MONTHYEARML18159A0392018-06-0606 June 2018 National Technical Systems (Nts) - Potential Part 21 on Dedicated Items Not Available for Pmi Testing (NUPIC) ML18102A5292018-04-0303 April 2018 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0121, Rev. 0, Refurbished Pressure Regulator Assembly, P/N 1776 506. ML18075A3552018-03-0606 March 2018 10 CFR Part 21 Notification of Defect on Crane Nuclear Figure Number 83 1/2 Spl 10x8x10 and 6x4x6 Bolted Bonnet Gate Valve ML17142A3232017-05-11011 May 2017 Interim Report Concerning Supply of Stainless Steel Tubing ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology ML12347A3082012-12-12012 December 2012 Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology ML12319A0122012-09-27027 September 2012 Error in Main Steam Line High Flow Calculational Methodology ML12158A4472012-06-0606 June 2012 Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML11273A0482011-09-28028 September 2011 10 C.F.R. Part 21 Notification of Potential Defect in Solid State Relay ML1127000672011-09-26026 September 2011 GE-Hitachi Part 21 Reportable Condition Notification: Failure to Include Seismic Input in Channel-Control Blade Interference Customer Guidance ML1112502392011-05-0202 May 2011 10 C.F.R. Part 21 Notification of Potential Defect, P/N 611130-T13-N SS5 Solid State Relay ML1025202192010-09-0303 September 2010 Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance ML1018907392010-07-0101 July 2010 Part 21 Report Concerning Failure of Turbine Overspeed Reset Control Valve Diaphragm ML0907611882009-03-11011 March 2009 Part 21 Notification - Defective Hk and K-Line Circuit Breaker Tension Springs ML0511602412005-04-14014 April 2005 Thermo Electron Svioc, SV18C and SV28C Series Recorders ML0232901622002-11-18018 November 2002 Final Report, Stability Option III: Possible Successive Confirmation Count Resets - Not Reportable ML0228102902002-09-30030 September 2002 Main Steam Line Valve Out-of-Service Final Report 2018-06-06
[Table view] Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML24004A2092023-12-12012 December 2023 Flowline, Inc. - Interim Part 21 Report Notification Regarding Supply of 1 Sch. 80 (0.179 Wall) SB466 Uns C71500 Buttweld Long Radius 90 Degree Elbow; Manufacturer: Flowline; Heat No: 27668; 27 Pieces - Heat Code ML23352A2382023-12-0808 December 2023 56882-EN 56882 - Tioga Pipe, Inc Interim Part 21 Report Re Supply of 1 Inch Sch. 80 SB466 Uns C71500 Buttweld Long Radius 90 Degree Elbow ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML21322A0512021-10-27027 October 2021 Paragon Energy Solutions, LLC, P21-09282021, Rev. 0, Final Notification of a Deviation with Inverter Assembly (Model NLI-072034-CSI-K-5-A) ML21295A2472021-10-18018 October 2021 Engine Systems, Inc., Part 21 Reportable Notification on a Pressure Regulator Valve ML21260A0072021-09-0909 September 2021 Ametek Solidstate Controls, Notification of Potential Defect - 10CFR Part 21 Report Re Omron Timer Relay ML19024A1642019-01-0707 January 2019 Ametek - Notification of Potential Defect - 10CFR Part 21 Re Solidstate Controls Safety-Related Operational Spare Parts Kits ML18102A5292018-04-0303 April 2018 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0121, Rev. 0, Refurbished Pressure Regulator Assembly, P/N 1776 506. ML18087A0032018-03-21021 March 2018 Crane Nuclear, Inc. - Part 21 Notification of Defect on Crane Nuclear Figure Number 83 1/2 Spl 10x8x10 and 6x4x6 Bolted Bonnet Gate Valve (Updated) ML18075A3552018-03-0606 March 2018 10 CFR Part 21 Notification of Defect on Crane Nuclear Figure Number 83 1/2 Spl 10x8x10 and 6x4x6 Bolted Bonnet Gate Valve ML18079A0142018-03-0606 March 2018 Crane Nuclear, Inc., 10 CFR Part 21 Notification of Defect on Crane Nuclear Figure Number 83 1/2 Spl I0x8x10 and 6x4x6 Bolted Bonnet Gate Valve ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17142A3232017-05-11011 May 2017 Interim Report Concerning Supply of Stainless Steel Tubing ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML16281A2712016-09-30030 September 2016 Part 21 - Safety Related Component Welding