Forwards Insp Repts 50-272/94-02 & 50-311/94-02 on 940124-28 & 0207-10.No Violations Noted
ML18100A972
Person / Time
Site: Salem  PSEG icon.png
Issue date: 03/28/1994
From: Ruland W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Miltenberger S
Public Service Enterprise Group
Shared Package
ML18100A973 List:
References
NUDOCS 9404040014
Download: ML18100A972 (4)


See also: IR 05000272/1994002

Text

Docket Nos. 50-272

50-311

Mr. Steven E. Miltenberger

Vice President and Chief Nuclear Officer

Public Service Electric and Gas Company

P.O. Box 236

Hancocks Bridge, NJ 08038

Dear Mr. Miltenberger:

MAR 2 8 1994

SUBJECT:

NRC REGION I COMBINED INSPECTION REPORT NOS. 50-272/94-02

AND 50-311/94-02

This letter transmits the report of the announced safety inspection conducted by

Mr. L. L. Scholl of this office for the periods of January 24-28 and February 7-10, 1994,. at*

the Salem Nuclear Generating Station located in Hancocks Bridge, New Jersey. The

inspector discussed the findings of this inspection with members of your staff on

February 17, 1994.

,

-

The inspection was directed towards areas important to public health and safety. Areas

examined are*described in the NRC inspection report enclosed with this letter. Within these

areas, the inspection consisted of document reviews and personnel interviews.

The purpose of the inspection was to review the rod control system performance and

associated maintenance and modifications performed following the rod control system

Augmented Inspection Team (AIT) activities of June 1993. Procedure and program

improvements implemented after the rod control system problems were also reviewed.

The inspector found that the rod control systems on Salem Units 1 *and 2 were operating

reliably. Modifications have been performed on Unit 1 during the last refueling outage to

further improve the rod control system reliability. Similar modifications are planned for

Unit 2 during the next refueling outage.

9404040014 940328

PDR

ADDCK 05000272

O

PDR

I

/(:6D'.

I

LY

Public Service Electric

and Gas Company

2

MAR 2 8 1994

The lack of a comprehensive root cause analysis program was a weakness identified by the

AIT. The inspector noted that this weakness was subsequently confirmed during the PSE&G

comprehensive performance assessment team evaluation and that a team has been formed to .

develop a comprehensive root Ca.use analysis program. The NRC acknowledges this effort

and encourages PSE&G management to ensure successful implementation of a rigorous

program.

Your cooperation with us is appreciated. No response to this letter is requested.

Sincerely,

William H. Ruland, Chief

Electrical Section

Engineering Branch

Division of Reactor Safety

Enclosure: NRC Inspection Report Nos. 50-272/94-02 and 50-311/94-02

cc w/encl:

J. J. Hagan, Vice President-Operations/General Manager-Salem Operations

S. La.Bruna, Vice President - Engineering and Plant Betterment

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

R. Hovey, General Manager - Hope Creek Operations

  • F. Thomson, Manager, Licensing and Regulation

R. Swanson, General Manager - QA and Nuclear Safety Review

J. Robb, Director, Joint Owner Affairs

A. Tapert, Program Administrator

R. Fryling, Jr., Esquire

M. Wetterhahn, Esquire

P. J. Curham, Manager, Joint Generation Department,

Atlantic Electric Company

Consumer Advocate, Office of Consumer Advocate

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

K. Abraham, PAO (2)

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

~

4

JL/.

I

bee w/encls:

~ 1 ~

UA.-

Public Service Electric

and Gas Company

2

MAR 2 8 1994

The lack of a comprehensive root cause analysis program was a weakness identified by the

AIT. The inspector noted that this weakness was subsequently confirmed during the PSE&G

  • comprehensive performance assessment team evaluation and that a team has been formed to

develop a comprehensive root cause analysis program. The NRC acknowledges this effort

and encourages PSE&G management to ensure successful implementation of a rigorous

program.

Your cooperation with us is appreciated. No response to this letter is requested.

William H. Ruland, Chief

Electrical Section

Engineering Branch

Division of Reactor Safety

  • *Enclosure: NRC Inspection Report Nos. 50-272/94-02 and 50-311/94-02

cc w/encl:

J. J. Hagan, Vice President-Operations/General Manager-Salem Operations

S. LaBruna, Vice President - Engineering and Plant Betterment

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

R. Hovey, General Manager - Hope Creek Operations

F. Thomson, Manager, Licensing and Regufation

R. Swanson, General Manager - QA and Nuclear Safety Review

J. Robb, Director, Joint Owner Affairs

A. Tapert, Program Administrator

R. Fryling, Jr., Esquire

M. Wetterhahn, Esquire

P. J. Curham, Manager, Joint Generation Department,

Atlantic Electric Company

Consumer Advocate, Office of Consumer Advocate

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

K. Abraham, PAO (2)

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

bee w/encls:

Public Service Electric

and Gas Company

bee w/encls:

Region I Docket Room (with concurrences)

bee w/encls: (via E-Mail)

J. Stone, NRR

S. Dembek, NRR

V. McCree, OEDO

C. Miller, PDI-2, NRR

M. Shannon, ILPB

RI:DRS

Sci>>

31J7194

RI:D~/4 _

R~lo/~

3fJ5'794

3

OFFICIAL RECORD COPY

A:SA940202.INS

MAR 2 8 1994