ML18092B363

From kanterella
Jump to navigation Jump to search
Insp Repts 50-272/86-23 & 50-311/86-23 on 860811-15.Major Areas Inspected:Implementation of Program for Establishing & Maintaining Qualification of Electric Equipment Consistent w/10CFR50.49.Potential Enforcement/Unresolved Items Noted
ML18092B363
Person / Time
Site: Salem  
Issue date: 11/17/1986
From: Hubbard G, Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML18092B362 List:
References
RTR-NUREG-0588, RTR-NUREG-588 50-272-86-23, 50-311-86-23, IEIN-84-44, NUDOCS 8612010033
Download: ML18092B363 (17)


See also: IR 05000272/1986023

Text

Report Nos:

Docket Nos:

License Nos:

Licensee:

Facility Name:

Inspection At:

Inspection Conducted:

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

50-272/86-23; 50-311/86-23

50-272/311

DPR-70, DPR-75

Public Service Electric and Gas Company

80 Park Place

Newark, New Jersey

07101

Salem Generating Station, Units 1 and 2

Lower Alloways Creek, New Jersey

August 11-15, 1986

Inspector: ~};}--=_* . ....,..,/__,._Jj_A.A.-'~~~.--___,..-=-......,....,.....,,...,..--.--=--==-----=---.-

G. T. Hubbard, Equipment Qualification & Test Engineer 'illff

ate

Also participating in the inspection and contributing to the report were:

L. Cheung, Reactor Engineer, RI

  • R. Paolino, Lead Reactor Engineer, RI

J. W. Grossman, Member of Technical Staff, Sandia National Laboratories

M. Trojovsky, Engineer, ldaho National Engineering Laboratory (INEL)

D. E. Jackson, Senior Engineer, INEL

Approved by:

8612010033 861113

\\

  • SDR

ADOCK 05000272

PDR

INSPECTION SUMMARY

Inspection on August 11-15, 1986 (Inspection Report Nos:

50-272/86-23;50-311/86-23)

Areas Inspected: Announced inspection to review the licensee's implementation of

a program for establishing and maintaining the qualification of electric equip-

ment within the scope of 10 CFR 50.49.

Results: The inspection determined that the licensee has implemented a program

to meet the requirements of 10 CFR 50.49, except for certain deficiencies listed

below.

Report

Name

Paragraph

Item Number(s)

Potential Enforcement/Unresolved Items:

1.

Qualification of Rockbestos Coaxial

4.0.(2)

50-272/86-23-03;

and EPR Cables

50-311/86-23-03

2.

Qualification of Scotch 70/

4.E.(l)

50-272/86-23-09;

Construction Splices

50-311/86-23-09

3.

Qualification of Inside Containment

4.0(3)

50-272/86-23-04;

Limitorque Operators without Gear

50-311/86-23-04

Case Grease Relief Valves

4.

Qualified Life of Components in

4.0(4)

50-272/86-23-05;

Exo Sensors Hydrogen Analyzers

50-311/86-23-05

5.

Post-Accident Operating Times for

4.0.(5)

50-272/86-23-06;

ASCO Solenoid Valves

50-311/86-23-06

6.

Engineering EQ Training

4.A.

50-272/86-23-01;

50-311/86-23-01

7.

Mounting of Rosemount Transmitters

4.E.(2)

50-311/86-23-10

Open Items:

1.

Completion of EQMLs

4.C.

50-272/86-23-02;

50-311/86-23-02

2.

BIW Coaxial Cable File Additions

4.0.(6)

50~272/86-23-07;

50-311/86-23-07

3.

Conax ECSA File Additions

4.D.(7)

50-272/86-23-08;

50-311/86-23-08

'**

1.

DETAILS

PERSONS CONTACTED

1.1 Public Service Electric and Gas Company (PSE&G)

  • C. McNeill, Vice President-Nuclear
  • L. Reiter, General Manager-Licensing and Reliability

J. T. Boettger, Assistant Vice President

  • J. N. Leech, Principal Engineer-Licensing
  • D. J. Vito, Senior Engineer-Licensing
  • G. R. Sayer, Group Head-Engineering Core Group
  • W. N. Macintyre, Quality Assurance (QA) Core Group

W. R. Meyer, Principal Training Supervisor

R. V. Watson, Chemistry Supervisor

  • E. B. Robinson, Instrument and Controls (I&C) Training Supervisor
  • K. M. 0

1Gara, Licensing Engineer

R. S. Patwell, Senior Staff Engineer-Licensing

D. K. Strong, Maintenance Engineer

C. W. Lambert, Principle Engineer

  • R. A. Burricelli, General Manager-Engineering and Plant Betterment

P. White, Maintenance Manager

  • B. A. Preston, Manager-Licensing and Regulation
  • D. A. Perkins, Manager Station QA
  • M. Levine, Technical Audit Team Leader

