Advises That 6 & 9-month Responses for Info Re Control of Heavy Loads Will Not Be Provided within Identified Time Period,Per 801222 Request.Requests Extension Until 811030 & 820226 for 6 & 9-month Responses,Respectively
ML18086A865
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/05/1981
From: Mittl R
Public Service Enterprise Group
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0612, RTR-NUREG-612 NUDOCS 8108140266
Download: ML18086A865 (1)


Text

0 PS~G Public Service Electric and Gas Company 80 Park Plaza, T160 Newark, N.J. 07101 201/430-8217 Robert L. Mitt!

General Manager - Licensing and Environment Director of Nuclear Reactor Regulation

.U.S. Nuclear Regulatory Commission Washington, DC 20555 August 5, 1981 ATTN:

Mr. Darrell G. Eisenhut, Director Division of Licensing Gentlemen:

NUREG-0612 CONTROL OF HEAVY LOADS NO. 1 AND 2 UNITS SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-272 AND 50-311 In your December 22, 1980 letter on the above subject, you required a six and nine month response for information on "Control of Heavy Loads" at Salem Nuclear Generating Station.

In keeping with the last paragraph on page 2 of that letter, we request an extension for those submittals.

The requested extension dates are October 30, 1981 and February 26, 1982 for the six and nine month responses, respectively.

Due to the allocation of resources and the extensive amount of information requested by NUREG-0612, we find ourselves unable to provide this infor-mation in the identified time frame.

To further enable us to meet this requirement, PSE&G has employed a consultant to assist in the collection and preparation of the requested responses.

Should you have any questions in this regard, do not hesitate to contact us.

Very truly yours, CC Mr. Leif Norrholm Senior Resident Inspector (f L H~if?.~uy