Responds to NRC Questions Re Implementation of Safety Parameter Display Sys (SPDS) Per Suppl 1 to NUREG-0737. Proposed Milestone Implementation Schedule from Revised.Spds Contract to Be Awarded in Sept 1983
ML18089A310
Person / Time
Site: Salem  
Issue date: 08/18/1983
From: Liden E
Public Service Enterprise Group
To: Varga S
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 NUDOCS 8308240237
Download: ML18089A310 (2)


Text

Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department August 18, 1983 Director of Nuclear Reactor Regulation

u. s. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20014 Attention:

Mr. Steven A. Varga, Chief Operating Reactors Branch 1 Division of Licensing Gentlemen:

REQUIREMENTS FOR EMERGENCY RESPONSE CAPABILITY SUPPLEMENT 1 TO NUREG 0737 REVISED INTEGRATED SCHEDULE NO. 1 AND 2 UNITS SALEM GENERATING STATION DOCKET NOS. 50-272 AND 50-311 In response to questions raised by your staff regarding implementation of the Safety Parameter Display System (SPDS),

PSE&G has revised the proposed milestone implementation schedule transmitted by our letter of June 1, 1983.

As indicated on the attached implementation schedule, the SPDS contract will be awarded in September 1983.

Subsequently, with vendor input we will establish an implementation schedule for SPDS installation and project completion.

This revised schedule will be provided by December 1983.

Should you have any questions, please do not hesitate to contact us.

8808240237 a3681s PDR ADOCK 05000272 F

PDR Attachment CC:

Mr. Donald C. Fischer Licensing Project Manager Mr. Leif Norrholm Senior Resident Inspector The Energy People Very truly yours, EA~/~

E. A. Liden Manager -

Nuclear Licensing and Regulation 95-2168(80M)11-82

.... _.... ~..

(

MILESTONE IMPLEMENTATION SCHEDULE I.

SAFETY PARAMETER DISPLAY SYSTEM (SPDS)

a.

Award vendor contract

b.

Submit SAR

c.

SPDS installation complete

d.

Operator training complete

e.

SPDS operable II.

DETAILED CONTROL ROOM DESIGN REVIEW (CRDR)

a.

Submit CRDR Program Plan

b.

Submit Summary Report III.

REGULATORY GUIDE 1.97

a.

Complete installation on Unit l

b.

Complete installation on Unit 2 IV.

EMERGENCY OPERATING PROCEDURES (EOPs)

a.

Submit generic technical guidelines

b.

Submit Procedures Generation Package

c.

Begin Operator Training (without SPDS)

d.

Implement EOPs without SPDS

e.

Implement EOPs with SPDS V.

EMERGENCY RESPONSE FACILITIES (ERFs)

a.
b.
c.
d.
e.
f.

Complete Operational Support Center (OSC)

Complete Emergency Operations Facility (EOF)

(without SPDS)

Select Technical Support Center (TSC) Contractor Complete TSC structural modifications Complete SPDS installation ERF project complete 9/83 1/84 Complete 12/83 Complete 12/83 Complete Complete 9/83 9/84 Complete Complete 9/83 1/84

  • Dates are to be developed with SPDS vendor input and will be provided by December 1983.