R. Edmonds, Assistant Manager Nuclear Training

J. H. MacKinnon, General Manager-Nuclear Safety Review

  • R. L. Gura, Manager-Engineering
  • B. G. Horst, Engineer

R. B. Donges, Licensing Engineer

  • J.M. Zupko, Jr., General Manager-Salem Operations
  • E. A. Liden, Manager-Offsite Safety Review
  • D. J. Jagt, Assistant General Manager-Project Engineering
  • L. Salamon, Public Information Representative-Nuclear
  • C. W. Hambert, Principal Engineer
  • R. Antonow, Senior Engineer-Salem Maintenance
  • M. J. Shaeffer, On-site Safety Review
  • V. Getsinger, Senior Maintenance Supervisor

R. VanderDecker, Senior Engineer, Engineering Planning Department

A. Osborne, Group Leader, Method and Assurance

C. Gregory, I&C Supervisor

F. Mekulsia, Senior Supervisor, I&C

1.2 PSE&G Contractors

  • M. J. Cavalier, Site Representative, Atlantic City Electric Company

1.3

NRC

  • U. Potapovs, Chief, Equipment Qualification Inspection Section
  • J. P. Durr, Chief, Engineering Branch, Region I
  • L. J. Nurrholm, Chief, Reactor Projects Section, Region I
  • T. J. Kenny, Senior Resident Inspector
  • K. H. Gibson, Resident Inspector
  • Denotes those present at exit meeting

2.

PURPOSE

The purpose of this inspection was to review the licensee's implementation

of a program meeting the requirements of 10 CFR 50.49 for Salem Nuclear

Generating Station, Units 1 and 2.

3.

BACKGROUND

The NRC held a meeting with PSE&G on April 24, 1984, to discuss the licen-

see 1 s proposed methods to resolve the deficiencies identified in the Unit 1

Safety Evaluation Report (SER) dated January 21, 1983, and Franklin Research

Center (FRC) Technical Evaluation Report (TER) dated July 15, 1982, and the

Unit 2 SER dated January 19, 1983, and FRC TER dated July 15, 1982.

Discus-

sions also included PSE&G's general methodology for compliance with 10 CFR

Part 50.49 and Justification* for Continued Operation (JCO) for those equip-

ment items for which environmental qualification was not completed.

Minutes

of the meeting and proposed methods of resolution for each of the EQ defi-

ciencies were documented in the licensee submittal June 8, 1984.

Final EQ

SERs were issued for Unit 1 on December 5, 1984, and for Unit 2 on

January 14, 1985.

On May 8, 1986, PSE&G submitted Licensee Event Report (LER) number

86-007-00 to the NRC concerning problems with their compliance with 10 CFR

50.49.

The LER stated that during.a "self initiated walkdown inspection

of environmentally qualified equipment for Unit 1 during the refueling out-

age which started on March 22, 1986, it was discovered that eleven inside

containment Limitorque motor valve operators were not in full compliance

with 10 CFR 50.49 requirements due to T-drains not being installed in

operator motor housings.

Additionally the LER documented for Unit 1, that

12 solenoid operated valves did not have required Conax seal assemblies,

7 junction boxes were not properly sealed, and 4 Limitorque motor valve

operators (located outside containment) had brakes still installed. The

LER stated that although the brakes had been electrically disconnected,

the brake assemblies had not been physically removed from the valve

operators.

As a result of the Unit 1 findings, an inspection of Unit 2 was started on

May 1, 1986.

Based on the initial findings of this inspection, PSE&G

shutdown Unit 2 on May 1, 1986, to correct qualification deficiencies

similar to the ones discussed above for Unit 1. Additionally, it was

determined from reviews of junction box documentation for Units 1 and 2

that flow transmitter connections were made with terminal blocks rather

than required splices. The LER stated that corrective action for all

identified deficiencies for both units was completed by May 6, 1986.

On August 6, 1986, PSE&G notified the NRC that as of 6:30 PM that day

both Units 1 and 2 were being shutdown due to questionable environmental

qualification of Limitorque motor valve operators.

The licensee shut

both units down because physical inspections of selected operators

determined that qualification of internal jumper wires in the operators

could not be established. PSE&G replaced the jumper wires in their

2

qualified operators with qualified Rockbestos Firewall III SIS wire

following the shutdowns.

Both units were back in operation prior to the

end of the inspection.

On August 7, 1986, PSE&G submitted LER 86-015-00 to the NRC documenting

that during their review and evaluation of Information Notice (IN) 86-53

they determined that Raychem splices in Unit 1 had not been installed in

accordance with Raychem instructions. Unit 2 Raychem splices were

determined to be in accordance with Raychem instructions. Based on this

determination PSE&G performed an analysis of their splice installation

and determined that affected equipment was operable. Futhermore, they

obtained qualification test data from Wyle Laboratories which supported

qualification of their splice installations. This data was reviewed by

the NRC inspectors during the inspection.

4.

FINDINGS

The NRC inspectors examined the licensee

1 s program for establishing the

qualification of electric equipment within the scope of 10 CFR 50.49.

