope, or the individual shall be fingerprinted by the subject utility, and the contractor shall be subject to the utilitys access authorization program.

As described in this section, DFS shall conduct criminal history and credit checks and a security assurance interview with the individual. On the basis of the results of these checks, DFS shall determine the individuals eligibility for temporary access and indicate an objection or no objection to NRC pending completion of the required background investigation.

16.2 Final Approval Final approval shall be granted if:

- The individual has completed processing (by the Office of Personnel Management) of the required investigation resulting in NRC endorsement for unescorted access at all nuclear facilities for the life of the contract.

- The contractor has obtained unescorted access authorization (other than temporary access) at the specific utility through that utilitys access authorization program, resulting in unescorted access at a specific facility.

- The individual possesses a valid Government-issued clearance as verified by DFS.

- A valid Government-issued clearance is defined as a U.S. Government-issued security clearance equivalent to or higher than an NRC "L" clearance (i.e., Secret) based on a comparable investigation not more than 10 years old. The investigation may involve an National Agency Check and Inquiries (NACI) or other investigation as deemed necessary by DFS in accordance with 10 CFR Part 10, 10 CFR 73.22, NRC MDs 12.3, NRC Personnel Security Program and 12.7 NRC Safeguards Information Security Program. Any question regarding the individuals eligibility for unescorted access to protected or vital areas of nuclear power facilities will be resolved in accordance with the provisions set forth in MD 12.3, which are incorporated into the Order by reference as though fully set forth therein.

The contractor shall, for each contractor individual approved for access under the provisions of this section, submit to DFS through NRC a signed statement from the individual that he or ATTACHMENT 2 she understands his or her responsibility to report information bearing on his or her continued eligibility for access authorization as specified in MD 12.3. Access to SGI not also involving unescorted access to protected and vital areas of nuclear power plants shall require the submission of a completed Personnel Security Forms Packet to DFS through NRC and will require a Background Check in accordance with 10 CFR Part 73.22 and MD 12.7. Any questions regarding the individuals eligibility for access to nuclear power reactor SGI shall be resolved in accordance with the provisions set forth in MD 12.7, which is incorporated into this contract by reference as though fully set forth herein. On the basis of the review of the applicants security forms by DFS and/or the receipt of adverse information by NRC, the individual may be denied access to nuclear power reactor SGI until a final determination of his or her eligibility for access is made under the provisions of MD 12.7.

16.3 Fitness for Duty Pursuant to NRC policy, all individuals proposed for work under this IAA who require unescorted access to nuclear power plants shall be subject to the requirements of the licensees fitness-for-duty program (10 CFR Part 26).

16.4 Basic Exposure Control and Personnel Dosimetry Training Requirements The contractor shall certify that personnel working under the scope of this contract have completed basic exposure control and personnel dosimetry training sufficient to meet the requirements of commercial nuclear power plants for unescorted access. Site specific training obtained at each site shall still be required during the performance of work under this contract in addition to the basic training.

16.5 Subcontractor InformationSubcontracting The servicing agency organization shall notify the issuing NRC office in writing reasonably in advance of entering into any major or significant technical service subcontract not contained in the original proposal. Major or significant must be used with judgment and related to the total value of the project and/or impact on the results. This advance notification shall include the following:

- A description of services to be called for by the subcontract

- Identification of the proposed subcontractor

- The proposed subcontract costs (in total)

- A statement that the proposed subcontract will not result in a real or apparent organizational conflict-of-interest situation. If the NRC program office requires additional specific subcontractor information or limitations, those requirements shall be stated in the IAA modification authorizing the subcontract.

