Text
, ..
Docket No. 50-272
Mr. Steven E. Miltenberger *
Vice President and Chief Nuclear Officer
Public Service Electric and Gas Company
P. 0. Box 236
Hancocks Bridge, New Jersey 08038
Dear Mr. Miltenberger:
- NOV 2 6 1993
SUBJECT: NRC REGION I INSPECTION REPORT NO. 50-272/93-25 *
. This letter transmits the findings of the announced safety inspection, conducted by
Mr. P. Patnaik of this office, from October 25 through October 29, 1993, at the Salem.
Nuclear Generating Station, Unit 1, Hancocks Bridge, New Jersey.
The inspection was directed at areas important to public health and safety, and focused on
reviews of the inservice inspection program, the steam generator eddy current examination.
program, sample data from the erosion/corrosion monitoring of components, and the steam
generator primary- to-secondary leakage monitoring program. The results of this inspection
were discussed with the members of your staff at the exitmeeting on October 29, 1993.
The inspector found the steam generator leakage monitoring program, as implemented, with
procedures for detection of leakage and the operator's actions in the event of a primary-to-
seeondary leak, to be generally effective. Notwithstanding the limits on power reduction
and/or shutdown, the operations procedure, however, does not address appropriate actions
against any step increase in primary-to-secondary leakage below the shutdown margin, as
seen in some of the recent tube failures at other plants.
9312070043 931126 r
ADOCK 05000272
G
PDR ~.
~o(
/
It (
NOV 2 6 1993
. Public Service Electric
2
and Gas Company .
The inservice inspection and the eddy current examination activities were generally planned,
controlled, and documented properly. The erosion/corrosion ~ta indicated proper
implementation of your updated program. No violations were identified during this
inspection, hence, no response to this letter is required.
Sincerely,
~~-f
Jacque P. Durr, Chief
Engineering Branch
Division of Reactor Safety.
Enclosure: NRC Region I Inspection Report No. 50-272/93-25
cc w/encl:
J. J. Hagan, Vice President, Nuclear Operations
C. Schaefer, External Operations - Nuclear, Delmar\\ra Power & Light Co .
. C. Vondra, Geneial Manager -*Salem Operations
R. Hovey, General Manager - Hope Creek Operations
F. Thomson, Manager, Licensing* and Regulation
R. SwanSC>n, General Manager - QA and Nuclear Safety Review
J. Robb, Director, Joiiit Owner Affairs *
A. Tapert, Program Administrator
R. Fryling, Jr., Esquire
M. Wetterhahn, Esquire
P. J. Curham, Manager, Joint Generation Department,
Atlantic Electric Company *
Consumer Advocate, Office of Consumer Advocate
William Conklin, Public Safety Consultant, Lower Alloways Creek Township
K. Abraham, PAO (2)
- Public Document Room (PDR)
Local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector
State of New Jersey
Public Service Electric
and Gas Company
bee w/encl:
3
Region I Docket Room (with concurrences)
bee w/encl: (Via E-Mail)
J. Stone, NRR
S. Dembek, NRR
V. McCree, OEDO
L. Nicholson, Acting PDI-2, NRR
RI: DRS
~k
11/22f93
/
Rl:DRS
Durr
(' //z, ;:,,, J /3 {J .
11/71/93
OFFICIAL RECORD COPY
A:SA19325.INS
J 1993
NOV 2 6 1993