The program was evaluated by examination of the licensee

1s qualification

documentation files, review of procedures for controlling the licensee

1 s

EQ efforts, verification of the adequacy and accuracy of the licensee

1s

10 CFR 50.49 equipment list, and examination of the licensee

1s program

for maintaining the qualified status of the covered electric equipment.

Based on the inspection findings, which are discussed in more details

below, the inspection team determined that the licensee has implemented

a program to meet the requirements of 10 CFR 50.49, although some

deficiencies were identified.

A.

EQ Program Requirements

The NRC inspectors examined the implementation and adequacy of the

licensee

1 s EQ program for establishing and maintaining the environ-

mental qualification of electrical equipment in compliance with the

requirements of 10 CFR 50.49.

The licensee

1s program for establishing

and maintaining qualification of electric equipment within the scope

of 10 CFR 50.49 is defined in the following procedures.

GM8-EMP-022, "Environmental Qualification of Safety Related

Electrical Equipment for Salem Generating Station," Revision 1,

dated February 12, 1986

GM8-EMP-Oll,

11 I tern Classification Guidelines,

11 Revision 0, dated

March 1, 1985

GM8-EMP-010,

11 Safety Evaluations and Field Directives,

11

Revision 1, March 1, 1985

GM8-EMP-013,

11Material Order/Item Classification Processing,

11

Revision 0, dated February 7, 1985

3

GMB-EMP-019, "Engineering Evaluation, Revision 0, dated

April 16, 1985

GMB-EMP-009, "Operational Design Change Control, Revision 0,

dated December 2, 1985

The licensee's qualification program, which was incorporated into the

licensee's existing procedures when the program was established, is

defined in Procedure GMB-EMP-022. This procedure defines the require-

ments for establishing the Equipment Qualification Master List (EQML)

and ensuring that all equipment on the list is qualified. This

procedure together with the listed procedures and other procedures

discussed in this report ensure that qualification of equipment is

documented, equipment is installed and maintained in accordance with

qualification documentation, EQ is considered when plant modifications

are made such as installation of new or replacement equipment, and

personnel are trained in the requirements of EQ.

The NRC inspectors' review of the licensee's procurement activities

for qualified equipment determined that the system sponsor engineer

is responsible for determining appropriate environmental qualification

requirements for procurement.

He utilizes the EQML, which contains

information such as purchase order number, plant location, design

change control numbers, and other identifying information for each

piece of qualified equipment, in determining appropriate requirements.

For new equipment, the discipline design change sponsor is responsible

for determining the need for equipment to be environmentally qualified

based on function and location. These requirements are identified in

the procurement specification and added to the EQML. Procedure GM8-

EMP-022 requires that the Systems Analysis Group (SAG) review all

changes for concurrence with the sponsor's environmental qualification

classifications.

Procedure M27-P-235 describes the responsibilities and requirments for

ordering spare parts and general inventory items.

The Nuclear Quality

Assurance (NQA) Group reviews final equipment classification in

accordance with procedure GM9-QAP-3-1 and updates purchase requisiticr.s

with appropriate QA codes.

Procedure GM9-QAP-3-l.l, revision 1,

describes the process implemented by NQA to verify item classifications

established by Nuclear Engineering.

The inspectors' review of the implementation of the licensee's train-

ing program determined that 44 plant craftsmen and 14 plant quality

control inspectors performing EQ maintenance and inspection activities

had recieved training in EQ.

While the inspectors determined through

review of plant training records and observation of one training

$ession that plant personnel were receiving EQ training, the inspectors

determined that the licensee had no evidence that personnel in SAG had

received any dedicated EQ training (such as 10 CFR 50.49, NUREGs,

Regulatory Guides, and IEEE Standards). Since SAG personnel are

4

responsible for reviewing and evaluating EQ test reports, preparing

and approving qualification documentation, and preparing and approving

all EQ related field directives, training for these personnel is

essential.

This finding is considered to be significant since the inspectors

identified the use of several qualification techniques without proper

  • justification. An example of this was the referencing of the 10

degree C rule

11 for thermal evaluations in many qualification files

without justification that use of this methodology was more conserva-

tive than Arrhenius analysis techniques.

The inspectors also deter-

mined that an outside audit report of the Salem EQ program, dated

February 7, 1986, questioned references to the

11 10 degree C rule"

without proper justification; however, this rule was still referenced

in some files during the audit. Additionally, the licensee used

thermal equivalancies under time-temperature profiles to justify

differencies of 50 degrees Fahrenheit (F) between peak test temper-

atures and plant design basis accident temperatures.

While the licensee was able to establish qualification, after question-

ing by the inspectors, based on qualification methods acceptable to

the NRC, the use of the original techniques to establish equipment

qualification indicates that training would have been appropriate.

The

licensee stated that training-on procedure GM8-EMP-022 was scheduled

for SAG personnel on Tuesday August 19, 1986, as part of their normal

engineering training.

