Forwards IE Insp Rept 50-311/81-02 on 810113-16.No Noncompliance Noted
ML18085B146
Person / Time
Site: Salem 
Issue date: 02/09/1981
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18085B147 List:
References
NUDOCS 8104060154
Download: ML18085B146 (2)


See also: IR 05000311/1981002

Text

. UNITED ST ATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

B fEB 198.i

Docket No. 50-311

Public Service Electric and Gas Company

ATTN:

Mr. F. W. Schneider

Vice President - Production

80 Park Plaza - ISA

Newark, New Jersey 07101

Gentlemen:

Subject:

Inspection 50-311/81-02

This refers to the routine inspection conducted by Dr. L. H. Bettenhausen of

this office on January 13-16, 1981 at Salem Unit 2, Hancock's Bridge, New Jersey

of activities authorized by NRC License No. DPR-75 and to the discussions of our

findings held by Dr. Bettenhausen with Mr. Driscoll of your staff at the conclu-

sion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspec-

tion report will be placed in the NRC 1s Public Document Room.

If this report

contains any information that you (or your contractor) believe to be proprietary,

it is necessary that you make a written application within 20 days to this

office to withhold such information from public disclosure.

Any such application

must be accompanied by an affidavit executed by the owner of the information,

which identifies the document or part sought to be withheld, and which contains

a statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

Sl0.4060 \\ S~

' .

9

FEB 1981

No reply to this letter is required; however, if you have any questions concern-

ing this inspection, we will be pleased to discuss them with you.

Sincerely,

dl~

§146~ J. Brunner, Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-311/81-02

cc w/encl:

J. T. Boettger, General Manager, Corporate Quality Assurance

E. N. Schwalje, Manager - Quality Assurance

R. L. Mittl, General Manager - Licensing and Environment

H. J. Midura, Manager - Salem Generating Station

R. A. Uderitz, General Manager - Nuclear Production