ML18100A603

From kanterella
Jump to navigation Jump to search
Responds to Re Notice of Violations Noted in Insp Repts 50-272/93-08,50-311/93-08 & 50-354/93-06
ML18100A603
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 08/30/1993
From: Cooper R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Miltenberger S
Public Service Enterprise Group
References
NUDOCS 9309150239
Download: ML18100A603 (6)


See also: IR 05000272/1993008

Text

Docket Nos. 50-272

50-311

50-354

Mr. Steven E. Miltenberger

Vice President and Chief Nuclear Officer

Public Service Electric and Gas Company

P.O. Box 236

Hancocks Bridge, NJ 08038

Dear Mr. Miltenberger:

AUG 3 0 199j

SUBJECT:

NOTICE OF VIOLATION CONTAINED IN INSPECTION REPORT NOS.

50-272/93-08, 50-311/93-08,AND 50-354/93-06, SALEM NUCLEAR

GENERATING STATION, UNITS 1 AND 2, AND HOPE CREEK

GENERATING STATION

This responds to your letter of June 7, 1993, which was written in response to the Notice of

Violation (NOV) contained in the subject combined inspection report. This NOV cited a

failure to properly implement the requirements of 10 CPR 50.59 (b) (1). In your letter you

stated that you did not dispute that a violation occurred; but you disagreed with two of the

three examples cited i~ the NOV.

The staff has reviewed your response to the NOV concerning the two cited examples of not

providing a written safety evaluation that you claim were in compliance with industry

guidance, plant specific guidance, and lOCFR 50.59 requirements. The staff disagrees with

your assertion that these two instances are. not examples of the violation, as described below.

Hope Creek. Use-as-is Disposition for Unqualified Gauges:

If a proposed change, test, or experiment changes the facility as described in the UFSAR,

then a 10 CPR 50.59 safety evaluation (i.e., an unreviewed safety question determination) is

required. In this particular case, UFSAR Figure 6.3-2 depicts the gauges in question as

being "Q" gauges (i.e., the gauges are clearly shown within the "Q" boundary and the root

valves to the gauges are clearly shown as being normally open). The proposed change to the

facility (i.e., allowing the use of non-qualified gauges instead of the qualified gauges and

placing the root valves in a normally closed position) did change the facility as described in

the UFSAR and therefore, did require a 10 CFR 50.59 safety evaluation.

As noted in the inspection report, the safety significance of this particular issue is minor.

The violation states that the UFSAR describes the gauges as being safety related and that the

root valves for the gauges as being normally open. The issue is the UFSAR description, not

.

.

141123

9309150239 930830

1~~

PDR

. ADOCK 05000272 11:"

0

PDR

~-.

~l

1

1

AIH~ 3 0 1993

Public Service Electric and Gas Company

2

the actual qualification of the gauges. The inspector was presented with enough information

during the inspection to determine that the gauges were not actually safety related.

However, your 10 CFR 50.59 applieability review should have-reviewed UFSAR Figure 6.3-

2 and should have noted that the figure describes the gauges as being safety related and

subsequently resolved the apparent error. Further, your original 10 CFR 50.59 applicability

review should have referenced UFSAR Table 3.2-1, since this table provides the

classification of the structures, systems and components at Hope Creek. Accordingly, we

believe that the original 10 CFR 50.59 applicability review was not performed satisfactorily.

In this case, the figure that depicts the system, and the table that provides the classification

for the components in question, were not referenced and were not addressed in the 10 CFR

50.59 applicability review to validate the correct configuration and description.

Salem Unit 2. Temporary Modification CT-MOD) TMR 92-043:

In your response, you state that the installation of the blank flange in the service water

system was a maintenance activity. Maintenance, as defined in PSE&G Administrative

Procedure NC.NA-AP.ZZ-0059, Rev. 0, (NAP-59) "(c)onsists of activities to prevent or

correct the malfu.nction of a structure, system, or component (SSC) which involves no design

or configuration change (i.e., the SSC must be returned to its original condition or

con.figuration). Maintenance includes calibration, refurbishment, exact replacement-in-kind,

and housekeeping." The maintenance work was performed on the 22 SW return header, not

the flange in question. Therefore, it is the staffs position that this was not a maintenance

activity, but an activity required to support a maintenance activity. It should be noted that.if

the interpretation of maintenance, as stated by PSE&G in the June 7, 1993 letter, is correct,

then the installation of temporary power in T-MOD TMR 92-031 would also be a

maintenance activity. In that case you have already agreed that it should have had a 50.59

safety evaluation.