Appendix 3A of the Salem Updated FSAR, Revision 1, dated July 22,

1983, cormnits to compliance with Regulatory Guide 1.33, Revision 2,

dated 1978, which endorses ANSI Nl8.7-1976.

ANSI N18.7-1976 requires

that provisions be made for training of personnel performing activities

affecting quality to assure that suitable proficiency is achieved and

maintained.

The licensee's failure to have documentation, during the

inspection, of EQ training for SAG personnel is identified as a

Potential Enforcement/Unresolved Item (50-272/86-23-01; 50-311/

86-23-01).

B.

EQ Maintenance Program

The NRC inspectors reviewed the licensee's provisions for preserving

the qualified status of equipment qualified to 10 CFR 50.49.

The

licensee identifies maintenance requirements for qualified equipment

in field directives and lists the appropriate field directive for each

equipment item on the EQML.

The field directives are written for each

type of equipment in accordance with GM8-EMP-010. The following field

directives were reviewed by the inspectors to ensure that they were

consistent with applicable qualification documentation.

S-C-A910-NFD-092, "Maintenance Requirements for Environmentally

qualified Namco Limit Switches, Model EA-180," Revision 5, dated

September 26, 1985

5

L

S-C-A910-NFD-100, "Maintenance of Rosemount 1153 Seri es D

Pressure Transmitters Requiring Environmental Qualification,"

Revision 2, dated June 6, 1985

S-C-A910-CFD-0327, "Maintenance Requirements for Environmentally

Qualified RDF Corporation Bypass Loop Narrow Range RTD

1s,

11

Revision 0, dated July 29, 1985

S-C-A910-NFD-0335, "Maintenance Requirements to Ensure the

Continued Environmental Qualification of the Target Rock Solenoid

Operated Valves," Revision 0, dated October 2, 1985

S-C-A910-CFD-306, "Maintenance Procedures for Environmentally

Qualified ASCO NP-Series Solenoid Valves," Revision 3, dated

March 12, 1986

S-C-A910-CFD-0328, "Maintenance Requirements for Maintaining the

Environmental Qualification of the Exe-Sensors Hydrogen

Analyzer," Revision 0, dated July 29, 1985

The NRC review determined that once field directives are written

by SAG, the directives are transmitted to the station response

coordinator.

The station response coordinator then reviews the

directives and incorporates the specific maintenance requirements

into the "Maintenance Tracking System (computer program)." Station

EQ maintenance procedures are then written by the field I&C and

electrical engineers, reviewed by station qualified reviewers,

and approved by appropriate maintenance managers.

In addition to the field directives reviewed above, the following

station maintenance procedures were reviewed to ensure that they

contained maintenance information consistent with applicable

field directives and sufficient for the craftsmen to perform the

required maintenance activities.

IC-14.1.013,

11Maintenance of Environmentally qualified Limit

Switches (EA-180),

11 Revision 2, dated July 2, 1986

IC-14.1.021,

11Maintenance of Environmentally Qualified Solenoid

Valves,

11 Revision 1, dated August 6, 1986

IC-14.1.019,

11Maintenance of Environmentally Qualified

Transmitters, Revision 1, dated August 8, 1986

Prior to due dates of the maintenance activities (scheduled by the

computerized maintenance tracking system), senior instrumentation and

control (I&C) supervisors issue work orders to appropriate I&C super-

visors, who direct craftsmen in completion of the specified maintenance

activities. The inspectors review of work orders 86-03-31-075-1,

dated March 31, 1986 and 86-06-19-039, dated June 19, 1986 determined

that the activities were properly performed and appropriate hold

points were identified for quality control inspection and supervisor

approval.

6

The inspectors' review of the licensee's maintenance activities

identified no deficiencies in the areas reviewed.

C.

10 CFR 50.49 List (EQ Mast~r List)

The licensee is required to establish and maintain an up-to date list

of the equipment that must be qualified under 10 CFR 50.49.

At Salem

Units 1 & 2, an extensive review of electrical equipment was performed

by the licensee to determine the equipment required to be qualified

and included on the master list. The criteria used for determining the

electric equipment requiring qualification included the identification

of Class lE equipment required to function to mitigate the consequences

of design basis events, and which must operate in harsh environments.

This included devices required for the initiation of automatic protec-

tive functions as well as those required for post-accident recovery

actions.

In addition, equipment located in areas subject to harsh

environments and not required to perform a safety function, but whose

failure or misoperation could cause a degradation of required safety

equipment was considered.

Many of the items in this category were

control systems for normal plant operation that had been assumed to

remain "as is for various accident scenarios. Devices or components

that provide operator information or indication required for operator

action was also included on the master list. All electrical and

control equipment which was required to mitigate the consequences of

an accident and which is not located in the control room was identified.

The data generated by the high energy line break analysis and docu-

mented in equipment qualification record (EQR) No. 1 was utilized to

identify equipment which would be subject to elevated temperatures

and pressures due to a line break. Calculations were performed to

determine radiation doses within the plant following a design basis

ac.ci dent.

