Forwards Insp Repts 50-272/94-13,50-311/94-13 & 50-354/94-11 on 940501-0625.No Violation Noted.Noted That Quality of Operability Determinations at Plant Could Be Improved Through Documentation of Basis for Determinations
ML18100B192
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 07/01/1994
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Miltenberger S
Public Service Enterprise Group
Shared Package
ML18100B193 List:
References
EA-94-112, NUDOCS 9407130024
Download: ML18100B192 (3)


See also: IR 05000272/1994013

Text

,*

Docket Nos. 50-272

50-311

50-354

EA No.94-112

Mr. Steven E. Miltenberger

Vice President and Chief Nuclear Officer

Public Service Electric and Gas Company

P.O. Box 236

Hancocks Bridge, NJ 08038

Dear Mr. Miltenberger:

JUL - I 1994

SUBJECT:

SALEM AND HOPE CREEK RESIDENT INSPECTION NOS. 50-272/94-13;

50-311/94-13; 50-354/94-11

The enclosed report documents an inspection for public health and safety, conducted by Mr.

C. Marschall, Senior Resident Inspector and other members of the NRC resident and

regional staff at the Salem and Hope Creek Nuclear Generating Stations for the period

between May 1, 1994 and June 25, 1994. The inspectors discussed the findings of this

inspection with Messrs. J. Hagan and R. Hovey of your staff.

During the inspection period we noted that you operated the Salem and Hope Creek plants

safely overall. However, we also noted that the quality of operability determinations at

Salem and Hope Creek could be improved through documentation of the basis for the

determinations. Matters pertaining to our followup inspection on issues relative to the

April 7, 1994 trip of Unit 1 are provided for your information. In accordance with 10 CFR

2.790 of the NRC's "Rules of Practice," a copy of this letter and the enclosure will be

placed in the NRC Public Document Room (PDR). No response to this letter is required.

Your cooperation with us is appreciated.

Sincerely,

Edward C. Wenzinger, Chief

Projects Branch No. 2

Division of Reactor Projects

Enclosure: NRC Inspection Report Nos. 50-272/94-13; 50-311/94-13; 50-354/94-11

t

.~. *' 1 r r

....... ~

.;,. ... I...* l.* .... ;J

9407130024 940701

PDR

ADOCK 05000272

Ci

PDR

..

Mr. Steven E. Miltenberger

2

JUL - l 1994

cc w/encl:

S. La.Bruna, Vice President - Engineering and Plant Betterment

J. Hagan, Vice President-Operations/General Manager-Salem Operations

R. Hovey, General Manager - Hope Creek Operations

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

F. Thomson, Manager, Licensing and Regulation

J. Robb, Director, Joint Owner Affairs

A. Tapert, Program Administrator

R. Swanson, General Manager - QA and Nuclear Safety Review

M. Wetterhahn, Esquire

R. Fryling, Jr., Esquire

P. J. Curham, Manager, Joint Generation Department, Atlantic Electric Company

Consumer Advocate, Office of Consumer Advocate

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

K. Abraham, PAO (2)

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

Mr. Steven E. Miltenberger

3

bee w/encl:

Region I Docket Room (with concurrences)

K. Gallagher, DRP

bee w/encl via E-Mail:

J. Stone, NRR

W.Dean,OEDO

C. Miller, PDI-2, NRR

M. Shannon, ILPB

M. Callahan, OCA

D. Holody, EO

E. Kelly, DRS

J. Wiggins, DRS

R. Summers, DRP

C. Marschall, SRI - Salem/Hope Creek

J. White, DRP

E. Wenzinger, DRP

J. Lieberman, OE

~~A_.d

~mg

er

7 I ( 194

OFFICIAL RECORD COPY

A:94131311.SHC