17. Information on NRC Cooperative Programs with Foreign Governments and Organizations and With U.S. Industry Servicing agency facilities, contractors, and subcontractors working on NRC cooperative programs with foreign governments and organizations and with U.S. industry perform this work with the understanding that draft or formal reports on this work are to be available only to ATTACHMENT 2 participants in the program until public availability is authorized by the NRC office. Reports or codes (including data) on this work shall be issued as Draft Preliminary Reports (Codes) until the office authorizes issuance of the report as a formal report with the designation NUREG/IA-XXXX for international agreement reports or NUREG/CR-XXXX for contractor reports. Details of the handling of reports may be obtained from the NRC COR.
18. Stop-Work Order The NRC CO may, at any time, by written modification to the servicing agency, require the servicing agency to stop all or any part of the work called for by this work order for a period of up to 90 days after the order modification is delivered to the servicing agency, and for any further period to which the parties may agree. Any such order will be specifically identified as a stop-work order issued pursuant to this clause. Upon receipt of such an order, the servicing agency shall forthwith comply with its terms and take all reasonable steps to minimize the incurrence of cost allocable to the work covered by the order during the period of work stoppage.

Within a period of 90 days after a stop-work order is delivered to servicing agency or within any extension of that period to which the parties shall have agreed the office shall either:

- Cancel the stop-work order

- Terminate the work covered by this work order If a stop-work order issued under this clause is cancelled or the period of the stop-work order or any extension thereof expires, servicing agency will authorize the resumption of the work. An adjustment will be made in the delivery schedule or cost, or both, and the Order must be modified in writing accordingly. If a stop-work order is not cancelled and the work covered by the order is terminated in accordance with the terms of the GT&C section of the IAA, costs resulting from the stop-work order will be allowed in arriving at the termination settlement.

Attachment 3 NRC IAA No. 31310018S0016 UNITED STATES DEPARTMENT OF THE INTERIOR INTER/INTRA-AGENCY AGREEMENT (IAA)

1. Period of Performance START END 04/20/2018 09/30/2018 Buyer has work performed for them by the Seller named in item 6b. Seller to perform work as described herein for the agency named in item 6a.

SEE INSTRUCTIONS ON PAGE 2

2. Common Document Number (Agreement Number) 3. Check appropriate box IAA-18-HRD-PRJ-NRC-30 Original Modification No.
4. Under the authority of (Cite authorities) 43 U.S.C. 1701 et seq., (FLPMA) Working Capital Fund (WCF) 43 USC 1467, 1468 Department of the Interior Appropriation Act for FY Other (Buyer must cite authorities from Seller):

31 U.S.C. 1535 (the Economy Act)

5. Description of Work (If more space is needed, attach additional Project

Title:

sheets):

See attached IAA Supplemental - Description of Services HR Operations Gap Analysis BUYER SELLER 6a. Agency: Nuclear Regulatory Commission 6b. Agency: Interior Business Center - Human Resources Directorate Address: 111545 Rockville Pike Address: 7301 W. Mansfield Avenue Address: Address:

City: Rockville State: MD Zip: 20852 City: Denver State: CO Zip: 80235 Administrative POC: Romona Bowling Administrative POC: Karen Roper Email: Ramona.Bouling@nrc.gov Email: karen_roper@ibc.doi.gov Phone: 301-287-0699 Fax: Phone: 703-964-3581 Fax:

Technical POC: Technical POC:

Email: Ramona.Bouling@nrc.gov Email:

Phone: 301-287-0699 Fax: Phone: Fax:

ACCOUNT DATA BUYER SELLER

7. Agency Location Code 7a. 7b.
8. DUNS Number FSN 8a. 8b.
9. Treasury Account Symbol 9a. 9b.

(TAS)

10. Standard General Ledger 10a. 10b.

11a. 11b.

Fund: Fund:

11. Cost Structure/Account DOI Functional Area: DOI Functional Area:

only Cost Center: only Cost Center:

WBS: WBS:

12. Business Event Type Code 12a. DISB 12b. COLL
13. Requisition Number for 13a. 13b.

Buyer/Project Account for Seller OCHCO-18-0088

14. Contract Line Number for 14a. 14b.

Buyer/Proposal Number or other data for Seller

15. Buyer provide Expiration of 15a. 15b.

NOTE: Seller, ensure project completion by this date. (Seller must not Funding Source (Date or indefinite - no year incur additional costs). See Block 15a.

indefinite)

16. Amount Obligated by Buyer 17. Bill To (Name and Address, including zip code of Finance Office):
a. Initial or current obligation $ 24,745.00 Name:
b. Modification Amount (Check one) Address:

Increase Decrease Address:

c. Total obligation: $24,745.00 City: State: Zip:
18. Billing for Federal Agencies and DOD will be processed via IPAC.