At Salem the SAG is responsible for establishing, maintaining, coor-

dinating, and controlling the EQ program to ensure compliance with

10 CFR 50.49. These activities include maintaining the 10 CFR 50.49

list or EQML, as it is known at Salem.

Changes to the EQML occur when a design change request (DCR) is

prepared for implementation.

The EQ sponsor is responsible for

reviewing the OCR and its impact on the environmental profiles and

the EQ program.

If necessary, the EQ sponsor will issue an opera-

tional design change notice (ODCN) which is included in the DCR for

update of the EQML.

The NRC inspectors performed an audit of the EQMLs to determine their

validity.

To determine the validity of the lists, the inspectors

reviewed 25 items of equipment to determine whether they should be

on the lists. The 25 items consisted of 5 ASCO solenoid valves, 9

Rosemount transmitters, 4 Westinghouse motors, 4 Namco limit switches,

2 Victoreen radiation detectors, and 1 RDF resistance temperature

detector. The licensee was able to either show that the selected

equipment was on the appropriate EQMLs or justify its exclusion by

using applicable piping and instrumentation drawings, equipment lists,

and the qualification files.

7

At the time of the inspection, the licensee had performed a walkdown

verification of the Unit 1 EQML in accordance with section five of

field directive S-C-A910-NFD-0356, Revision 0. Results of the walkdown

had not been included in the latest revision of EQML at the time of

the inspection. The Unit 2 walkdown and equipment verification of the

EQML had not been performed and was scheduled during the next outage,

October 1986. Licensee verification and completion of the EQMLs for

Units 1 & 2 is identified as an Open Item (50-272/86-23-02; 50-311/

86-23-02) which will be reviewed during a future NRC inspection.

The NRC inspectors' evaluations of the EQMLs identified only the open

item discussed above; however, during the plant physical inspection,

the inspectors identified cable splices in Limitorque operators which

were not on the EQMLs. Additional information on this deficiency is

discussed in paragraph 4.E.(1).

0.

Environmental Qualification Files

The files were examined to verify the qualified status of equipment

within the scope of 10 CFR 50.49. In addition to comparing plant

service conditions with qualification test conditions and verifying

the bases for these conditions, the inspectors selectively reviewed

areas such as required post-accident operating time compared to the

duration of time the equipment has been demonstrated to be qualified;

similarity of tested equipment to that installed in the plant (e.g.,

insulation class, materials of components of the equipment, tested

configuration compared to installed configuration, and documentation

of both); evaluation of adequacy of test conditions; aging calculations

for qualified life and replacement interval determination; effects of

decreases in insulation resistance on equipment performance; adequacy

of demonstrated equipment accuracy; evaluation of test anomalies; and

applicability of EQ problems reported in IE INs/Bulletins and their

resolution.

The inspectors reviewed 20 qualification files associated with 20 equip-

ment items for both Units 1 & 2.

At Salem, the qualification files

for each equipment item support qualification of the equipment for

use in either unit. An equipment item is defined as a specific type G'

electric equipment, designated by manufacturer and model, which is

representative of all identical equipment in a plant area exposed to

the same environmental service conditions.

(1)

The inspectors' review of the qualification files determined, fer

the files reviewed, that the files supported qualification, except

as discussed in this report.

However, the inspectors had diffi-

culty in following some of the licensee's evaluations and con-

clusions as documented in the files. While the licensee was

able to clarify his positions and establish qualification in the

8

files, the difficulties encountered by the inspectors in

reviewing the files resulted in the inspectors recommending

to the licensee that the following file improvements be made.

(a)

Revise the qualification files or provide other controlled

qualification documentation that clearly reflects the level

of qualification (e.g. NUREG-0588 Category I or II) of the

equipment being qualified. Initially, the inspectors could

not determine the level of qualification; however, the

licensee finally provided a list of the equipment which

was considered qualified to NUREG-0588 Category I. The

inspectors were told that all other equipment was considered

qualified to NUREG Category II.

When this information was

provided, the inspectors identified problems with regard to

the level of qualification for the cables connected to

Victoreen radiation detectors and Exe-Sensors hydrogen

analyzers.

Even though the licensee was able to resolve

the problems, they might have been avoided if qualification

levels of each type of equipment had been clearly documented.

Identification of qualification levels would also help

prevent similar problems in the future when qualified equip-

ment is upgraded or replaced during the life of the plant.

(b)

Remove any information in the files that is not pertinent

to qualification. The inspectors found files which contained

information which was not needed to support qualification of

the equipment. In some cases several tests reports were

in a file and it was unclear to the inspectors which

report/reports were used by the licensee to qualify the

equipment.

In another case the licensee included data to

support qualification based on the

1110 degree C Rule

11 of

thermal aging when this data was not needed for qualifi-

cation. See additional discussions on the

11 10 degree C

rule

11 in paragraphs 4.A.,4.D.(4), and 4.D.(5).