Changes, as defined in NAP-59, Section 6.2, "(a) re modifications that affect the design,

function or method of peiforming the function of a structure, system or component described

in the SAR." In addition, NAP-59, Section 6.2.1 states "(c)hanges include the following:

Temporary design changes (i.e., jumpers, lifted leads, disconnected piping/tubing;

installation or removal of components and appunenances, temporary lead shielding on pipes

and equipment, temporary blocks and bypasses, temporary suppons, and equipment used on

a temporary basis)." In this case the isolation function was changed by the temporary

installation of a blank flange. Accordingly, the staff concludes that the temporary installation

of the blank flange was a change to the facility as described in the UFSAR and should have

undergone a safety evaluation as required by lOCFR 50.59 .

. --- _:-I

AUG 3 0 1993

Public Service,Electric and Gas Company

3

Based on the above, the staff determined that the "use-as-is" disposition for the installation of

unqualified gauges at Hope Creek, and the installation of the blank flange in the service

- water system at Salem 2 are valid examples of failure to properly implement the

requirements of lOCFR 50.59 (b) (1).

Accordingly, your corrective actions, as stated in the response to the NOV, may not be

sufficient. Please review the actions you have taken to date and determine if additional

modifications to your program are appropriate, and inform this office accordingly, 'within

thirty days of the date of this letter.

You a.Te required to respond to this letter and should follow the instructions specified in the

Notice enclosed with the subject inspection report when preparing your response. In your

response, you should document the specific actions taken and any additional actions you plan

to prevent recurrence. After reviewing your revised response, including your proposed

corrective actions and the results of future inspections, the NRC will determine whether

further NRC enforcement action is necessary to ensure compliance with NRC regulatory

requirements.

-In accordance with 10 CFR 2. 790 of the NRC's "Rules of Practice," a copy of this letter and

its enclosures will be placed in the NRC Public Document Room.

The response directed by this letter and the enclosed Notice are not subject to the clearance

-procedures of the Office of Management and Budget as required by the Paperwork reduction

Act of 1980, Public Law No. 96.511.

~

Your cooperation with us is appreciated.

Sincerely,

Original Signed By:

/IJ¥!_ I~ P-,

Richard W. Cooper, II, Director

_ Division of Reactor Projects

A ur, 3 (} 19!:t3

Public Service Electric and Gas Company

4

cc:

J. Hagan, Vice President - Nuclear Operations

C. Vondra, General Manager, Salem Operations

R. Hovey, General Manager, Hope Creek Operations

F. Thomson, Manager, Licensing and Regulation

J. Robb, Director, Joint Owner Affairs

A. Tapert, Program Administrator

R. Swanson, General Manager, Quality Assurance and Nuclear Safety Review

cc w/cy of Licensee's Letter:

C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.

  • M. Wetterhahn, Esquire

R. Fryling, Jr., Esquire

P. J. Curham, Manager, Joint Generation Department, Atlantic Electric Company

Consumer Advocate, Office of Consumer Advocate

Lower Alloways Creek Township

William Conklin, Public Safety Consultant, Lower Alloways Creek Township

K. Abraham, Public Affairs Officer

Public Document Room (PDR)

~al Public. Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

)*

I ,

.

.; ***

""AUG 3- 0 1993

Public Service Electric and Gas Company

bee w/cy of Licensee's Letter:

Region I Docket Room (with concurrences)

E. Wenzinger, DRP .

J. White, DRP

J. Stone, NRR

S. Dembek, NRR

M. Boyle, PDI-2D, NRR

D. Holody, ORA

~1~~~ -

~:~

~er

t

EWenzinger ~

5

8!,({!J3

8~93

8f/f 93

OFFICIAL RECORD COPY

g:letter.sal

f,

'

'

Public Service Electric and Gas Company

5

bee w/cy of Licensee's Letter:

Region I Docket Room (with concurrences)

, E. Wenzinger, DRP

J. White, DRP

J. Stone, NRR

S. Dembek, NRR

M. Boyle, PDI-2D, NRR

D. Holody, ORA

  • RJ:DRP
  • RI:DRP'

JWhite

EWenzinger

8/ /93

8/ /93

RI: ORA

R~

r1il

DHo1ody

R oo r

8~&'93

8!'f{'J93

OFFICIAL RECORD COPY

  • See Prev_ious Concurrence Page

g:letter.sal