Forwards 830414 & 26 Ltrs Documenting Review of Corrective Action Program Re 830222 & 25 Reactor Trip Breaker Failures. Ltrs Previously Transmitted at 830414 & 26 Meetings
ML18087A876
Person / Time
Site: Salem PSEG icon.png
Issue date: 04/27/1983
From: Uderitz R
Public Service Enterprise Group
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML18087A877 List:
References
NUDOCS 8305020150
Download: ML18087A876 (2)


Text

,.....--------------------------------------- ----*-*---

Richard A. Uderitz Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 935-6010 Vice President -

Nuclear April 27, 1983 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. Darrell G. Eisenhut, Director qivision of Licensing Gentlemen:

BETA CORPORATION REPORTS REACTOR TRIP BREAKER FAILURES SALEM GENERATING STATION UNITS NO. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 PSE&G hereby transmits copies of the April 14 and 26, 1983 letters from BETA Corporation,.. which document the.ir review of PSE&G's Corrective Action Program related to the February 22 and 25, 1983 reactor trip breaker failures.

These letters have been previous-ly'.t'ransmitted at meetings with the NRC staff on April 14 and *26;,.l983.

Sincerely, CC:

Mr. Richard w. Starostecki, Director Division of Project and Resident Programs Region I Mr. Leif Norrholm NRC Senior Resident Inspector 8305020150 830427 PDR ADOCll\\ 05000272 S

PDR

BASIC 9 ENERGY TECHNOLOGY ASSOCIATES, INC.

Mr. Richard M. Eckert, Chairman Public Service Electric & Gas Company 80 Park Place Newark, New Jersey 07101

Dear Mr. Eckert:

ROSSLYN CENTER. SUITE 825 1700 N. MOORE STREET ARLINGTON. VIRGINIA 22209 I 703) 243-4600 April 14, 1983 In accordance with your request of April 5, 1983, BETA began an independent review of the adequacy of the actions being taken by PSE&G as a result of the recent reactor breaker trip incidents at the Salem Generating Station.

We* have completed the preliminary phase of this review and, as you directed, we are attaching herewith our report covering the work performed to date.

We intend to continue our review of the adequacy of the long term actions and will provide you a report upon completion of that effort.

Attachment Sincerely, (J.!J_r-.

W. Wegn Associa