(c) Clarify equipment operability times. Operability times were

identified on generic SCEW (system component evaluation work-

sheet) sheets in each file that covered all the equipment in

the file. This led to some problems when the inspectors

determined that some of the equipment actually had shorter

operability requirements due to the fact that the equipment

was submerged prior to re~ching the claimed operability ti~es.

While the licensee referenced, on the SCEW sheets, a sub-

mergence analysis for the equipment subject to submergence

and shorter than stated operability times, the inspectors

found the stated operability times on the SCEW sheets to be

misleading in some files.

9

(d)

Make sure SCEW sheets are accurate reflections of the

environments to which ~he equipment would be exposed

during a design basis accident (DBA).

In two cases the

licensee claimed qualification of equipment to peak

temperatures of 347 degrees F from a high energy line

break (HELB).

When the inspectors questioned the quali-

fication temperatures, th~ licensee determined that the

equipment was only exposed to loss of cooling accident

(LOCA) peak temperatures of 260 degrees F and was qualified

for that temperature.

(e)

Include discussions in qualification documentation which

addresses how functional performance of cable (particu-

larly insulation resistance for instrumentation cable)

is ensured.

The licensee

1s approach is to specify

performance requirements (including minimum insulation

resistance requirements) in procurement documents and

obtain certificates of compliance from the cable vendors.

This methodology should be discussed in qualification

documentation so that there is documented evidence that

cable function performance requirements have been addressed

when cable qualification is established.

(f) Make .corrections to.files to reflect minor documentation

discrepancies identified to the licensee during the

inspection.

The licensee was able to address the inspectors concerns regarding

the files based on the personal knowledge of the licensee

1s EQ

personnel.

However, the inspectors considered the recommendations

appropriate to ensure that during future EQ activities during the

life of the plant, licensee personnel will be able to understand

the basis for qualification of the equipment.

(2)

Rockbestos Cable, Files EQ-08 and EQ-32

(a)

When the NRC inspectors initially reviewed file EQ-08 for

ethylene propylene rubber (EPR) cable, qualification was

based on Franklin Test Report FC3798 and Rockbestos Test

Reports 7801 and 1804. Since these reports are subject to

the concerns identified in IE Information Notice (IN) 84-44

on Rockbestos cable, the inspectors questioned the licensee

as to whether or not he had taken any of the possible

corrective actions discussed in the IN. The licensee was

unable to provide any documented evidence that he had

undertaken any of the discussed actions; however, during

the inspection the licensee added Wyle Laboratories

Qualification Test Report 17722-2 to the file. This Wyle

report established qualification of the EPR cable for its

application at Salem.

10

(b)

When the inspectors initially reviewed file EQ-32 for

coaxial cable the file contained Rockbestos Qualification

Report, dated March 15, 1979, which is also subject to the

concerns of IN 84-44. Again the licensee was unable to

provide the inspectors with documented evidence that any of

the corrective actions of the IN were taken. Prior to the

end of the inspection, the licensee added Rockbestos

Qualification Report QR 6802 for

11 LE

11 coaxial cable and a

similarity analysis to demonstrate the similarity of the

tested "LE" cable to the installed

11L0

11 (foam dielectric)

cable to the file. This report and the similarity analysis

demonstrated qualification of the installed

11L0

11 coaxial

cable for its application at Salem.

Even though the licensee was able to establish qualification of

the EPR and coaxial cables prior to the end of the inspection,

the qualification files as presented to the inspectors did not

support qualification of the cables, since the licensee was not

able to provide documented evidence that adequate corrective

action had been taken with regard to IN 84-44.

The reports upon

which qualification was initially based were not adequate to

establish qualification.

Failure to establish qualification of

the Rockbestos EPR and coaxial cables is identified as a

Potential Enforcement/Unresolved Item (50-272/86-23-03; 50-311/

86-23-03).

(3)

Limitorgue Motor Valve Operators, File EQ-51:

The inspectors' review of file EQ-51 for Limitorque motor valve

operators determined that operators were installed in inside

containment applications without gear case grease relief valves.

This is contrary to the information provided in paragraph 6~0

"Design Life" of the basic Limitorque Qualification Report,

80058, dated January 11, 1980.

Paragraph 6.0 states that grease

relief valves are used to accommodate the extreme temperatures

and pressures of containment OBA environments.

The inspectors

questioned the licensee concerning his justification for not

using the grease relief valves and the licensee did not have any

documented analysis for not using the valve when questioned.

Based on the concerns raised by the inspectors and prior to the

end of the inspection, the licensee documented his position as

to why the inside containment operators were considered qualified

without the relief valves.

The inspectors' review of this justi-

fication determined that it was adequate to establish qualification

of the installed configuration of the operators.

Since there was no documented justification in the file for

installing the inside containment operators in a configuration

different than the qualified configuration when the file was

initially reviewed, this is identified as a Potential Enforcement/

Unresolved Item (50-272/86-23-04; 50-311/86-23-04).