by an Unqualified Welder ML16321A4502016-08-31031 August 2016 Part 21 Notification - Flowserve Swing Check Valves ML16243A4752016-08-26026 August 2016 Part 21 Safety Related Component Welding by an Unqualified Welder ML16188A3742016-06-30030 June 2016 Part 21 - Inadequate Swaging and Adherence of Silicone O-Ring and Silicone PAD Soft Seat Main Disc and Pilot Disc Assemblies ML16039A2692016-02-0303 February 2016 Nutherm International, Inc. - Potential Issue Regarding Incorrect Industrial Irradiation Dose, Per Cooper, Oconee, Fitzpatrick, Point Beach, Brunswick, and Susquehanna ML15265A4182015-09-21021 September 2015 Sor, Inc. - Part 21 Notification of Deviation - ML15251A212 Irradiation Certification with Insufficient Margin BSEP 15-0054, Part 21 Notification Regarding Allen Bradley Model 700RTC Relays2015-06-25025 June 2015 Part 21 Notification Regarding Allen Bradley Model 700RTC Relays ML15162A0232015-06-0909 June 2015 Part 21 - Incorrect Part Number Relay Shipped to Brunswick Nuclear Plant ML15173A0162015-06-0808 June 2015 Engine Systems, Inc. - 1OCFR21 Reporting of Defects and Non-Compliance - Report No. 10CFR21-0112, Rev. 0, Incorrect Relay Installed in Governor Control Panel, P/N 8002096-PANEL ML15155A5772015-05-28028 May 2015 Part 21 Notification Regarding Allen Bradley 700RTC Relay Configuration ML15103A2442015-04-0606 April 2015 Part 21 Report - Deviation of Hk Circuit Breaker Close Latch Spring ML14261A1502014-09-17017 September 2014 Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M1 Diaphragms, Customer Testing ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML14204A7082014-07-23023 July 2014 Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14210A0092014-07-21021 July 2014 Part 21 Report - Incorrect Valve Solenoids Provided ML14070A1832014-02-14014 February 2014 Part 21 Report - Failed Pressure Regulator During Post Installation EDG Pressure Testing ML13340A3822013-12-0505 December 2013 Part 21 Reportable Condition Notification: Failure of Relay Logic Card Modules in 2 Out of 4 Voters ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12347A3082012-12-12012 December 2012 Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology ML12318A0412012-11-0808 November 2012 Part 21 Report - Commercial Grade Dedication Not Properly Applied to Butterfly Valves ML12319A0122012-09-27027 September 2012 Error in Main Steam Line High Flow Calculational Methodology ML12177A0562012-06-21021 June 2012 Part 21 - Reliability Degradation of Resistors in Trip Units and Readout Assemblies ML12163A1302012-06-0606 June 2012 Part 21 Report - Failure of CRD Collet Retainer Tube/Outer Tube Weld ML12158A4472012-06-0606 June 2012 Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld ML12123A0892012-04-27027 April 2012 Abb, Inc., Notification of Potential Part 21 Report - Hk Circuit Breaker Studs Failed to Meet Specification ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12058A1412012-02-23023 February 2012 Part 21 Report - Rosemount Nuclear Instruments, Inc., Pressure Transmitter with Nonzero Based Calibrations ML12040A2832012-02-0707 February 2012 Notification of Potential Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance ML12038A0282012-02-0202 February 2012 Failure of CRD Collet Retainer Tube/Outer Tube Weld ML12032A2402012-02-0101 February 2012 Notification of Potential Part 21 - 60-Day Interim Report Notification: Failure of CRD Collet Retainer Tube/Outer Tube Weld ML11278A0762011-09-28028 September 2011 Abb, Inc. - 10 CFR Part 21 Notification of Potential Defect, Solid State Relays - Update of Previous Notification 2023-05-24
[Table view] |
Text
ENGINE SYSTEMS, INC.
175 Freight Road Telephone: 252/977-2720 Rocky Mount, NC 27804 Fax: 252/446-1134 April 3, 2018 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001
Subject:
10CFR21 Reporting of Defects and Non-Compliance -
En~ine Systems, Inc. Report No. 10CFR21-0121, Rev. 0 Refurbished Pressure Regulator Assembly, P/N 1776 506
Dear Sir:
The enclosed report addresses a reportable notification on a refurbished pressure regulator assembly, P/N 1776 506.
