MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 ML18102A7361997-01-0707 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Eighteen Month Surveillance Performed to Measure RCS Total Flow Rate to Account for Necessary Plant Conditions for Performing Test in Mode 1 & Current Extended Plant Outages 1999-08-25
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML20148K0841997-06-0404 June 1997 Amends 194 & 177 to Licenses DPR-70 & DPR-75,respectively, Changing TSs 3.4.3 & 3.4.5, Relief Valves, to Ensure That Automatic Capability of PORVs to Relieve Pressure Is Maintained When Valves Are Isolated ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 1999-08-25
[Table view] |
Text
- '-. *-
Public Service Electric and Gas Company Joseph J. Hagan Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations OCT 111994 NLR-N94149 LCR 93-28 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
REQUEST FOR AMENDMENT SALEM GENERATING STATION UNIT NOS. 1 AND 2 FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 The proposed request changes the Limiting Condition for Operation (LCO) 3/4.4.4 (for both units) by adding the phrase "capable of being powered from an emergency power supply" to the Limiting Condition for Operation statement. This request also proposes to change the frequency of surveillance requirement 4.4.4.2 (for both units) from 92 days to every refueling outage. As discussed in Attachment 1 to this letter, PSE&G's conclusion is that granting this request would not involve a significant hazards consideration. Attachment 2 contains the Technical Specifications marked up pages.
Upon NRC approval of this proposed change, PSE&G requests that the amendment be made effective on the date of issuance, and to be implemented within sixty (60) days to provide sufficient time for associated administrative activities.
Sincerely, 0 . .. n n ~'! r)
(--------- -------
~"' 1. t...) '...)
~ ~:....}
i 9410240065 941011 ~
1 ~DR ADOCK 05000272 PDR
OCT 11 7994 Document Control Desk 2 NLR-N94.149 Attachment (2)
C Mr. L. N. Olshan, Licensing Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. c. S. Marschall (S09)
USNRC Senior Resident Inspector Mr. T. T. Martin, Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Kent Tosch, Manager, VI New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625
NLR-N94149 LCR 93-28 STATE OF NEW JERSEY SS.
COUNTY OF SALEM J. J. Hagan, being duly sworn according to law deposes and says:
I am Vice President - Nuclear Operations of Public Service Electric and Gas Company, and as such, I find the matters set forth in the above referenced letter, concerning the Salem Generating Station, Unit No. 1, are true to the best of my knowledge, information and belief.
Subscribed and Sw o be~me this '7 da£ C'e- , 1994 j& j~_,,_ ~,N4 BARBARA A. POWELL NOTARY PUBLIC OF NEW JERSEY My Commission expires on ~~~~~~DlJ-llKWw=l~D~#~21~6~03~2~3~~~
My comission Expires Dec. 2, 1998
NLR-N94149 ATTACHMENT 1 LCR 93-'28 I. DESCRIPTION OF THE PROPOSED CHANGES IA Proposed change to Limiting Condition for Operation (LCO) 3/4.4.4 (for both units)
The pressurizer shall be OPERABLE with a water volume of less than or equal to 1650 cubic feet (92% indicated level), and at least two groups of pressurizer heaters each having a capacity of 150 kw and capable of being powered from an emergency power supply.
IB Proposed change to surveillance requirement 4.4.4.2 (for both units)
The capacity of each of the above required groups of pressurizer heaters shall be verified by measuring circuit current at least once each refueling outage.
II. REASON FOR THE PROPOSED CHANGES IIA The proposed change to LCO 3/4.4.4, as described in section IA above, is intended to clarify all requirements needed to consider the Pressurizer operable. The proposed change is consistent with NUREG 1431, Standard Technical Specifications Westinghouse Plants, issued on September 1992.
IIB The proposed change to surveillance requirement 4.4.4.2 is consistent with guidance of NUREG 1366 (Improvements to Technical Specifications Surveillance Requirements, published December 1992), and Generic Letter 93-05 (Line-Item Technical Specifications improvements to Reduce Surveillance Requirements for Testing During Power Operation, issued on September 27, 1993)
- NLR-N94149 ATTACHMENT 1 LCR 93-'28 III.JUSTIFICATION AND EVALUATION OF THE SAFETY SIGNIFICANCE AND POTENTIAL CONSEQUENCES OF THE REQUEST IIIA The proposed change clearly states that the required heater group must be capable of being powered from an emergency power supply.