11

(4)

Exo Sensors Hydrogen Analyzer, File EQ-38:

The inspectors' review of file EQ-38 for Exo Sensors hydrogen

analyzers determined that the qualification test profile for

OBA conditions did not envelope plant conditions (test 300

degrees F, plant 347 degrees F).

The licensee had included an

analysis using the 10 degree C rule to show thermal equivalence;

however, the inspectors found this method of resolving the

profile differences unacceptable.

Upon questioning by the

inspectors, the licensee determined that the analyzers were

only needed for LOCA accident conditions which had peak temper-

atures of 260 degrees F; therefore, the analyzers' test profile

enveloped its plant profile for DBA environments at Salem.

The

inspectors recommended that the file be changed to reflect the

LOCA requirement.

The inspectors also identified concerns with regard to the quali-

fied life of components in the analyzers.

The qualification file

indicated that the pressure transducers and resistance temperature

detectors (RTOs) used in the analyzers should be replaced every

two years; however, Field D"ir1~ci111! ~~ .. c*-t~lC-CFD-0328-RO for

hydrogen analyzer maintenance requires replacement of the trans-

ducers and RTDs every ten years. During the inspection the

licensee was unable to provide documentation supporting a ten

year qualified li Fe for *:tu~ prE!S5.ure transducers and RTDs.

Following the inspection, the licensee provided summary test data

from Exo Sensors, Inc. to the NRC which claimed a qualified life

of 19.2 years for the transducers and the RTOs.

Since the licensee's documentation was not in agreement with

regard to the qualified lifes for pressure tranducers and RTDs

used in the hydrogen analyzers and the licensee did not have

documentation during the inspection to support the replacement

schedule (qualified life) contained in the field directive for

hydrogen analyzer maintenance, this failure to support a

qualified life for the transducers and RTOs is identified as a

Potential Enforcement/Unresolved Item (50-272/86-23-05;

50-311/86-23-05).

(5)

ASCO Solenoid Valves, File EQ-42:

The inspectors reviewed file EQ-42 for ASCO models 206-380,

206-381, 206-832, 208-266, 208-448, 210-036, NP8314, NP8316,

NP8320, and NP8323 solenoid valves. This review identified

some confusion regarding post-accident operating times in the

licenseels documentation.

The file SCEW sheet indicated that

the required post-accident operating time had been revised

from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 120 days; however, the qualified operating time

on the SCEW sheet was 30 days.

Qualification documentation (QD) analysis 1 in the file documented

that the valves could be qualified for 120 days using the 10

degree C rule (this method is not considered acceptable unless

12

it is demonstrated to be more conservative than Arrhenius method-

ology).

QD analysis 2 using Arrhenius methodology documented

that the valves were qualified for 100 days.

QD analysis 3 using

Arrhenius methodology documented that the valves were qualified

for greater than 119 days.

Since none of these documents demon-

strated, by an acceptable means, that the qualified valve operat-

ing times enveloped the required 120 day post-accident operating

time, this item is identified as a Potential Enforcement/Unresolved

Item (50-272/86-23-06; 50-311/86-23-06).

(6)

BIW Coaxial Cable, File EQ-27:

When the inspectors reviewed the file EQ-27 for cross-linked

polyethylene (XLPE) insulated/hypalon jacketed coaxial cable,

qualification was claimed for a HELB OBA environment with a

maximum temperature of 347 degrees F. The inspectors were able

to find only one page of data in the file which documented

testing which would support qualification for an HELB environment.

This page of data was a summary of a proprietary Franklin test

report, documenting testing of the BIW cable.

When the

inspectors questioned the adequacy of the one page summary to

meet the documentation requirements of NUREG 0588, the licensee

determined that the BIW coaxial cable was only used in the

Victoreen radiation monitoring system and was subject only to a

LOCA accident environment with maximum temperatures of 260

degrees F.

The file contained a BIW test report, 8912, to

support qualification to the LOCA environments.

The inspectors

review of this report determined that test parameters enveloped

plant requirements; however, the report did not provide informa-

tion on cable IR values during the accident testing. The

inspectors recommended that the licensee obtain IR data obtained

during the testing to assure that the licensee's minimum speci-

fication values for cable !Rs (see discussion in paragraph

4.0.(l)(e)) were met.

The inspectors also recommended that the

file be changed to reflect that qualification is established

for LOCA environmental conditions.

The obtaining of cable IR

data during accident testing and the changing of *the file to

reflect qualification to LOCA environments is identified as ar.

Open Item (50-272/86-23-07; 50-311/86-23-07) which will be

reviewed during a future NRC inspection.

(7)

Conax Electrical Conductor Seal Assemblies (ECSAs), File EQ-22:

File EQ-22 for Conax ECSAs stated that the tested equipment was

not identical to the installed equipment and there was no analysis

demonstrating why the tests on the tested equipment were applicable

for supporting qualification of the installed equipment.

