May 13, 1992 Docket Nos. 50-272, 50-31.

. and 50-354 LICENSEE:

Public Service Electric and Gas Company FACILITY:

Salem Nuclear Generating Station, Units 1 and 2, and Hope Creek Generating Station

SUBJECT:

SUMMARY

OF MEETING WITH PUBLIC SERVICE ELECTRIC AND GAS COMPANY (PSE&G) ON MAY 6, 1992, REGARDING CURRENT LICENSING ISSUES A meeting was held at the NRC offices in Rockville, Maryland, on May 6, 1992, to discuss current licensing issues and to discuss the NRC's concerns with PSE&G's responses to generic issues as noted in the latest Salem and Hope Creek SALP reports.

The licensee discussed responses to generic issues that were mentioned in the NRC's SALP report.

The licensee's discussion included their perception of the problems with their generic issue responses and their plan to address the staff's concerns.

The corrective actions to be taken by the licensee include having the licensing department involved earlier in the generic issue response process.

Additionally, the licensee stated that they will quickly propose meetings to resolve technical differences or to clarify the NRC's questions.

The licensee will also improve their project planning, monitoring and control processes.

The NRC staff members attending the meeting felt that the licensee fully understood the concerns raised by the NRC and that the licensee's actions should improve their future responses to generic issues.

Additionally, the status of amendment requests that had been submitted for NRC approval was discussed for both Salem and Hope Creek.

Several amendment requests being developed by PSE&G were also discussed.

Enclosure:

List of Attendees cc w/enclosure:

See next page DISTRIBUTION w/enclosure:

0ocket File NRC & Local PDRs PDI-2 Reading TMurl ey /FMi ragl i a, 12Gl8 JPartlow, 12Gl8 SVarga JCalvo CMiller SDembek OFFICE NAME

/SI Stephen Dembek, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation JStone MO'Brien(2)

OGC EJordan, 3701 TJohnson, RGN-I ACRS (10)

RLobel, EDO l?G-21 EWenzinger, RGN-I JWhite, RGN-I

~DA~TE~~~r/~9~2~~S--~/~/~//_9_2___._~S~;~~~/_92~.i---J~/,~J~;_f_v__._~~~---' (\\Lo\\

OFFICIAL - COR COPY

~1

____ FJLENAM~_: A:\\MTG.SUM

\\\\\\

92os2ooos9-9205i 3-~~~

\\

~DR ADOCK 05000272 PDR

Docket Nos. 50-272, 50-311 and 50-354 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 May 13, 1992 LICENSEE:

Public Service Electric and Gas Company FACILITY:

Salem Nuclear Generating Station, Units 1 and 2, and Hope Creek Generating Station

SUBJECT:

SUMMARY

OF MEETING WITH PUBLIC SERVICE ELECTRIC AND GAS COMPANY (PSE&G) ON MAY 6, 1992, REGARDING CURRENT LICENSING ISSUES A meeting was held at the NRC offices in Rockville, Maryland, on May 6, 1992, to discuss current licensing issues and to discuss the NRC's concerns with PSE&G's responses to generic issues as noted in the latest Salem and Hope Creek SALP reports.

The licensee discussed responses to generic issues that were mentioned in the NRC's SALP report.

The licensee's discussion included their perception of the problems with their generic issue responses and their plan to address the staff's concerns.

The corrective actions to be taken by the licensee include having the licensing department involved earlier in the generic issue response process. Additionally, the licensee stated that they will quickly propose meetings to resolve technical differences or to clarify the NRC's questions.

The licensee will also improve their project planning, monitoring and control processes.

The NRC staff members attending the meeting felt that the licensee fully understood the concerns raised by the NRC and that the licensee's actions should improve their future responses to generic issues.

Additionally, the status of amendment requests that had been submitted for NRC approval was discussed for both Salem and Hope Creek.

Several amendment requests being developed by PSE&G were also discussed.

Enclosure:

List of Attendees cc w/enclosure:

See next page

~~/UL Stephen Dembek, Project Manager Project Directorate 1-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

LIST OF ATTENDEES C. Miller, Director, PDI-2, NRR J. Stone, Salem PM, PDI-2, NRR S. Dembek, Hope Creek PM, PDI-2, NRR T. Johnson, Senior Resident Inspector, Region I F. Thomson, Manager-Licensing, PSE&G ENCLOSURE R. Brown, Principal Engineer-Licensing and Regulation, PSE&G S. Singh, Nuclear Engineer, State of N.J. Department of Environmental Protection

Public Service Electric & Gas Company cc:

Mark J. Wetterhahn, Esquire Winston & Strawn 1400 L Street NW Washington, DC 20005-3502 Richard Fryling, Jr., Esquire Law Department - Tower 5E 80 Park Place Newark, NJ 07101 Mr. Calvin A. Vondra General Manager - Salem Operations Salem Generating Station P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. S. LaBruna Vice President - Nuclear Operations Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. Thomas P. Johnson, Senior Resident Inspector Salem Generating Station U.S. Nuclear Regulatory Commission Drawer I Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection CN 415 Trenton, NJ 08625-0415 Maryland People's Counsel American Building, 9th Floor 231 East Baltimore Street Baltimore, Maryland 21202 Mr. J. T. Robb, Director Joint Owners Affairs Philadelphia Electric Company 955 Chesterbrook Blvd., 51A-13 Wayne, PA 19087 Salem Nuclear Generating Station, Units 1 and 2, and Hope Creek Generating Station Richard Hartung Electric Service Evaluation Board of Regulatory Commissioners 2 Gateway Center, Tenth Floor Newark, NJ 07102 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Lower Alloways Creek Township c/o Mary 0. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Mr. Frank X. Thomson, Jr., Manager Licensing and Regulation Nuclear Department P.O. Box 236 IL:incocks Bridge, NJ 08038 Mr. David Wersan Assistant Consumer Advocate Office of Consumer Advocate 1425 Strawberry Square Harrisburg, PA 17120 Mr. J. A. Isabella MGR. - Generation Department Atlantic Electric Company P.O. Box 1500 1199 Black Horse Pike Pleasantville, NJ 08232 Carl D. Schaefer External Operations - Nuclear Delmarva Power & Light Company P.O. Box 231 Wilmington, DE 19899 Public Service Commission of Maryland Engineering Division ATTN:

Chief Engineer 231 E. Baltimore Street Baltimore, MD 21202-3486

IA

,1*

P' Public Service Electric & Gas Company cc:

Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 241 Hancocks Bridge, New Jersey 08038 Mr. J. J. Hagan General Manager - Hope Creek Operations Hope Creek Generating Station P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, New Jersey 08038