Mr. Leon R. Eliason
Chief Nuclear Officer & President
Nuclear Business Unit
Public Service Electric and Gas Company
P. 0. Box 236
Hancocks Bridge, New Jersey 08038
September 10, 1996
SUBJECT:
COMBINED SALEM EXAMINATION REPORT NOS. 50-272/96-09 (OL) AND
50-311 /96-09 (OL)
Dear Mr. Eliason:
From July 8-12, 1996, the NRC administered examinations to six employees of your
company who had applied for licenses to operate the Salem Nuclear Generating Station,
Units 1 and 2. The examination was conducted in accordance with Revision 7 of NUREG-
1021, "Operator Licensing Examiner Standards." At the conclusion of the examination,
generic findings and observations that evolved as a result of the examination were
discussed with Messrs. J. Zerbo and C. Bakken and other members of your staff identified
in the enclosed report.
Based on the results of the examinations, all six of the senior reactor operator (SRO)
candidates, which included five SRO instant and one SRO upgrade, passed the
examination. The licenses for the SRO instant candidates were not issued, however,
because the five plant reactivity manipulations required by 10 CFR 55.31 (a)(5) had not yet
- een accomplished due to the Salem units being in an extended shutdown condition. Upon
- ~Jmpletion of the reactivity manipulations, licenses will be issued to these five candidates .
.
~\\ license was issued to the one candidate who was an SRO upgrade.
)11 accordance with 10 CFR 2. 790 of the Commission's regulations, a copy of this letter
and its enclosure will be placed in the NRC Public Document Room.
No reply to this letter is required, but should you have any questions regarding this
examination, please contact me at 610-337-5211.
9609180372 960910
ADOCK 05000272
V
Sincerely,
- (original signed by)**
Glenn W. Meyer, Chief
Operator Licensing and
Human Performance Branch
Division of Reactor Safety
,.
. '
Mr. Leon R. Eliason
2
Docket Nos. 50-272; 50-311
Enclosure:
Examination Report Nos. 50-272/96-09 (OL)
and 50-311/96-09 (OL) w/Attachments 1-3.
cc w/encl; w/o Attachments 1-3:
L. Storz, Senior Vice President - Nuclear Operations
E. Simpson, Senior Vice President - Nuclear Engineering
E. Salowitz, Director - Nuclear Business Support
C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.
D. Garchow, General Manager - Salem Operations
J. Benjamin, Director - Quality Assurance & Nuc;lear Safety Review
D. Powell, Manager, Licensing and Regulation
R. Kankus, Joint Owner Affairs
A. Tapert, Program Administrator
R. Fryling, Jr., Esquire
M. Wetterhahn, Esquire
P. MacFarland Goelz, Manager, Joint Generation
Atlantic Electric
Consumer Advocate, Office of Consumer Advocate
William Conklin, Public Safety Consultant, Lower Alloways Creek Township
Public Service Commission of Maryland
State of New Jersey
State of Delaware
cc w/encl and Attachments 1-3:
J. McMahon, Manager, Nuclear Training
W. O'Malley, Manager, Training Operations
J. Nichols - Principal Training Supervisor
Distribution w/encl and Attachments 1-3:
DRS Master Exam File *
PUBLIC
Nuclear Safety Information Center (NSIC)
Distribution w/encl; w/o Attachments 1-3:
Region I Docket Room (with concurrences)
L. Vick, NRR, HOLB
J. Wiggins, DRS
P. Bissett, Chief Examiner, DRS
NRG Resident Inspector
L. Nicholson, DRP
- S. Barber, DRP
G. Kelly, DRS
N. Della Greca, DRS
J. Nickolaus, Contract Examiner, PNL
Mr. Leon R. Eliason
3
Distribution w/encl; w/o Attachments 1-3 (Via E-Mail):
L. Olshan, NRR
W. Dean, DEDO
J. Stolz, PDl-2, NRR
S. Richards, OLB/NRR
M. Callahan, OCA
Inspection Program Branch, NRR (IPAS)
DOCUMENT NAME: A:SA960909.INS
To receive a copy of this document. indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclo~ure. "N" = No copy
OFFICE
RI/DRS
l., RI/DRS
I
I
I
I
'
NAME
PBi ssett/dmg Jfl&-rGMeyer
(1
/
DATE
09/0,2'/96
09/ ~* /96 '- rt'1'"
09/
/96
09/
/96
09/
/96
JU
OF iICIAL RECORD COPY
I ..
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALE ROAD
KING OF PRUSSIA, PENNSYLVANIA 19406-1415
Mr. Leon R. Eliason
Chief Nuclear Officer & President
Nuclear Business Unit
Public Service Electric and Gas Company
P. 0. Box 236
Hancocks Bridge, New Jersey 08038
September 10, 1996
SUBJECT:
COMBINED SALEM EXAMINATl.ON REPORT NOS. 50-272/96-09 (OL) AND
50-311 /96-09 (OL)
Dear Mr. Eliason:
From July 8-12, 1996, the NRC administered examinations to six employees of your
company who had applied for licenses to operate the Salem Nuclear Generating Station,
Units 1 and 2. The examination was conducted in accordance with Revision 7 of NUREG-
1021, "Operator Licensing Examiner Standards." At the conclusion of the examination,
generic findings and observations that evolved as a result of the examination were
discussed with Messrs. J. Zerba and C. Bakken and other members of your staff identified
in the enclosed report.
Based on the results of the examinations, all six of the senior reactor operator (SRO)
candidates, which included five SRO instant and one SRO upgrade, passed the
examination. The licenses for the SRO instant candidates were not issued, however,
because the five plant reactivity manipulations required by 10 CFR 55.31 (a)(5) had not yet
been accomplished due to the Salem units being in an extended shutdown condition. Upon
completion of the reactivity manipulations, licenses will be issued to these five candidates.
A license was issued to the one candidate w_ho was an S_RO upgrade.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter
and its enclosure will be placed in the NRC Public Document Room.
No reply to this letter is required, but should you have any questions regarding this
examination, please contact me at 610-337-5211.
Sincerely,
.
.*
.
.
.
. .
. .
. .. :
.
.
Glenn W. Meyer, Chief
Operator Licensing and
Human Performance Branch
Division of Reactor Safety
-.
Mr. Leon R. Eliason
2
Docket Nos. 50-272; 50-311
Enclosure:
Examination Report Nos. 50-272/96-09 (OL)
and 50-311 /96-09 (OL) w/Attachments 1-3.
cc w/encl; w/o Attachments 1-3:
L. Storz, Senior Vice President - Nuclear Operations
E. Simpson, Senior Vice President - Nuclear Engineering
E. Salowitz, Director - Nuclear Business Support
C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.
D. Garchow, General Manager - Salem Operations
J. Benjamin, Director - Quality Assurance & Nuclear Safety Review
D. Powell, Manager, Licensing and Regulation
R. Kankus, Joint Owner Affairs
A. Tapert, Program Administrator
R. Fryling, Jr., Esquire
M. Wetterhahn, Esquire
P. MacFarland Goelz, Manager, Joint Generation
Atlantic Electric
Consumer Advocate, Office of Consumer Advocate
William Conklin, Public Safety Consultant, Lower Alloways Creek Township
Public Service Commission of Maryland
State of New Jersey
State of Delaware
cc w/encl and Attachment$ 1-3:
J. McMahon, Manager, Nuclear Training
W. O'Malley, Manager, Training Operations
J. Nichols - Principal Training Supervisor