Corrected Startup Test Power Coefficients for Cycle 2 Reload Originally Submitted 790803
ML18079A793
Person / Time
Site: Salem PSEG icon.png
Issue date: 08/08/1979
From:
Public Service Enterprise Group
To:
Shared Package
ML18079A792 List:
References
NUDOCS 7908140419
Download: ML18079A793 (1)


Text

Startup Test Program Description Salem Unit 1 Cycle 2 Test Power Coefficient Initial Conditions:

Reactor power is not changing.

The Xenon concentration is within 3% of its equilibrium value.

This test is run twice during the startup program.

First at 50% power, then at 100%.

Test

Description:

Take a heat balance.

Change turbine power be-tween 2% and 4% with the control rods in manual.

The Tavg andilT recorders will monitor changes in these parameters as a function of time.

Acceptance Criteria:

Design:

Design value ~ 30%

FSAR/T.S.

Must fall between upper and lower curve assumed in FSAR accident analysis.