Billing will be done: Bi-weekly Monthly Quarterly In advance Upon Approval, this agreement constitutes an obligation against the Buyer requesting the work, or authority to proceed with work by the Seller for the herein named agency in anticipation of reimbursement.

19. Approved for Buyer:

Mark Lohrmann Digitally signed by Mark Lohrmann Date: 2018.04.20 13:35:08 -04'00' KAREN ROPER Digitally signed by KAREN ROPER Date: 2018.04.06 09:12:35 -04'00' (Contracting Officer or other Authorized Signature) (Sellers Authorizing Signature)

  • other only for WCF 19a. Name (Type): Mark Lohrmann 20a. Name (Type): Karen Roper 19b.

Title:

Contracting Officer 20c. Date: 04/20/2018 20b.

Title:

Client Advocate 20c. Date:

Print

IAA Supplemental Termination Provisions:

This agreement may be terminated before the end performance date by written notice from either party, followed by mutual agreement between the parties. The customer will be billed for all costs incurred at the time of the termination.

Continuing Resolution:

18 Subject to availability of Fiscal Year _______ funding. Under a Continuing Resolution (CR),

billing will be at the prescribed daily rate with reconciliation to occur upon passage of the full 18 Fiscal Year _______ appropriation Description of Services Agreement Number: IAA-18-HRD-PRJ-NRC-30 Purpose of Agreement:

To document the provided Personnel and Payroll systems and related services as described in the Service Level Agreement (SLA) and in accordance with the Security Services Advisory (SSA).

IBC IPAC Contact Person: Matthew Schallenberg, (303)969-7274 Purpose of Modification:

IAA Supplemental - Description of Services IAA-18-HRD-PRJ-NRC-30 Agreement Number_________________________________________________________

A - HR Application Services Service____________________________________________________________________

Activity Hours/Units Amount

Title:

HR Operations Gap Analysis Fixed $ 24,745.00 The proposed Gap Analysis is a meeting conducted onsite at NRC between the IBC and NRC stakeholders involved with managing and delivering HR operations services.

Tentatively scheduled May 15 - 16, 2018 Details and deliverables are further described in the proposal issued 3/6/2018

Title:

Title:

Title:

Title:

Title:

Fixed

Title:

Fixed IAA Grand Total $ 24,745.00 Service Total $ 24,745.00

IAA Instructions Executing the IAA is a two part process.

Part 1: Please sign (19) and complete (19a, 19b, and 20c), fill in your Agency Location Code (7a), Customer DUNS Number (8a), Treasury Account Symbol-TAS (9a), Expiration of Funding Source (15a), and return IBC's IAA within 30 days of receipt. This is an acknowledgement of receipt (which can be signed by the program office) and in no way obligates funds, however your signature and verification of financial identification allows us to load your information into our financial system and begin providing services on October 1st. This is a mandatory step in setting up your recurring services.

Agency Location Code-ALC (7a) - need to validate as this is how your IPAC is routed to you.

A valid billing Treasury Account Symbol (TAS, 9a) - please ensure Finance confirms the correct billing TAS which will be used in booking the IPAC. An incorrect TAS will cause your billings personnel much additional work.

Expiration of Funding Source (15a) - please indicate the date your funding source expires:

For one-year money: 9/30/2017 For multi-year money that expires next year: 9/30/2018 For no-year money: Indefinite Part 2: Full funding must be received no later than November 15th. Please fill in the Obligating Document Number (13a) and return to IBC. Note: the new IAA form calls this a Requisition Number, but we cannot accept a Purchase Requisition (PR). We need a fully executed Purchase Order (PO)/Obligating Document Number to process your funding document. In the event of a Continuing Resolution (CR), IBC needs to receive the limit/portion of the funding authorized by the CR to continue operating as soon as possible after October 1st. Once the budget is passed, IBC needs to receive the balance of funding due in full as soon as possible.

Vendor Product Renewals - In addition to CR funding, vendor product renewals must be paid in full as soon as possible after October 1st. IBC cannot initiate a contracting action until we receive full funding. If you do not submit funding, your agency runs the risk of suspended service.