Provides Suppl to Request,Deleting License Condition 2.c(24)(a) Re Shift Manning & Incorporated Controls on Use of Overtime Into Units,Per GL 82-12
ML18102A493
Person / Time
Site: Salem  PSEG icon.png
Issue date: 10/24/1996
From: Storz L
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML18102A494 List:
References
GL-82-12, LCR-S96-11, LR-N96305, NUDOCS 9610310308
Download: ML18102A493 (4)


Text

Public Service Electric and Gas Company Louis F. Storz Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-5700 Senior Vice President - Nuclear Operations OCT 24*1995 LR-N96305 LCR S96-11 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 SUPPLEMENT TO REQUEST FOR CHANGE TO OPERATING LICENSE AND TECHNICAL SPECIFICATIONS SALEM GENERATING STATION UNITS 1 AND 2 FACILITY OPERATING LICENSES DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 Gentlemen:

By letter LR-N96264, dated August 27, 1996, Public Service Electric and Gas Company (PSE&G) submitted a request to amend the Operating License for Salem Unit 2 and the Technical Specifications for Salem Units 1 and 2. This letter provides a supplement to that request.

The requested change to the Salem Unit 2 facility operating license deleted license condition 2.C(24) (a) Shift Manning and incorporated controls on the use of overtime into the Salem Units 1 and 2 Technical Specifications Administrative Controls Section.

PSE&G is revising the wording associated with the control of overtime.

The revised wording will delete the reference to Generic Letter 82-12 and require administrative contro'is be established which will ensure adequate shift coverage is maintained without routine heavy use of overtime. In addition, the revised specification will require authorization in advance by the General Manager -

Salem Operations or his designee for any deviations from the overtime guidelines. The guidelines will require monthly review of overtime to ensure that excessive hours have not been

___________ assigned.

The proposed change to.the Salem Unit 2 operating license is not affected by this supplement.

~~~~~~~~~-=-=--=-=~~~~-,---------------,

( 9610310308 961024 '

i PDR ADOCK 05000272 P PDR IXJ.. Printed on

\:ti Recycled Paper

OCT 2 41996 Document Control Desk 2 LCR S96-11 LR-N96305 PSE&G has reviewed the previously submitted evaluation in accordance with the three standards set forth in 10CFR50.92 and has concluded that no change is necessary as a result of the revised pages and that the conclusion of the no significant hazards consideration remains valid. contains the revised wording on marked pages of the Salem Unit 1 and 2. Technical Specifications. These pages supersede previously provided marked up pages for the Administrative Controls Section.

Should there be any questions regarding this submittal, please contact us.

Sincerely, HLO/pfr Attachment ( 1)

Affidavit

OCT 2 4 1996 Document Control Desk 3 LCR S96-11 LR-N96305 C Mr. H. J. Miller, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. L. Olshan, Licensing Project Manager - Salem U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr. C. Marschall (X24)

USNRC Senior Resident Inspector Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering 33 Arctic Parkway CN 415 Trenton, NJ 08625

REF: LR-N96305 STATE OF NEW JERSEY SS.

COUNTY OF SALEM L. F. Storz, being duly sworn according to law deposes and says:

I am Senior Vice President - Nuclear Operations of Public Service Electric and Gas Company, and as such, I find the matters set forth in the above referenced letter, concerning the Salem Generating Station, Unit Nos. 1 and 2, are true to the best of my knowledge, information and belief.

1996 KIMBERLY JO BROWN NOTl\RY PUBLIC OF NEW JERSEY My Commission expires on My Commission Expires April 21. 1998