As presently written, the LCO does not include this requirement as part of the LCO itself. Consequently, the Pressurizer could be considered operable without having the capability of powering the required heater group from an emergency power source, as intended by the basis of the Technical Specifications and clearly stated in LCO's Action statement. ACTION (a) partially states that with an inoperable emergency power supply, operation may only continue for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
Therefore, the proposed change will correctly relocate the operability requirement to the LCO statement rather than in its action statement.
IIIB As stated in the NUREG 1366 (Improvements to Technical Specifications Surveillance Requirements, published December 1992), most pressurizer heaters are in constant use, both the variable and to some extent the back-up heaters. In additon, the pressurizer heaters have a history of being reliable, and the purpose of this surveillace requirement is to demonstrate that the capacity of the heaters has not degraded. Therefore, based on the heater reliability the 92 day surveillance frequency requirement seems to be excessive.
The Salem Station Pressurizer heaters are electric immersion heaters. The pressurizer has seventy eight (78) vertically mounted immersion heaters. The total heater capacity of 1800 KW is divided among the one (1) variable group (415KW) and two (2) backup groups {21/11 group - 415KW and 22/12 group - 969 KW).
Variable control heaters are used during steady state operations to compensate for ambient heat losses in the pressurizer and the continuous bypass spray flow. The backup group heaters are used during initial heatup (bubble drawing) coming from refueling outages and during reactor coolant system transients to aid the variable heaters. The design of the Salem Station Pressurizer heaters is identical to that described in the NUREG, and the extension of the surveillance requirement is a recognized enhancement and assurance to the continued reliability of the pressurizer heaters.
NLR-N94149 ATTACHMENT 1 LCR' 93-"28 IV. DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION The discussion below applies to both proposed changes.
This proposed Amendment request:
- 1. Does not involve a significant increase in the probability or consequences of an accident previously evaluated.
The request (both proposed changes) does not change any assumption or parameter assumed to function in any of the design/licensing basis analysis.
The proposed change as described in section IA merely relocates the requirement to supply emergency power to the required heater group from the action to the LCO statement.
The change as described in section IB does not eliminate the surveillance requirement, but extends its frequency from 92 days to once per refueling outage in accordance with NRC recommendation. The design of the Salem station Pressurizer heaters is identical to that described in the NUREG 1366 (Improvements to Technical Specifications Surveillance Requirements, published December 1992), and Generic Letter 93-05 (Line-Item Technical Specifications improvements to Reduce Surveillance Requirements for Testing During Power Operation, issued on September 27, 1993), and the extension of the surveillance requirement is a recognized enhancement and assurance to the continued reliability of the pressurizer heaters.
Based upon the above, PSE&G concludes that the proposed changes do not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does not create the possibility of a new or different kind of accident from any accident previously evaluated.
The proposed changes do not introduce any design or physical configuration changes to the facility which could create new accident scenarios.
NLR-N94149 LCR' 93-*28 ATTACHMENT 1
- 3. Does not involve a significant reduction in a margin of safety.
As stated in response to question number 1 above, the request does not change any assumption or parameter assumed to function in any of the design/licensing basis analysis. One change merely relocates a requirement from one section of the LCO to another, and the second change incorporates the recommendations and enhancements as stated in NUREG 1366 and GL 93-05.
Consequently, PSE&G concludes that the change does not involve a significant reduction in any margin of safety.
NLR-N94149 ATTACHMENT 2
,Lc~**93...:*2a Insert A The pressurizer shall be OPERABLE with a water volume of less than or equal to 1650 cubic feet (92%
indicated level), and at least two groups of pressurizer heaters each having a capacity of 150 kw and capable of being powered from an emergency power supply.
Insert B The capacity of each of the above required groups of pressurizer heaters shall be verified by measuring circuit current at least once each refueling outage.