The

licensee provided the inspectors with a report from Conax whic~

documented the similarity of the materials of the tested and

installed ECSAs.

The inspectors* review of the similarity report

and other documentation in the file determined that qualification

of the ECSAs at Salem was supported; however, the inspectors

recommended that the similarity report be included in the quali-

fication file.

The licensee also should make appropriate correc-

13

tions to the file to demonstrate equipment similarity. Inclusion

of the Conax report and related corrections in the file is

identified as an Open Item (50-272/86-23-08; 50-311/86-23-08)

which will be reviewed during a future NRC inspection.

(8)

IE Information Notices and Bulletins:

The NRC inspectors reviewed and evaluated the licensee's

activities related to the review of EQ-related INs and Bulletins.

The inspectors* review included examination of Commitment

Management procedure VPL-LEP-03, revision 1, and procedure

GM8-EMP-008, revision O.

The commitment management procedure

describes the requirements and responsibilities for ensuring

compliance and systematic tracking of commitments to regulatory

agencies and to ensure that the commitments are met in a

responsive and timely manner.

Sources of commitments include

responses to NRC inspection reports and responses to NRC Bulletins/

Circulars/INs/Generic Letters. Procedure GM8-EMP-008 establishes

the methods used by the Nuclear Engineering Department (NED) to

coordinate the review of NRC documents.

The inspectors reviewed

seven INs and one Bulletin as part of the review of the licensee's

system.

Other INs and Bulletins were reviewed as part of the

inspectors* individual file review.

The inspectors* system review

determined that the licensee has a system for review and tracking

of INs/Bulletins relative to qualified equipment and that they

are addressed in appropriate equipment files. The only concern

associated with the handling of INs/Bulletins identified during

the inspection pertained to the licensee's resolution of IN 84-44,

Rockbestos cable (see paragraph 4.D.(2)).

E.

Plant Physical Inspection

The plant physical inspection consisted of the examination of eight types

of safety-related equipment located outside containment on either/or both

Units 1 and 2.

Since both units were operating the day of the physical

inspection, examination of inside containment equipment was not possible.

The inspectors examined characteristics such as mounting configuration,

orientation, interfaces, model number, environment, and physical

condition.

(1)

During the physical inspection, the inspectors identified electric

wiring splices in outside containment Limitorque valve operators

1SJ67 and 1CS16.

The licensee had no documentation to support

qualification of these splices nor were these splices included on

the EQML for either unit. These splices were identified to the

inspectors as Scotch 70 or construction splices and the licensee

stated that they were probably used in most of the operators

located outside containment.

Prior to the end of the inspection,

the licensee provided the inspectors with a summary of a test of

similar splices written for the Surry Nuclear Operating Station.

During the afternoon of August 15, 1986, following the inspection

exit meeting, the licensee provided the inspectors from Region I

with a complete copy of the test report conducted for Surry. This

14

.~.

report was reviewed by the NRC following the inspection, and was

considered adequate to support qualification of the splices.

However,

in order to establish qualification of the splices for Salem applica-

tion, the licensee must include the report in a qualification file and

evaluate the report for its applicability to Salem environments.

This

failure to establish qualification of these splices and include them

on the EQML is identified as a Potential Enforcement/Unresolved Item

(50-272/86-23-09; 50-311/86-23-09).

(2)

During the inspection the inspectors identified that Rosemount flow

transmitter 2FT-128 was installed on a pipe support with U-bolts to

fasten the transmitter in place.

Rosemount instruction manual for

1153 transmitters (section on mechanical installation) states: "the

transmitter was seismically qualified with the bracket mounted using

4 each 3/8 inch diameter bolts." It also states:

11 if the transmitter

is *mounted to a nonrigid panel the user must ensure that seismic

input to the mounting bracket does not exceed qualification levels

given in paragraph 7.2 of Rosemount Report No. 08400102.

Engineering justification for the U-bolt and seismi.c input to mounting

bracket was not available for this inspection. This observation is

not within the.scope of 10 CFR 50.49; however, it is of concern to

the NRC from the standpoint of seismic qualification and is identified

as a Potential _Enforcement/Unresolved Item (50-311/86-23-10).

(3)

In addition to the items discussed above, the observations discussed

below were made during the plant walkdown.

These observations are

provided for the licensee's information and action as determined

appropriate.

(a)

Evidence of grease weapage around the gease seals of the

limit/torque switches of Limitorque motor operators 11RH4,

11CC16, 1CS16, and 1SJ67.

The evidence consisted of the

observation of a thin film of oil/grease on the inside wall*

of the limit/torque switch compartments of the operators .

. (b)

External inspection of Limitorque valve operator 11SJ33

revealed possible seal leakage by the presence of oil/

grease on the external surface of the limit/torque

switch cover. This is of particular significance since

the operator is oriented such that the switch compartment

is down and directly below the gear case of

the operator.

15