A copy of the report has been mailed to our affected nuclear customer.
Please sign below, acknowledging receipt of this report, and return a copy to the attention of Document Control at the address above (or, fax to number 252/446-1134) within 10 working days after receipt.
Yours very truly, ENGINE SYSTEMS, INC.
Susan Woolard Document Control Please let us know if ANY of your mailing information changes - name of recipient, name of company/facility, address, etc. Mark the changes on this acknowledgment form and send to us by mail or FAX to the number above.
RECEIVED:---------
93 DATE:
Quality Performance With Pride
ENGINE SYSTEMS, INC.
175 Freight Road, Rocky Mount, NC 27804 Telephone: 252/977-2720 Fax: 252/446-1134 Report No. 10CFR21-0121 Rev. 0: 03/30/18 10CFR21 REPORTING OF DEFECTS AND NON-COMPLIANCE COMPONENT: Pressure Regulator Assembly - Component Omitted During Refurbishment P/N 1776 506 SYSTEM: Emergency Diesel Generator CONCLUSION: Reportable in Accordance With 10CFR21 Prepared By: Date: 3 /30/18
~tM Engineering Manager Reviewed By: ~ f2J4- Date: 3)30 );J Quality Manager Quality Performance With Pride
~-, ..
Report No. 10CFR21-0121 Record of Revisions Page: 1 of 1 REV DATE PAGE DESCRIPTION 0 03/30/18 Initial issue.
Report No. 10CFR21-0121 Revision: 0 Date: 03/30/18 Page: 1 of 2 Pursuant to 10 CFR 21.21(d)(4), ESI is presenting the required information as follows:
(i) Name and address of the individual or individuals informing the Commission.
Dan Roberts John Kriesel Quality Manager Engineering Manager Engine Systems Inc. Engine Systems Inc.
175 Freight Rd. 175 Freight Rd.
Rocky Mount, NC 27804 Rocky Mount, NC 27804 (ii) Identification of the basic component supplied within the United States which fails to comply or contains a defect.
Pressure Regulator Assembly, PIN 1776 506.
(iii) Identification of the firm supplying the basic component which fails to comply or contains a defect.
Engine Systems Inc:
(iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect of failure to comply.
ES! supplied a refurbished pressure regulator assembly, PIN 1776 506, SIN 20776487, to Brunswick Nuclear Plant in August 2017. ES/ later determined that two components of the assembly, an upper and lower diaphragm plate, were omitted during reassembly of the refurbished regulator. Reference item 8 on Figure 1 for location of the diaphragm plates within the pilot valve portion of the regulator assembly. These metal diaphragm plates distribute load and retain the associated rubber diaphragm.
Omission of the metal plate may not initially affect operation of the pilot valve and therefore may not be detected during functional testing; however over repeated cycles there is a strong possibility that the rubber diaphragm would tear or rupture without the benefit of load distribution and support provided by the metal diaphragm plate.
The regulator assembly is used in the safety-related air start system of the emergency diesel generators (EDGs) at Brunswick Nuclear Plant. Failure of the regulator to function properly due to the omission of a component within the pilot valve portion of the assembly could adversely affect the starting capability of the EOG. Since the EOG is a safety system used to ensure the safe shutdown of the nuclear reactor, this issue is considered to be a reportable defect as defined by 10CFR-part 21.
(v) The date on which the information of such defect or failure to comply was obtained.
February 1, 2018 (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
ES/ Sales Customer ES/ Serial Mfg Serial Customer Qty C-of-C Date Order P.O. Number Number Duke Energy -
8002796 03048459 1 0812412017 8002796-5.1-1 20776487 Brunswick Nuclear Plant (vii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
The assembly has been recalled and will be reworked by ES/ using a new, dedicated repair kit and re-assembled and tested per approved procedures. An additional QA inspection will be performed to ensure presence of the diaphragm plates. This activity will be completed within the next 30 days.
(viii) Any advice related to the potential defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
NIA
Report No. 10CFR21-0121 Revision : 0 Date : 03/30/18 Page : 2 of 2 Item 8 is the diaphragm plate Figure 1: Outline Dwg of Pilot Valve Portion of Regulator Assembly