UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

JAN 2 1 1981

Docket Nos.

50-272*

50-311

Public Service Electric and Gas Company

ATTN:

Mr. F. W. Schneider

Vice President.- Production

80 Park Plaza - 15A

Newark, New Jersey

07101

Gentlemen:

Subject:

Combined Inspection 50-272/80-32 and 50-311/80-22

This refers to the routine inspection conducted by Mr. L. J. Norrholm of this

office on November 16, 1980 - December 31, 1980 at Salem Nuclear Generating

Station, Units 1 and 2 of activities authorized by NRC License Nos. DPR -70

and DPR-75 and to the discussions of our findings held by Mr. L. Norrholm with

Mr. H. Midura of your staff at the conclusion of the inspection *

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's "Rules of Practice,

11 Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC 1s Public Document Room.

If this

report contains any infonnation that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20

days to this office to withhold such information from public disclosure. Any

such application must be accompanied by an affidavit executed by the owner of

the information, which identifies the document or part sought to be withheld,

and which contains a statement of reasons which addresses with specificity the

items which will be considered by the Commission as listed in subparagraph (b)

(4) of Section 2.790. The infonnation sought to be withheld shall be incor-

porated as far as possible into a separate part of the affidavit. If we do

not hear from you in this regard within the specified period, the report will

be placed in the Public Document Room *

810819.0 ?~'5

___ .d,

\\

Public Service Electric and Gas Company

JAN 2 1 1981

2

No reply to this letter is required; however, if you should have any questions

concerning this inspection, we will .be pleased to.discuss them with.you.

Enclosure:

Sincerely,

/iJ~~n~r~ Chief -

Rea tor Operations and.Nuclear

, upport Branch

1. Combined Office of Inspection and Enforcement Inspection Report Numbers

50-272/80-32 and 50-311/80-22

cc w/encl:

J. T. Boettger, General Manager - Corporate Quality Assurance

R. L. Mittl, General Manager - Licensing and Environment

H. J. Midura, Manager - Salem Generating Station

R. A. Uderitz, General Manager - Nuclear Production