Forwards Insp Repts 50-272/96-80 & 50-311/96-80 on 960506-17 & 1021-25.Violations Noted But Not Cited
ML18102A730
Person / Time
Site: Salem  PSEG icon.png
Issue date: 12/31/1996
From: Wiggins J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Eliason L
Public Service Enterprise Group
Shared Package
ML18102A731 List:
References
EA-96-548, NUDOCS 9701090180
Download: ML18102A730 (3)


See also: IR 05000272/1996080

Text

EA No.96-548

Mr. Leon R. Eliason

Chief Nuclear Officer & President

Nuclear Business Unit

December 31, 1996

Public Service Electric and Gas Company

P.O. Box 236

Hancocks Bridge, New Jersey 08038

SUBJECT:

SALEM LICENSING BASES TEAM INSPECTION REPORT 96-80

Dear Mr. Eliason:

This letter transmits the report of the U.S. Nuclear Regulatory Commission (NRC) Special

Team Inspection (STI) at Salem Unit 2, and various follow-on inspection activities

conducted in several phases between May 6 and October 25, 1996.

The preliminary findings of the May 1996 team were initially discussed at a meeting

between Mr. B. Simpson and other members of your staff, and Mr. J. Wiggins and other

NRC representatives, on May 23, 1996. The May 1996 team found examples in the

Unit 2 control air, fuel handling ventilation, and containment cooling systems where the

design and licensing bases were not well understood and connected. A meeting was held

on June 11, 1996, to discuss the preliminary findings of this team and, more broadly, your

actions with respect to the conformance of the Salem Station to its licensing basis. The

extent and significance of these issues were such that you supplemented your current

outage efforts by initiating an "FSAR Project" to examine licensing bases conformance in a

systematic manner. Aspects of that project, including 17 specific NRC questions, were

discussed in telephone conferences and are summarized in your August 23, 1996 letter to

the NRC. We understand that the information from your FSAR project, coupled with the

results of previously completed as-built walkdowns, provided the basis for your conclusion

that there is reasonable assurance that Salem Unit 2 could be operated within its

licensing/design bases. That conclusion was subsequently presented to your Management

Review Committee (MRC) and approved on September 30, 1996. NRC management will

review the results of both the SSFI ano the inspection reported herein, in reaching its

conclusion in these matters.

The NRC observed portions of the FSAR Project in progress (from July-September 1996)

and reviewed a sample of its outputs. During the week of October 21, 1996, progress in

addressing specific items from this team was also examined by the NRC. Our observations

of the FSAR Project found it to be a substantial effort that was well managed. The Project

included well-focused elements of independent confirmation. Nevertheless, to provide an

independent review of your efforts and a measure of additional assurance that Salem

Unit 2 can be operated within its licensing/design bases, the NRC initiated a Safety System

Functional Inspection (SSFI), which will be reported upon separate from this effort.

Jf-:C'J r

1

( r

9701090180 961231

PDR

ADOCK 05000272

G

PDR

Mr. Leon R. Eliason

2

Several findings from this inspection represent violations of NRC requirements, but are not

being cited in coordination with the Office of Enforcement, in accordance with the criteria

of Section Vll.B.2 of the NRC Enforcement Policy, principally because they stem from

licensed activities prior to the shutdown period and have since been addressed by broad

comprehensive PSE&G programs underway at Salem to identify and correct such problems.

In accordance with 10 CFR 2. 790 of the Commission's regulations, a copy of this letter

and its enclosure will be placed in the NRC Public Document Room.

Enclosures:

Sincerely,

ORIGINAL SIGNED BY

James T. Wiggins, Director

Division of Reactor Safety

1. NRC Region I Team Inspection Report No. 50-272/96-80 and 50-311196-80

2. Special Team Inspection 96-80 Charter

3. Slides from Public Service Electric & Gas Presentation

Docket Nos. 50-272

50-311

cc w/encl:

L. Storz, Senior Vice President - Nuclear Operations

E. Simpson, Senior Vice President - Nuclear Engineering

E. Salowitz, Director - Nuclear Business Support

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

D. Garchow, General Manager - Salem Operations

J. Benjamin, Director - Quality Assurance & Nuclear Safety Review

D. Powell, Manager, Licensing and Regulation

R. Kankus, Joint Owner Affairs

A. Tapert, Program Administrator

R. Fryling, Jr., Esquire

M. Wetterhahn, Esquire

P. MacFarland Goelz, Manager, Joint Generation

Atlantic Electric

Consumer Advocate, Office* of Consumer Advocate

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

Public Service Commission of Maryland

State of New Jersey

State of Delaware

' '

' *

Mr. Leon R. Eliason

3

Distribution w/encl:

Region I Docket Room (with concurrences}

Kay Gallagher, DRP

Nuclear Safety Information Center (NSIC}

J. Wiggins, DRS

L. Nicholson, DRP

S. Barber, DRP

G. Kelly, DRS

N. Della Greca, DRS

D. Screnci, PAO

NRC Resident Inspector

PUBLIC

DRS Files (2)

Distribution w/encl: (Via E-Mail}

L. Olshan, NRR

W. Dean, OEDO

J. Stolz, PDl-2, NRR

M. Callahan, OCA

Inspection Program Branch, NRR (IPAS}

R. Correia, NRR

R. Frahm, Jr., NRR

DOCUMENT NAME: A:\\SA968080.FIN

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" =No copy

OFFICE

RI/DRS

I

Rl/DRP

I

RI/DRS

I

RI/

I

RI/

NAME

EKelly

LNicholson

JWiggins

DATE

01 /03/97

01/ /97

01 / /97

01 /

/97

01/ /97

OFFICIAL RECORD COPY

I